williamstown fire department fire station feasibility study 2008 2013 n.
Download
Skip this Video
Loading SlideShow in 5 Seconds..
Williamstown Fire Department Fire Station Feasibility Study 2008 - 2013 PowerPoint Presentation
Download Presentation
Williamstown Fire Department Fire Station Feasibility Study 2008 - 2013

Loading in 2 Seconds...

play fullscreen
1 / 24

Williamstown Fire Department Fire Station Feasibility Study 2008 - 2013 - PowerPoint PPT Presentation


  • 123 Views
  • Uploaded on

Williamstown Fire Department Fire Station Feasibility Study 2008 - 2013 . Existing Station. Location 34 Water Street Built 1950 Extended the building front forward 15’ in 1990 4325 Sq ft 1 story building 1/3 Acre site River bank on one side Masonry walls Wood framed roof.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

Williamstown Fire Department Fire Station Feasibility Study 2008 - 2013


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
existing station
Existing Station
  • Location 34 Water Street
    • Built 1950
    • Extended the building front forward 15’ in 1990
    • 4325 Sqft 1 story building
    • 1/3 Acre site
    • River bank on one side
    • Masonry walls
    • Wood framed roof
apparatus bay
Apparatus Bay
  • Existing
    • 2,422 sq. ft.
    • 3 bays wide
    • 2 Overhead doors: 1 -10’ x 11’& 1- 20’ x 11’
    • 4 trucks total =1,320 sq. ft.
    • Other miscellaneous equipment
existing conditions
Existing Conditions
  • Can’t open doors

Tight quarters

Isle Obstructions

Firefighter to close to Trucks

existing spaces
Existing Spaces

Training

Meeting Space

Kitchen

Office

space needs program outlined by mcguire group 2008
Space Needs ProgramOutlined By McGuire Group2008
  • Staffing and Parking
  • Space Allocations
  • Apparatus and Support
  • Public Lobby/Dispatch
  • Administration
  • Firefighters Headquarters
  • Indoor Training
  • Building Support and Mechanical
operational issues
Operational Issues
  • Overhead doors too narrow and too low
  • Apparatus bays too narrow and too low
  • Administrative spaces inadequate
  • No Day Room for firefighters
  • Air-Pak filling station in apparatus bay is a hazard
  • No Decontamination area for Gear and Equipment
  • Male/ Female Shower rooms non-existent
  • Kitchen is too small for current staff
space deficiencies
Space Deficiencies
  • Only one office
  • No room for new construction print review
  • No office for Asst. Chief’s / Training , Pre- Planning fires, Truck & Equipment maintenance records
  • No area for code enforcement information
  • Not adequate space for firefighters
    • Locker room
    • Shower room
apparatus bay comparison
Apparatus Bay Comparison

Williamstown FD Existing

2242 Sq./Ft

Modern Fire Station

6100 Sq./Ft

apparatus bay space needs
Apparatus Bay Space Needs

Williamstown FD Existing

Modern Fire Station

administrative space
Administrative Space

Present Conference Rm

Present Office

Modern

Modern

training
Training

Modern

Existing

apparatus
Apparatus

Williamstown 1975

Williamstown 2012

size comparison
Size Comparison

Existing

Station

thank you
Thank You

Anytime

Anywhere

Anything

We’ll Be There!

Any Questions?