This document provides a comprehensive review of the implementation of the Mahatma Gandhi National Rural Employment Guarantee Scheme (MGNREGS) in Purba Medinipur District as of June 2010. It discusses the establishment of Programme Management Units, availability of vetted estimates, and the necessity of maintaining records and conducting audits. Key issues include timely measurement engagement, preparation of labor budgets, execution of schemes during monsoon, and the completion of social audits. The review aims to highlight challenges and suggest improvements for better employment and fund management.
E N D
REVIEW ON MGNREGS IMPLEMENTATION JUNE, 2010 DISTRICT ‘MGNREGS’ CELL PURBA MEDINIPUR
ISSUES FOR DISCUSSION • Establishment of Programme Management Unit & dedicated working space & facilities(G.O. No. 6253 dated 16/09/2009). • Availability of GP-wise vetted estimates to combat any event of unemployment allowance during monsoon. • Ensure maintenance of Scheme Register/Asset Register • Arrangement for timely measurement – engage GRS as per G.O. No. 2746 dated 23/04/2010
ISSUES FOR DISCUSSION • Preparation of labour budget by November 2010 & audit reply for 2008-2009 • Schemes identified for execution during monsoon season (Social forestry/nursery/plantation/river bank protection etc.) • Identification of habitation to be connected with all weather roads
Audit of MGNREGS Fund • Para wise reply from GP/PS(PIA) against the audit report for 2008-09 not received only from Sutahata and Patashpur-I Block.
Conduct of Social Audit • Complete conduct of social audit immediately, if not done within 30/06/2010. Upload findings of social audit in MGNREGA website within 15/07/2010. Only Nandakumar and Ramnagar-I uploaded one report each.
POINTS TO REMEMBER • Inspection for all schemes taken up from 2010-11 plan • Improve quality of asset creation • Maintenance of books of accounts • Disposal of complaints • Estimates become as high as 2.5 times from the approved plan, example - Moyna • Requisition forms are not filled in properly • Too many schemes implemented by GP at a particular period of time-compromising in quality
Blockwise creation of Woman Persondays as a percentage of total persondays as on 07.07.2010
Blockwise creation of SC persondays as a percentage of total persondays as on 07.07.2010
Blockwise creation of ST persondays as a percentage of total persondays as on 07.07.2010
GP WISE PERSONDAYS GENERATED(as on 07.07.2010)(BLOCK: TAMLUK) District Avg.- 3747.34Sub-Division Avg.-3714.08 , Block Avg.-3799.67
GP WISE PERSONDAYS GENERATED(as on 07.07.2010) (BLOCK: SAHID MATANGINI) District Avg.- 3747.34Sub-Division Avg.-3714.08 , Block Avg.-4902.5
GP WISE PERSONDAYS GENERATED(as on 07.07.2010) (BLOCK: PANSKURA - I) District Avg.- 3747.34Sub-Division Avg.-3714.08 , Block Avg.-2867.29
GP WISE PERSONDAYS GENERATED(as on 07.07.2010) (BLOCK: NANDAKUMAR) District Avg.- 3747.34Sub-Division Avg.-3714.08 , Block Avg.-1382.00
GP WISE PERSONDAYS GENERATED(as on 07.07.2010) (BLOCK: MOYNA) District Avg.- 3747.34Sub-Division Avg.-3714.08 , Block Avg.-4257.55
GP WISE PERSONDAYS GENERATED(as on 07.07.2010) (BLOCK: KOLAGHAT) District Avg.- 3747.34Sub-Division Avg.-3714.08 , Block Avg.- 4482.69
GP WISE PERSONDAYS GENERATED(as on 07.07.2010) (BLOCK: CHANDIPUR) District Avg.- 3747.34Sub-Division Avg.-3714.08 , Block Avg.-4306.90
Blockwise Expenditure on Water conservation and water harvesting (digging of new tanks/ponds percolation tanks, small check dams etc to be indicated separately) (Sector-2) as per percentage of total expenditure upto JUNE, 2010
Blockwise Expenditure on Drought proofing (afforestation and tree plantation and other activities to be indicated separately)(Sector-3) as per percentage of total expenditure upto JUNE, 2010
Blockwise Expenditure on Micro irrigation works (minor irrigation canals and other activities to be indicated separately) (Sector-5) as per percentage of total expenditure upto JUNE, 2010
Blockwise Expenditure on Provision of irrigation facility,horticulture & plantation to land owned by : (scheduled castes and scheduled tribes, beneficiaries of land reforms and beneficiaries of IndraAwasYojana ) (Sector-8) as per percentage of total expenditure upto JUNE , 2010
Blockwise Expenditure on Renovation of traditional water bodies (desalting of tanks/ ponds, desolating of old canals, desolating of traditional open well etc. to be indicated separately) (Sector-7) as per percentage of total expenditure upto JUNE, , 2010
Blockwise Expenditure on Land development(plantation, land leveling other activities to be indicated separately)(Sector-6) as per percentage of total expenditure upto JUNE, 2010
Blockwise Expenditure on Flood control and protection (drainage in water logged areas, construction and repair of embankment to be indicated separately) (Sector-4) as per percentage of total expenditure upto JUNE, 2010
Blockwise Expenditure on Rural connectivity(Sector-1) as per percentage of total expenditure upto JUNE, 2010