An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Transit & Growth Management Tara Bartee –FDOT Public Transit Office

  2. Presentation Overview • Transit Basics • Proportionate Fair-Share Equation • Examples

  3. Why Growth Management? To try to manage sprawl

  4. What works where • Cost of Transit • Transit is flexible

  5. Automobile Space

  6. Person (automobile) Space

  7. Pedestrian / Bicycle Space

  8. Person/Bus Space

  9. What is Transit-Oriented Development? What is TOD? Comp Plan Language • Define the 3Ds Design Density Diversity

  10. Definition • “Transit-Oriented Development (TOD) is moderate to higher-densitydevelopment, located within an easy walk of a major transit stop, generally with a mix of residential, employment and shopping opportunities designed for pedestrians without excluding the auto. TOD can be new construction or redevelopment of one or more buildings whose design and orientation facilitate transit use.” Design Density Caltrans Diversity

  11. What is a transit-oriented development? Design for people

  12. Density

  13. TOD is development that: Diversity Retail Office Residential • Contains a rich mix of uses – retail, residential, workplaces. • Has appropriate treatment of parking. Diversity

  14. Outcome One encourages TOD at the station One separates the station from the community

  15. Fronton in Miami • Land use doesn’t support transit • I’ve got the map

  16. Denver, CO Neighborhood to Urban TOD Neighborhood Urban

  17. Where money is spent to improve mobility Shelters Bus Priority Signal & Intersection Improvements

  18. Transit Development Plan (TDP) • Look at: • Specific requirement to look at goals and policies of the comp plan and LRTP. • Public Involvement • Adopted by Governing bodies (county commission) • 10 year needs plan • Financially feasible to 3 years CIE FLUM Transportation Element TDP LRTP

  19. Roadway improvement can be isolated to the “significantly” impacted area Transit costs can’t be limited to one hour a day and .74 miles Calculating the Costs Transit and roadways are different … O H, R E A L L Y ? ? ? ?

  20. Transit Prop Share Number of Project Trips Cost = Proportionate Share Change in Peak Hour Max Service Volume

  21. Proposed Methodology – Project Trips Number of Project Trips Cost = Proportionate Share Change in Peak Hour Max Service Volume 10 project trips = 10 needed seats/passengers on a bus

  22. Proposed Methodology – Change in Max Service Volume Number of Project Trips Cost = Proportionate Share Change in Peak Hour Max Service Volume • Typical value of 40 seats per bus • Fundamental Assumption: Providing capacity on transit satisfies identified roadway capacity issue • Does not address issue of use/ridership of service

  23. 3 years when TQOS A or B, 5 years when TQOS C or D, 7 years E or F or new service Capital Investments Technology Implementation Operating and maintenance Proposed Methodology - Cost Number of Project Trips Cost = Proportionate Share Change in Peak Hour Max Service Volume Time (years) (Capital + Operating) $ = Cost Transit Corridor Study Average Cost/Revenue Hour

  24. Proposed Methodology - Cost Initial Assumption: Entire length of transit route (sum of both directions) included in cost calculation

  25. Example Applications

  26. Small Development • Development adding 50 new peak hour trips to one segment of a constrained four-lane facility in urban area Development on ‘Failing’ Facility

  27. Small Development • Agency agreement that no roadway capacity projects are planned or could reasonably be constructed • Existing transit service on Main Street = LOS B • 10 minute headways, 6 buses per hour • Cost per operating hour = $75 • Length of existing bus route = 10 miles (20 miles round trip)

  28. 520 peak hours . year number of peak hours . year Duration of Funding (yrs) Sample Calculation Small Development 50 passengers_ peak hour 1.25 = bus _ peak hour 40 passengers_ bus IMPROVEMENT COST cost . hour = cost . hour = $75 3 years

  29. Sample Calculation Small Development 50 passengers_ peak hour 1.25 = bus _ peak hour 40 passengers_ bus

  30. Medium Development • Development adding peak hour trips to several segments of a constrained six-lane facility in suburban area Development on ‘Failing’ Facility

  31. Medium Development (Your turn) • Development adding peak hour trips to several segments of a constrained six-lane facility in suburban area Development on ‘Failing’ Facility

  32. Medium Development Development on ‘Failing’ Facility • Agency agreement that no roadway capacity projects could reasonably be constructed • Existing transit service on SR X = LOS D • Length of existing bus route = 10 miles (20 miles round trip) Local government and transit agency review site plan and negotiate so that TOD principles are included.

  33. Sample Calculation Medium Development

  34. Sample Calculation Medium Development

  35. Large Development Development on ‘Failing’ Facilities • Development adding peak hour trips to several segments of a constrained six-lane facility, segments of a constrained four-lane facility, and segments to an unconstrained facility

  36. Large Development • Agency agreement that no roadway capacity projects could reasonably be constructed on constrained facilities (SR X) • Existing transit service on SR X = LOS D • Length of existing bus routes = 10 miles (20 miles round trip)

  37. Sample Calculation Large Development SR X

  38. Sample Calculation Large Development Jon Street

  39. Questions?