The Sprint#1 Group Gamma summary highlights good team cooperation and time estimation, incorporating tests, reviews, and documentation. Challenges included a lengthy initiation phase and a lack of regular Scrum meetings. Progress tracking revealed a velocity of 98 hours, with 93.5 completed story points and 12 open story points. The sprint featured tasks like unit testing workshops, code reviews, and user contact establishment.
E N D
Personal Training Assistant – Sprint#1 Group Gamma
Sprint# 1 - Summary + good, cooperative team work + good time estimation + tests, reviews and documentations included - long initiation phase (backlog planning) - too few regular Scrum-meetings - tracking work progress
Sprint# 1 • 22-02-2012 – 14-03-2012, 22 days • Velocity (hours) = 98 • Completed story points (hours) = 93.5 • Open story points (hours) = 12 • Besides user stories’ tasks • Workshop on Unit-Testing • Code reviews • Documentation • Establishing user contacts
User stories • As an athlete, I want to make my heart rate available online. • As a trainer, I want to see athletes' heart rates live. • As an athlete, I want to store personal data related to exercises on my phone.