1 / 7

PIP- Booster RF

PIP- Booster RF. Spare c avity s tatus and tuner update 9/28/11 M . Slabaugh. Spare Booster RF Cavity. Cavity assembly was on hold for several weeks due to safety concerns (grinding on copper ) Resume welding on 9-29 Vendor having problems brazing ceramics, will use older ones on hand

tea
Download Presentation

PIP- Booster RF

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PIP- Booster RF Spare cavity status and tuner update 9/28/11 M. Slabaugh

  2. Spare Booster RF Cavity • Cavity assembly was on hold for several weeks due to safety concerns (grinding on copper) • Resume welding on 9-29 • Vendor having problems brazing ceramics, will use older ones on hand • Best case estimate, end of October • Realistically, hope to have before the holidays…

  3. Spare Booster RF Cavity • Cavity testing • Temperature spike on wide-bore cavity due to bad contact in the tuner stem. Did not flag at normal operating parameters! • Begs question??? “Acceptable” may no longer work! • Already know we have to re-work some cooling

  4. Booster RF Tuner model and drawings

  5. Booster RF Manpower and Schedule Manpower and discussion points • AD/MSD has provided two techniciansfor full-time RF/tuner work • TD is supplying one technician to help (and learn) build tuners • All three technicians are in training • Current MSD schedule (D. Augustine) is estimating about 5 weeks (25 days) to remove/rebuild/re-install one cavity • Not counting in schedule 10 tuners from TD budgeted for FY12. If available, these would help.

  6. Schedule- rebuilding tuners 9 cavities = 228 days (6/21/12 - 6/5/13)

  7. Schedule- procurement new tuners Ferrites delivered Sept. 2012

More Related