MidSTAR-1 USNA / STP Bi-Weekly IPT 2 November 2006. USNA Small Satellite Program. Prof Billy Smith, Director, USNA SSP 1Lt. Justin Hinman , STP Mission Manager Mr. Riaz Musani , Aerospace Corporation. Status Board. Spacecraft complete Environmental testing complete Bakeout underway.
E N D
MidSTAR-1 USNA / STP Bi-Weekly IPT 2 November 2006 USNA Small Satellite Program Prof Billy Smith, Director, USNA SSP 1Lt. Justin Hinman, STP Mission Manager Mr. Riaz Musani, Aerospace Corporation
Status Board • Spacecraft complete • Environmental testing complete • Bakeout underway
Schedule (rev. 11/02/06) • Week of: • 6 Nov: Closeout open MSPSP items; conclude bakeout • 13 Nov: Pre-ship review (16 Nov) • 26 Nov: Deliver to Cape • 4 Dec: Integrate onto IPS
Programmatics • Requirements Verification: • MS-1-RV-2: Closed • Mass model: • MS-1-RV-10: Closed • MS-1-RV-11: Closed • MS-1-RV-12: Closed