AGS RSVP Weekly Meeting 27 Jan 2005

AGS RSVP Weekly Meeting 27 Jan 2005. Agenda LOG Review Preliminary Recommendations (pile) New Guidance from the RSVP Project Office Cost reduction, first pass (Brown, Pendzick, Pearson, Phillips). Useful Links: RSVP Project : http://rsvp.bnl.gov

Download Presentation

AGS RSVP Weekly Meeting 27 Jan 2005

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AGS RSVP Weekly Meeting27 Jan 2005 Agenda • LOG Review Preliminary Recommendations (pile) • New Guidance from the RSVP Project Office • Cost reduction, first pass (Brown, Pendzick, Pearson, Phillips) • Useful Links: • RSVP Project: http://rsvp.bnl.gov • C-AD AGS Project: Office http://www.c-ad.bnl.gov/esfd/RSVP/RSVP_AGS_WBS.htm

  2. 18-20 Jan 05 LOG ReviewClose Out - Recommendations • AGS Project and MECO magnets cost and contingency well understood, all else not so well developed. Contingency adjustment recommended for all else. • RSVP management structure good but management should implement economy of scale and use common resources where possible. Examine streamlining and/or consolidation of project offices. It was noted there are now 5 project offices, two main office (Columbia and BNL), AGS, K0PIO and MECO. • RSVP is ready for technical design phase once funds become available. Recommend RSVP create TDR's and bottoms-up RLS's fully linked to the RSVP WBS structure ASAP.

  3. 24 Jan Meeting with NSF • Bill and Jon met with the NSF on 24 Jan • They have not yet received substantive feedback • they will let us know if/when that changes

  4. RSVP Project Office – New Guidance(quote from 25 Jan email from Kotcher) “RSVP is under extreme pressure to baseline in the spring. Under this kind of time constraint, with quite possibly the continuation of the project in the balance, many of the normal, more time-intensive means of communicating will have to take a back seat in the interest of trying to get things converge on this time scale. I hope all of you will make an effort to see past whatever minor perturbations this may introduce in appreciation of the bigger picture; I will nonetheless do what I can to keep things moving as smoothly as possible.”

  5. RSVP Project Office – New Guidance (cont’) All projects have been asked to design to cost, according to the following guidelines (burdened FY05$): • KOPIO - 55M • MECO magnet - 56M • MECO - 24M • AGS - 40M • Project Office - 20M • These numbers include contingency, which should be constructed according to the Lockheed guidelines as posted on the RSVP web site. • The Project Office will make any needed adjustments in the overall contingency. • The RSVP Project Office is assembling an April Baseline Review. • The usual backup material - cost books, C/TDR's, etc. - will be needed to review. • Project costs will have to be reported in escalated dollars

  6. RSVP Project Office – New Guidance (cont’) • “In light of this priority, the coming review schedule according to the Sep timeline will be changed in order to allow time for you to put all of this together.” • In particular, we will not have the reviews of the individual sub- projects via the ad hoc LOG committees. • An updated review schedule will be ready in a few days • “you should be entirely focused on constructing a "baselineable" project plan” • “To the very greatest extent possible, project personnel should drop everything during this intensive period”

  7. Misc • RSVP Project Office Account Number: 88542 • The K0PI0 funds have arrived, accounts are being setup • CFI work ($120K) • AGS upgrades work ($145,049) • K0PI0 Beam Lines ($285,928) • USE These accounts to charge your time!

  8. next significant events – TO BE UPDATED!!!

  9. Next Meeting • 3 Feb 2005 • Agenda • Cost reduction exercise – second pass (Mahler,Pendzick,Pearson,Phillips) • Status of cost scrubbing and RLS’s (Mahler/Lambiase,Pendzick,Pearson,Phillips)