An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Coherent X-ray ImagingWBS 1.3 Paul Montanez CXI Lead Engineer/CAM April 21, 2009

  2. Outline • WBS 1.3 Scope • Early Science/CD-4 Deliverables • Progress since CD-2 • Status • Engineering/Design Status • Cost & Schedule Performance • Critical Path • Milestones • Risk Identification & Mitigation • Safety • Summary

  3. WBS 1.3 – Early Science/CD-4 Deliverables Early Science: Early Finish – April 2011 (B/L Early Finish – May 2011) CD-4: Early Finish – January 2012 (B/L Early Finish – November 2011)

  4. Progress Since CD-2 Vertical/Horizontal PSD, 1-100Hz Measured near location of 1µm KB system • CXI Engineering/Design staff • Added 1 Mechanical Engineer & 1 Mechanical Designer – October 2008 • Added 2 Mechanical Engineers & 1 Mechanical Designer – March 2009 • All documentation completed & released • PRDs, ESDs, SOW’s, etc. • 1µm Kirkpatrick-Baez mirror system • Authorization to proceed with advanced procurement • Mirror system RFP released, proposals received and vendor selection made • Vendor site-visits made • Award in May 2009 • Design Reviews • Preliminary Design Reviews completed • CXI 1µm Sample Chamber – March 2009 • CXI Reference Laser – March 2009 • CXI Detector Stage & 1µm Precision Instrument Stand – prior to FIDR in June 2009 • Baseline vibration data obtained in the LCLS Far Experimental Hall

  5. Engineering/Design Status Optics & Diagnostics Diagnostics & Wavefront Monitor 1 micron Sample Environment 0.1 micron KB & Sample Environment, Particle Injector and IToF 1 micron KB Reference Laser CXI Early Science CXI CD-4 • CXI Engineering/Design staff • Armin Busse, Kay Fox, William Olson, Donald Schafer, Nathaniel Stewart, Paul Montanez

  6. Engineering/Design Status (2) • Documentation • CAD system model documentation hierarchy (CAD Drawing Tree/File Structure) released • XRT/FEH H5 beamline layout complete with all available models implemented & updated • 26 PRDs/ESDs released, 10 SOWs/ICDs released • Hutch Design • Reviewed 30%, 60%, 90% & 100% A&E drawings • FEH Hutch construction – June thru December 2009 (LCLS) • APP and Risk Identification/Registry complete and up to date

  7. Engineering/Design Status (3) • CXI Reference Laser (WBS 1.3.03.1) • PRD & ESD released • Successful PDR held March 2009 • Design Review Report TR-391-003-19-0 • Consider Class 2, 1mW, green laser (currently Class 3R, red) • Appropriate signage for laser safety • Additional interlocks for equipment protection • FDR scheduled for April 2009 • Start fabrication drawings • No significant design/cost changes since CD-2 • Use mechanical designs for the vacuum chamber and 6-DOF alignment stage that have previously sustained reviews • Leveraging existing designs (when applicable) reduces our overall engineering/design effort. Additionally, helps to ensure commonality within the LUSI instruments • Budget at Completion (BAC) ≈ $126K

  8. Engineering/Design Status (4) • CXI 1µm KB system (WBS 1.3.02.02) • PRD, ESD & SOWs released • Prime vendor to provide complete and integrated KB system, including: • Figured & Polished Substrates • Mirror Mechanics/Manipulators • Vacuum chamber/equipment and support stand • MOU for independent metrology/coating of the substrates • LLNL likely due to past experience with LCLS mirrors • Secured the services of an optics expert to assist with the evaluation of all procurement documents and to participate as a member of the Proposal Evaluation Committee • Procurement Activities • Advance Procurement Review – October 2008 (required for advanced procurement authorization) • Design Review Report TR-391-003-10 “CXI 1 Micron K-B Mirror System Advanced Procurement Technical Review” • Vendor site-visits by CXI staff – Q1 FY09 • Prequalification of vendors – December 2008/January 2009 • Posted on Federal Business Opportunities (FedBizOpps) website • RFP sent to vendors – January 2009 • Vendor proposals received – 24 March 2009 • Proposal Evaluation Committee Meeting – 9 April 2009 • Recommend a vendor to the Source Selection Official • Award in May 2009 • Delivery September 2010 • Budget at Completion (BAC) ≈ $1,280K ($970,000 in long lead procurement) • CXI 0.1µm KB system (WBS 1.3.02.01) • PRD, ESD & SOWs released • Procurement included as an “option” for the CXI 1µm KB contract • Delivery October 2010 • Budget at Completion (BAC) ≈ $1,400K

