1 / 22

Risk Assessment Contingency Endgame

Risk Assessment Contingency Endgame. John N. Galayda – Director of LCLS Construction March 30, 2009. Risks. Technical Injector through undulator system, risks are understood and controlled Electron beam systems performing well X-Ray systems construction complete

Download Presentation

Risk Assessment Contingency Endgame

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Risk AssessmentContingencyEndgame John N. Galayda – Director of LCLS Construction March 30, 2009

  2. Risks • Technical • Injector through undulator system, risks are understood and controlled • Electron beam systems performing well • X-Ray systems construction complete • Thoroughly tested functionality prior to delivery • Risks associated with damage to optics • Attenuator, sacrificial test coupons, spare mirrors • Early & ongoing testing of B4C damage threshold

  3. Risks • Schedule • Attempting to advance the schedule for AMO experiments compared to baseline schedule • Accelerate commissioning of upstream hardware • Accelerate installation • Not a concern for CD-4 • Hutch construction schedule is on critical path to CD-4, with 108 days float to CD-4 • Space renovation schedule has less float, 83 days float to CD-4 • Schedule for contingency allocation • Get bids for space renovation by end of April

  4. Risks • Cost • Overruns late in the project • Perform a bottoms-up cost estimate on all remaining work (Nov08) • Perform monthly EAC and contingency analysis • FEE & AMO installation • Perform a readiness review • Monitor detailed installation planning schedule • Owner-directed changes (hutches) • Perform cost estimates at 30%, 60% & 90% • Design-to-cost A/E contract • Space renovation • Scope of re-habilitation of Bldgs 28 & 750 is controllable • GMAX for new space

  5. Risks • Cost • Change orders for TCCo subs are largely negotiated • $600K return on allowances • $200K unused field change order BA • Claims ($4.6M) still the biggest risk • Accruals for claims have been established and subjected to external review • Enact endgame plans for construction budget • Revise accruals when new information is obtained • FEH Hutches – Today’s presentation • Space renovation is last major CF cost driver

  6. Risks • Safety • New work planning process • LCLS personnel are experienced and well-trained • New civil construction contractors onsite • LCLS experience, lessons learned • X-ray commissioning • Readiness Process

  7. January Contingency Analysis

  8. Scope Restoration Candidates

  9. LCLS End-Game Timeline Design LCLS Office Space w/Options OPA Review (DC) Turner Punchlist Done CD-4 (7/31/2010) Turner Constr Comp Award LCLS Office Space now Construct LCLS Office Space A S O N D J F M A M J J A S O N D J F M A M J J 2008 2009 2010 ETC Complete w/SXR Construct H4 & H5 H4 & H5 BO 1st Light in FEH Design H4, H5 H6 X-Rays in NEH 1st Light in FEE Award H4 & H5 H6 TBD Timeline allows endgame scope decisions to be made sequentially. Final scope contingency (space renovation) includes options.

  10. Decision Timeline

  11. Normalized phase space centroid jitter after BC1 (~4% of rms beam size) RMS AyN = 3.4% RMS AxN = 3.9% Stability is not so far from the goal (~10%) 1-s beam size D. Ratner … near end of linac (10-15% of rms beam size) RMS AyN = 9% RMS AxN = 14% DE/E jitter  0.03% DQ/Q jitter  1.5% Q = 0.25 nC

  12. Measuring Bunch Arrival Time Jitter BPM Y Position (mm) TCAV OFF TCAV ON 9 mm rms 110 mm rms Dt±0.6 ps e- S-band (2856 MHz) BPM V(t) Q = 0.25 nC slope = -2.34 mm/deg Now measure BPM jitter both with transverse RF OFF, and then ON (at constant phase) Timing Jitter (w.r.t. RF) = (110 mm)/(2.34 mm/deg) = 0.047 deg  46 fsec rms

  13. Other Commissioning Results • Measured effect of vacuum chamber wake fields- good agreement with predictions

  14. Trajectory is Straight Enough for 1.5 Angstom

  15. Diagnostics Working Well • 3 nanoradian kick easily discerned • Submicron motion of electrons easily discerned

  16. Predicted X-Ray FEL power, computed from electron beam properties M. Xie method, with wakes FEL Power 3D Gain Length

  17. sz 1 mm ? LiTrack (no CSR) 8 kA? gex 0.4 mm at sz 1 mm Measurements and Simulations for 20-pC Bunch at 14 GeV Photo-diode signal on OTR screen after BC2 shows minimum compression at L2-linac phase of -34.5 deg. PRELIMINARY Y. Ding 1.5 Å, 3.61011 photons Ipk = 4.8 kA ge 0.4 µm Horizontal projected emittance measured at 10 GeV, after BC2, using 4 wire-scanners. LCLS FEL simulation at 1.5 Å based on measured injector beam and Elegant tracking,with CSR, at 20 pC.

  18. 20-pC Bunch at 4.3 GeV, 15 Angstrom Approaches a Longitudinally Coherent Single Spike z = 25 m (power profile at z = 25 m varies from shot to shot due to noisy startup) Y. Ding 15 Å, z = 25 m, 2.41011 photons, Ipk = 2.6 kA, ge 0.4 µm 1.2 fs LCLS FEL simulation at 15 Å based on measured injector beam and Elegant tracking,with CSR, at 20 pC.

More Related