Energy Flow on the 1385 Cable November 18, 2003 ISO-NE Markets Committee Dave LaPlante

Energy Flow on the 1385 Cable November 18, 2003 ISO-NE Markets Committee Dave LaPlante. Background. 1385 Cable is needed to support reliability in Southwest Connecticut, especially during construction of new transmission lines in the next 3 to 5 years.

sora
Download Presentation

Energy Flow on the 1385 Cable November 18, 2003 ISO-NE Markets Committee Dave LaPlante

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Energy Flow on the 1385 Cable November 18, 2003ISO-NE Markets CommitteeDave LaPlante

  2. Background • 1385 Cable is needed to support reliability in Southwest Connecticut, especially during construction of new transmission lines in the next 3 to 5 years. • Connecticut DEP has requested NU/LIPA submittal of plans for Replacement or Removal 1385 Cable by December 31, 2003. • Development of interim and end-state plans for ensuring efficient utilization of 1385 Cable is a key element in LIPA decision on Replacement/Removal of 1385 Cable. • Presentation describes proposal to more effectively use the 1385 cable and solicit market participant comment on the proposal

  3. Status of Scheduling on 1385 Cable • Current:1385 flow is zero unless emergency energy needed • End-State:Objective is a separate External Node for 1385 cable allowing Market Participant transactions. End state not likely to be completed until 2005. • To help support continued operation of the cable, an interim solution that flows energy over the cable has been developed • Proposed Interim solution: ISOs will control flow on 1385 in Real-Time to mitigate congestion in one ISO, so long as flow does not incur congestion or reliability concerns in the other ISO

  4. End State Objective • NYISO and ISO-NE support end state solution of a separate External Node representing the 1385 Cable • Separate External Node: • Allows Market Participants to request schedules specifically over this facility • Allows accurate pricing of energy over the facility • Would create a total of three NY/NE interfaces (CSC, 1385, NYN)

  5. End State Objective • Operational issues regarding interaction of the three interfaces and corresponding transfer limits must still be resolved • Level of effort has been evaluated by the ISOs • NYISO level of effort is significant; priorities indicate mid-late 2005 implementation • ISO-NE level of effort is medium; planning will occur to match NYISO implementation date

  6. Benefits of an Interim Solution • Uses the 1385 cable more efficiently • Provides benefits similar to a separate scheduling node prior to implementation of such a node. • Flow over cable will not increase costs in sending area but will improve reliability and economics of receiving area.

  7. Interim Solution Details • 1385 flow may not be requested or scheduled by Participants • 1385 flow only allowed under defined system conditions • Net Interchange over NYISO/ISO-NE interface will not be affected • 1385 flow will be a subset of the total NYISO/ISO-NE flow currently determined by the markets • NYNE A/C ties will automatically adjust based on 1385 flow

  8. Conditions for 1385 Flow • Potential flow on 1385 when all the following occur: • Constraints exist in the ‘receiving’ Control Area that could be alleviated via flow on 1385 • There is currently no active constraint in the ‘sending’ Control Area that is affected by flow on the 1385 • Shifting flow onto the 1385 will not create a new constraint in the ‘sending’ Control Area • Shifting flow onto the 1385 cable will not violate sub-area reliability criteria (voltage/stability)

  9. Process for Setting Flow • ISOs normally evaluate 1385 flow on an hourly basis • No flow will occur if there is no congestion at the ISOs • If future hour forecasts no congestion, ISOs will shift flow back to zero MW • Flow will not be allowed to impact Market Participant transactions on New York / New England interfaces • When all conditions are met, sending ISO will determine MW flow on 1385 and communicate to all required parties

  10. Interruption of Flow • If ‘sending’ area incurs a binding constraint due to 1385 flow, the 1385 flow will be adjusted to zero • In response to a contingency that creates a binding constraint: • If adjusting 1385 relieves the constraint, that adjustment will be requested • If adjusting 1385 has no impact on the constraint, adjustments requests made upon operator discretion

  11. Schedule for Implementation • Joint Operating Agreement between NYISO and ISO-NE under final review • Operations Protocols are under final review • Implementation expected early 2004 • Implementation will be transparent to both NYISO and ISO-NE markets

  12. ?