An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IPA Adriatic Crossborder Cooperation 2007 -2013 • EUROPE -ADRIATIC SEA-WAY • EA SEA-WAY • Regulation of the coastal zone • in the port Ston – upgrade coast • Shkoder, 4. march 2015

  2. 2

  3. Achieved: Spatial plan – coastprovided for thereconstruction - build 2. ObtainedLocationpermits 3. Obtained Building permits Openedconstructionworksite Financing plan • Google prevoditelj iz prve ruke – Google prevoditelj

  4. The total valueprojectinvestment: 10.500.000,00 kuna (acc. 1.370.000,00 €) Sourcesoffunding Dubrovnik neretvaregionandproject EA Sea-Way – 2.500.000,00 kuna (acc. 327.000,00 €) Municipality Ston – 2.000.000,00 kuna (acc. 261.000,00 €) Dubrovnik neretvaCountyand Port authorityof Dubrovnik Neretva region – 2.000.000,00 kuna (acc. 261.000,00 €) Ministryofmaritimeaffairs, transport andinfrastructure – 4.000.000,00 kuna (acc. 521.000,00) Public tender : expectedinmarch 2015 (allphases)

  5. Expected completion of the investment: November 2015. (complete – all phases) Results of investment: Cultural heritage preservation Incresing number of visitors The possibility of developing futher projects Project contain waste disposal, oil separators etc. Project also included green areas

  6. Thank you for your attention! 5away.eu DUBROVNIK NERETVA COUNTY FB 4 Shkoder, 04. march 2015