1 / 11

PROGRAM EVALUATION REVIEW TECHNIQUE (PERT)

PROGRAM EVALUATION REVIEW TECHNIQUE (PERT). Ismu Kusumanto Jurusan Teknik Elektro UIN Sultan Syarif Kasim Riau. FORMULASI. te : weighted average activity time a : optimistic activity time b : pessimistic activity time m : most likely activity time. FORMULASI.

shyla
Download Presentation

PROGRAM EVALUATION REVIEW TECHNIQUE (PERT)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PROGRAM EVALUATION REVIEW TECHNIQUE(PERT) Ismu Kusumanto Jurusan Teknik Elektro UIN Sultan Syarif Kasim Riau

  2. FORMULASI te : weighted average activity time a : optimistic activity time b : pessimistic activity time m : most likely activity time

  3. FORMULASI TE : critical path duration Ts : scheduled project duration Z : probability

  4. EXAMPLE Berapa probabilitas proyek selesai dalam 67 hari ?

  5. ANSWER

  6. ANSWER

  7. ANSWER 43 3 D 30 B 59 64 A 13 16 F 1 2 5 6 30 5 E C 56 20 6 4 TE = 64

  8. ANSWER • Probabilitas proyek selesai dalam 67 hari adalah : P = 0.69 P = 69 %

  9. Tabel Probabilitas

  10. LATIHAN Berapa probabilitas proyek selesai dalam 55 hari ?

  11. Terima Kasih