  9. Engineering/Design Status (5) • Particle Injector (WBS 1.3.04.01) • PRD & ESD released • Existing Injector design from LLNL • CXI will advance the current design • Optimization of particle beam throughput • Remote operation of equipment • SLAC/LLNL Memorandum of Understanding (MOU) signed-off February 2009 • “Collaboration on the sample particle injector for the Coherent X-ray Imagining (CXI) instrument” • generation or exchange of research and test results, data, and know-how • fabrication or exchange of equipment • financial or other contributions to activities being undertaken • exchange of personnel • Physics Level of Effort (LOE) began upon MOU sign-off, engineering to follow as required • PDR scheduled for September 2009 • Budget at Completion (BAC)≈ $1,470K

  10. Engineering/Design Status (6) • CXI Precision Instrument Stands (WBS 1.3.05.01.02) • 1µm Precision Instrument Stand • PRD & ESD released • Support /Interface with 1µm Sample Chamber and Detector Stage (in all experimental configurations) • Engineering/Design effort, beyond conceptual design, begun in March 2009 • PDR currently scheduled for mid-June 2009, need to advance this to May to support Final Instrument Design Review (FIDR) • Budget at Completion (BAC) ≈ $240K • 0.1µm Precision Instrument Stand • PRD & ESD released • Support 0.1µm Sample Chamber, Detector Stage and 0.1µm KB System • PDR scheduled for April 2010 • Budget at Completion (BAC) ≈ $330K

  11. Engineering/Design Status (7) • CXI Sample Chambers (WBS 1.3.05.01.01) • 1µm Sample Chamber • PRD & ESD released • Successful PDR held March 2009 • Design Review Report TR-391-003-20-0 • Currently addressing PDR “Action Items” • Piezo stage vibration/stability due to stack-up • Equipment protection for in-vacuum stages (potential for clashing) • FDR “Early Finish” scheduled for September 2009 • FDR will be accelerated • Budget at Completion (BAC) ≈ $620K • 0.1µm Sample Chamber • PRD & ESD released • PDR scheduled for March 2010 • Chamber proper will likely be an integral part of the 0.1µm KB vacuum chamber • Budget at Completion (BAC) ≈ $500K

  12. Engineering/Design Status (8) Detector Stage (WBS 1.3.05.01.03) • PRD, ESD, SOWs & ICDs released • Cornell detector mechanical design progressing • SLAC PPA mechanical engineering completing design for a variable aperture detector • Complete assembly by September 2009 to meet LCLS CD-4 • Purchase order placed in March 2009 with a local design firm for the mechanical design and drafting of the CXI Detector Stage – CXI was resource limited • Move design forward in the schedule • Vendor design reviews • PDR – April 2009 • FDR – May 2009 • Budget at Completion (BAC)≈$330K

