Finland’s experience in implementing and applying the Espoo Convention

Finland’s experience in implementing and applying the Espoo Convention . Seija Rantakallio Councellor Moscow, 21 September. Espoon Convention. Finland ratified 1995 Agreement has entered into force 1997

swann
Download Presentation

Finland’s experience in implementing and applying the Espoo Convention

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Finland’s experience in implementing and applying the Espoo Convention Seija Rantakallio Councellor Moscow, 21 September

  2. Espoon Convention • Finland ratified 1995 • Agreement has entered into force 1997 • Party to the Convention can participate into other Party’s environmental impact assessment procedure (EIA) • Finland-Estonia bilateral EIA-agreement 2002 • Application of Convention between Finland and Estonia • Negotiations on bilateral EIA agreement with Russian Federation in 1990s

  3. Party of Origin Affected Party Party in two different rolesMinistry of the Environment is the competent authority of Espoo Convention Finland Finland Likely significant adverse transboundary environmental impact Party Party

  4. Finland as a Party of Origin • Finland • Sends a notification to potentially affected party about the project and its environmental impact • Sends EIA documentation on transboundary impact to affected party and gives a possibility for consultations • Gives a possibility to affected party’s public and authorities to participate in the Finnish EIA –similar opportunities as nationally • Takes the comments from affected party into account in the national EIA • Sends final decision

  5. Espoo procedure when Party of Origin Notification Affected Party Point of Contact for notification Finland Point of Contact for notification Ministry of the Environment EIA programme Comments For comments EIA documenta-tion Comments Final decision

  6. PoO -notification phase • Includes e.g. • what impacts are expected in the affected party • planned studies to assess likely transboundary environmental impact in the affected party • relevant parts of programme in affected party’s language EIA programme =Scoping document

  7. EIA notification phase and Espoo Convention Developer EIA competent authority Point of Contact for Espoo Ministry of the Environment Affected Parties Submits info to MoE Announcement Public hearing Notification EIA programme Answer on participation and comments on programme Gives statement on adequacy of programme Submits answers to EIA competent authority Takes into consideration when drafting the EIA report (documentation)

  8. PoO –EIA documentation phase Includes e.g. -likely transboundary environmental impact in affected party -given comments on the programme taken into account -translation of relevat parts in the affected party’s language EIA documentation

  9. Finland as Affected Party Notification Ministry of the Environment -announcement in newspaper -press release -documents for public display and for comments…in Finnish and in Swedish -request for statements and opinions from authorities and NGOs -answer to PoO (willingness to participate on EIA, comments on the adequacy of EIA) EIA documentation

  10. Agreement on practical arrangements for Espoo procedure between points of contact Finland Point of Contact for notification Ministry of the Environment Affected Party Point of Contact for notification -inform about timing of notification and documentation and dead line for answer -agree on timing and ways of public participation -translation of documents Early contacts

  11. Application of Espoo in Finland • Party of Origin and Affected Party several times • Ongoing processes and more expected • PoO: -two new nuclear power plant units -> neighbours + Baltic Sea subregion • AP: -Ignalina nuclear power plant, Lithuania -Narva power plant, Estonia -Offshore wind farm, Estonia -Offshore wind farm, Sweden • PoO+AP -Nord Stream gas pipeline

  12. Cooperation between Finland and Russian Federation under Espoo Convention • Finland has notified Russia • Imatra power plant 1996 • Final disposal of used nuclear fuel 1998 • New nuclear power plant unit to Loviisa 1998 • Waste water treatment plant in Lappeenranta 2006 • Nord Stream gas pipeline 2006 • New nuclear power plant unit to Olkiluoto 2007 • New nuclear power plant unit to Loviisa 2007 • Russia has notified Finland • Ust-Luga multipurpose harbour terminal 2003 • Nord Stream gas pipeline 2006 • How to treat projects with likely significant transboundary impact in the future?