Advanced Preempted Crossings – A Case Study Tim Oster Railroad Project Manager

Advanced Preempted Crossings – A Case Study Tim Oster Railroad Project Manager City of Fort Worth Mid-States Highway-Rail Grade Crossing Safety Conference May 19-21, 2008 Grapevine, Texas. Fort Worth Railroad Saftey Program Background. There are 193 grade crossings in the city.

tress
Download Presentation

Advanced Preempted Crossings – A Case Study Tim Oster Railroad Project Manager

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Advanced Preempted Crossings – A Case Study Tim Oster Railroad Project Manager City of Fort Worth Mid-States Highway-Rail Grade Crossing Safety Conference May 19-21, 2008 Grapevine, Texas

  2. Fort Worth Railroad Saftey Program Background • There are 193 grade crossings in the city • Fort Worth RR Safety Program: • RR signal upgrades • Quiet Zone Program • Crossing Surface Improvement Program • Planning & coordination of major projects : • Tower 55 • New commuter rail, etc.

  3. Fort Worth Railroad Saftey Program Background • TxDOT Stop and Yield Sign Pilot Program • Development Standards near Railroads • Signs and Pavement Markings Program • Portable Railroad Monitoring System • Traffic Signal Preemption Program

  4. When it comes to preemption

  5. Things are not always as they appear!

  6. FORT WORTH PREEMPTION PROGRAM Phase 1 – General Field Investigation Phase 2 – Detailed Field Investigation & Evaluation Phase 3 – Final Report and Recommendations Phase 4 – Develop City Policy, Training & Inspection Program Phase 5 – System Upgrade, Standardization, and Modernization

  7. PHASE 1 GOALS • Verify List of Preempted Locations • Gather Original Design Data • Inspect and Field Test Preemption • Verify Field Settings match Design

  8. PHASE I – RESULTSVERIFY LIST OF PREEMPTED LOCATIONS 18 Preempted Crossings • Represents 10% of railroad crossings and 2.5% of Traffic Signals in City • 15 Existing Locations Preempted • 3 Scheduled For Installation • 3 Simultaneous Preemption • Two New Locations Identified

  9. PHASE I – RESULTSGATHER ORIGINAL DESIGN INFORMATION 1. City Railroad Files 2. Traffic Signal Timing Sheets 3. TxDOT Files 4. Railroad Front Sheets/Design 5. Design Material from Cabinets

  10. PHASE I – RESULTSINSPECT AND FIELD TEST PREEMPTION • Created Simple Inspection Form • 6 of 12 Advance Preemption Sites required adjustments. • One Constant Warning Time Adjustment • Two Track Clearance Green Adjustments • Three Locations not working at all

  11. Location #1 Bad Relay Location #2 Bad AC Isolator Card

  12. Location #3 Traffic Signal Controller Installed 1995 Pull Box Railroad Controller Installed 1999

  13. PULL BOX 2007 What we have here is a failure to COMMUNICATE! City Preemption Cable Railroad Preemption Cable

  14. PHASE 2 GOALS DETAILED FIELD INSPECTIONS • Obtain Additional Expertise • Develop Detailed Inspection Form • Perform Joint Inspections • Demonstrate All Preempted Crossings Operating per Original Design

  15. Max Train Spd = 20MPH ADT +18,000 Advanced Preemption Warning Time Required: TxDOT Design = 22 sec Railroad Design = 18 sec Railroad HXP3 = 14 sec

  16. Max Train Spd = 40MPH ADT +45,000 Design: WT = 25 sec APT = 23 sec DAX = 48 sec HXP3 Settings: WT = 30 sec DAX = 31 sec Equals 1 sec APT TRAIN TEST REQUIRED!

  17. PHASE 2 – RESULTSJOINT INSPECTIONS • ALL 18 Preempted Locations operating per the original design • Using the TxDOT form only 2 Locations need additional time if FDW terminated • All Simultaneous Crossings are scheduled for upgrade • Two new locations on 2008 TxDOT Program

  18. PHASE 1 & 2 OBSERVATIONS • Original Design Data Unavailable • Track Clearance Greens too short • Loop Detectors not working • Driver Hesitation during Track Clearance Green at location with Permissive Left Turn movements • Railroad Warning Time not set Correctly • Approach Lengths not Programmed Correctly • Railroad Plans Missing or Conflicting • City Signal Maintainers Unfamiliar with Preemption Settings • Railroad Maintainers Unfamiliar with Preemption Settings • Regular Joint Testing (annually) on one Railroad

  19. PHASE 3 – FINAL REPORT • Prepare Overview of Preemption Program • Summary of Preemption Parameters and Recommended Practices • Evaluate each crossing using TxDOT Preemption Form • Summary of Recommended Improvements for each Location

  20. PHASE 4 – Policy, Training, and Inspection • Develop City Policy for preempted crossings • Minimum Green Time and Calculation Method • FDW Time and Calculation Method • Track Clearance Green Times • Elimination of Yellow Trap • Use of Right Turn Restrictions Signs During Preemption

  21. PHASE 4 – Policy, Training, and Inspection • Training and Inspection • Develop Training Program and Material • Provide Training for City Traffic Signal Employees and Railroad Employees (Jointly) • Develop Preemption Inspection Form • Develop Regularly Scheduled Joint Inspection Program

  22. PHASE 5 – FUTURE UPDATES • Standardize Traffic Controllers at each site • Railroad modifications for additional advanced preemption time • Intersection and/or traffic signal modifications to eliminate yellow trap • Provide communications to all preempted locations • Provide live video at all preempted locations • Provide alarms, email, or text messaging for notification of issues at each crossing • Provide battery back-up

  23. MAINTENANCE ISSUES Traffic Signal Maintainer’s Trouble Report: Preemption was on. Found Preemption switch in test position. Turned it OFF. WORKING FINE.

  24. Do you have Preemption? The appearance of preemption? or

  25. Railroad Program • Website Items: • RR Program Overview • Guideline for Project Selection • QZ Establishment Process • Sample NOI & NOE • For more info:www.fortworthgov.org

  26. Tim Oster Railroad Project Manager City of Fort Worth 817.392.6798 tim.oster@fortworthgov.org