  13. Engineering/Design Status (9) B4C “throttles” • CXI Hutch Facilities (WBS 1.3.06.01 & 1.3.06.02) • Hutch layout design • Raised flooring • Storage cabinets, work benches and tool chests • Utilities distribution • Budget at Completion (BAC)≈$350K • CXI Vacuum System (WBS 1.3.07.01 & 1.3.07.02) • Requirements • In general, beamline vacuum better than 10-7 Torr • Better than 10-9 Torr for KB Systems – isolation/differential pumping from HV required • Preliminary design of a compact, 2 stage, differential pump system complete – optimization of the throttle inner diameter in progress • Vacuum equipment: pumps, valves, gauges, etc. • Bellows and Spools • Use LCLS support stands where applicable (diagnostics supports/beampipe supports) to leverage existing engineering/design effort • PDRs • Vacuum Equipment – April 2009 • Vacuum Supports – October 2009 • Budget at Completion (BAC)≈$700K

  14. Engineering/Design Status (10) • Installation (WBS 1.3.08.01) • LUSI Installation Coordinator • Obtain required installation permits • Conduct daily tailgate meeting w/ UTR (University Technical Representative) • Conduit to engineering for field installation issues • Provide installation status for incorporation into LUSI schedule • CXI has a “phased installation” • Early Science • Diagnostics/Common Optics • Reference Laser • 1µm Sample Chamber & Precision Instrument Stand • 1µm KB System • Detector Stage • Vacuum • Equipment/Hardware/Supports • Early Finish – April 2011 • CD-4 • Diagnostics/Common Optics • 0.1µm Sample Chamber & Precision Instrument Stand • 0.1µm KB System • Particle Injector/IToF • Vacuum • Equipment/Hardware/Supports • Early Finish – January 2012

  15. Cost & Schedule Performance Month end February 2009 cumulative cost variance(+) Engineering/Design ≈ 40% of total CXI budget All labor ≈ 55% of total CXI budget Month end February 2009 cumulative schedule variance(-)

  16. Cost and Schedule Performance (2) SPA Chart Cumulative data through Feb 2009 CPI = 1.11 (BCWP/ACWP) SPI = 0.95 (BCWP/BCWS)

  17. CXI Critical Path KB Mirror AWARD & Vendor Design • Critical path (thru 1µm KB System) has 20d of schedule contingency KB Mirror Design/Fabrication Effort Post Vendor Effort and Installation KB Mirror Installation Effort

  18. CXI Milestones FY08 FY09 FY11 FY10 Preliminary Design Reviews • Reference Laser – March 2009 • 1 micron Sample Chamber – March 2009 • Detector Stage – May 2009 • 1 micron Instrument Stand – June 2009 • Particle Injector – September 2009 • 1 micron KB System – September 2009 • 0.1 micron System – January 2010 • Ion TOF – May 2010 CXI Advanced Procurement Review – November 2008 Final Instrument Design Review – July 2009 Final Design Reviews • Reference Laser – April 2009 • Detector Stage – September 2009 • 1 micron Sample Chamber – September 2009 • 1 micron Instrument Stand – September 2009 • Particle Injector – January 2010 • 1 micron KB System – December 2009 • 0.1 micron System – May 2010 • Ion TOF – June 2010 Project Ready for CD-3 - July 2009 Award PO • 1 micron KB System – May 2009 • 0.1 micron System – June 2009 • 1 micron Sample Chamber – January 2010 • Detector Stage – January 2010 • 1 micron Precision Instrument Stand – January 2010 Receive • 1 micron Sample Chamber – April 2010 • 1 micron Precision Instrument Stand – May 2010 • Detector Stage – July 2010 • 1 micron KB System – September 2010 • 0.1 micron System – October 2010 Early Science Installation Complete - April 2011 All dates are early finish

  19. CXI Milestones (2) • L2: DOE Site Office Authority (COMPLETE/APPROVED) • L3: Interface Milestones/Major Events • L4: Systems (COMP/RCV) • L6: Commitments/Awards (AWARD) • Significant recent & near-term CXI Instrument milestones • Current schedule (February data) vs. CD-2 approved schedule (October 2008) • Desired to move FIDR to June 2009 so that subsequent activities allow for the CD-3 Review to occur in June 2009

