1 / 12

CMS RPC Endcap RE1 Status Report

CMS RPC Endcap RE1 Status Report. Schedule V34.1. April 05. Sep 05. 2004 Milestones 3 RE1/2 & 1 RE1/3 pre production chambers tested Korean gaps deliveries ISR Assembly Lab on schedule CSC+RPC+LB Beam Tests Cosmic QC 20 RE1/2 +10 RE1/3. 2005 Milestones Production

thu
Download Presentation

CMS RPC Endcap RE1 Status Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CMS RPC Endcap RE1 Status Report Schedule V34.1 April 05 Sep 05 • 2004 Milestones • 3 RE1/2 & 1 RE1/3 pre production chambers tested • Korean gaps deliveries • ISR Assembly Lab on schedule • CSC+RPC+LB Beam Tests • Cosmic QC 20 RE1/2+10 RE1/3 • 2005 Milestones • Production • 18 RE1/2 and 18 RE1/3 Installation April end • 60 RE1/2 & 60 RE1/3 • Installation October-November • Cosmic Tests / Magnet Test Preparation On behalf of Peking University Colleagues And all at ISR

  2. Dec. 2004 HV connector Last step Cosmic stand and DAQ RE1/2 Completed chambers ready for quality control tests in the cosmic stand

  3. Production Status: 20 RE1/2 + 30 RE1/3 Assembled Preparation gas pipes – 120 chambers Cables – 60 chambers Mechanics .. Cover closing Alu plates Chamber production rate Expected 5 per week March 20 RE1/2 mass production re-launch GOAL: June RE1/2 complete April end RE1/3 Gaps expected mass production re-launch GOAL: Sept 30 RE1/2 complete 36 needed @ X5 April 2005 Chambers Planned Constructed GOAL: Dec 05 All certified!

  4. Database developed to store RPC production information http://forwardrpc/cms_forward_rpc/production_db/Main_db.htm

  5. Create plots from cosmic test data Strip response profile

  6. Cosmic QCSee Andrey’s talk % HV 9.2kV mA Noise < 10Hz/cm2

  7. Chamber QC 4 Checklists At different stages of production Cosmic Tests : Andrey Waiting for Final Destination: Point 5

  8. Barrel and Forward (Endcap) RPC’s Configuration and Condition database requirements for CMS Core DB Team Document history - Following DB Workshop Jan 24-28

  9. Schema for RPC Barrel and Endcap See Marcello’s talk – DB meeting Wednesday 16 at 8.30

  10. Magnet Tests SX5 Cables & Services horizontal distances inside SX5 18m Counting House (see next page) HB HB 10m 10m 15m 49m YE+2 YE+2 YE+2 YE+1 20m magnet test position YE1 6 RE1/2 Chambers (One sector 60o) 6 Link Boards available

  11. SX5 Cable Paths to be defined horizontal distances Counting House only runcontrol DAQ detectors 8m magnet 15m Counting House The Green Barrack

  12. Mass production gas gaps Korea full steam Assembly RE 1 ramped up @ ISR lab and has reached 5 chambers per week The final RE 1/2 RPC has been mated to ME 1/2 RE1/3 installation exercise performed Preparation for magnet tests started Summary and Conclusions RE 1 production expects to meet the CMS master schedule for its installation and commissioning

More Related