  20. CXI Milestones (3) • Six month “look-ahead” of CXI Instrument milestones • Current schedule vs. CD-2 approved dates (October 2008) • 8 Preliminary Design Reviews (PDR) • Including 2 Vendor PDRs (KBs) • 6 Final Design Reviews (FDR) • 2 Vendor Contract Awards (KBs) • 2 PDRs completed to-date • CXI Reference Laser • CXI 1µm Sample Chamber • 2 additional PDRs will be completed prior to FIDR • CXI Detector Stage • CXI 1.0µm Prec. Inst. Stand

  21. Risk Identification & Mitigation • Risk Identification/Registry complete and up to date as per “LCLS Risk Management Plan” PMD 1.1-002-r4 • 3 (of 17) risks retired prior to CD-2 • 7 (of 17) risks retired since CD-2 • KB Mirror Systems • Vendor can’t meet 0.1µm mirror specifications – Technical • Vendor can’t meet 1µm mirror specifications – Technical • No vendor willing to bid on 1µm mirrors – Technical & Schedule • No vendor willing to bid on 1µm mirror mechanical system – Technical & Schedule • No resident experience designing mirror mechanical system – Technical & Schedule • Sample Chamber • Custom stages for Sample Chambers cannot be made – Technical & Schedule • Cornell detector • Last minute changes to detector design – Technical & Schedule • Outstanding risks relate to • Procurement – Addressed in Management breakout session • Delivered mirror systems not meeting specifications • 45˚ KB configuration • Particle injector • Interfaces with adjacent beamlines • Custom linear stage for CXI Detector Stage

  22. Safety • LUSI Hazard Analysis Report (PM-391-001-34) complete • Safety issues are considered at every stage of the design, fabrication and installation process • Safety considerations (some examples) • Ionizing Radiation • Hutch walls will comply with SLAC Radiation Safety memo RP-RPG-080606-MEM-01 • Hutch PPS • Pressure/Vacuum Vessel Safety • Compliant with 10CFR851 • Seismic Safety • Designs compliant with: Seismic Design Specification for Buildings, Structures, Equipment, and Systems, SLAC-I-720-0A24E-002-R002 • Mechanical • Interlocks for equipment protection • Engineered solutions that prevent potential “pinch-points” with moving machinery • Hoisting and Rigging • Positioning of devices that require use of the FEH H5 overhead crane shall be performed only by qualified personnel with an approved lift plan. • Laser Safety • CXI Reference Laser, Class 3R, 2.5mW • Appropriate signage

  23. Summary • CXI designs are mature and concepts are based on proven developments made at FLASH and SR sources • CXI scope is stable and has not changed since CD-2 • Long Lead Procurement • Committee evaluation of vendor proposals for the 1µm KB system occurred on April 9, 2009 and a procurement recommendation forwarded to the Source Selection Official – award contract in May 2009 • 0.1µm KB system is an “option” included in the 1µm KB system RFP • Critical Path schedule contingency is reasonable (20d) for total schedule duration • Most major risks associated with the KB mirror systems have been retired • Remaining KB risks will be addressed during design/manufacture and testing • FIDR is planned for June 2009 in support of CD-3 review in July 2009 • Re-baseline of WBS 1.3 (CXI) due to ARRA funding in progress • CXI is on track to support an accelerated schedule

  24. Supporting Slides

  25. Cost & Schedule Performance • CXI month end February data • BCWS • BCWP • ACWP • SPI • CPI

  26. Cost & Schedule Performance – WBS 1.3

  27. Cost & Schedule Performance – WBS 1.3

  28. Expanded CSSR – by CAM

  29. Control Accounts & Work Packages – by WBS L2

  30. Control Accounts & Work Packages – by CAM

  31. P3 Files & Total Activities – by CAM

  32. P3 Files Milestones – by WBS L2

  33. Labor/Non-labor Split – WBS 1.3

  34. Split by Phase – WBS 1.3

  35. Procurements and Dollars – WBS