80 likes | 192 Views
This project on Beisel Road enhances roadway safety and environmental sustainability through improved drainage systems. Key features include uniformly sized concrete pipes and defined ditches, supported by a reinforced concrete base under an asphalt paving surface. Funded by Title II and County Transportation Committee, total expenditures reach $212,066.91, including $2,789.60 for road marking enhancements like double yellow lines and raised pavement markers. This initiative aims to effectively address drainage issues while ensuring a safer driving experience.
E N D
SCOPE SURVEYING ENGINEERING WITH FOCUS ON ENVIRONMENTAL ISSUES AND IMPROVING DRAINAGE IMPROVED DRAINAGE WITH UNIFORMLY SIZED CONCRETE PIPE AND DEFINED DITCHES ROADBED FORTIFIED WITH CONCRETE BASE ASPHALT PAVING
FUNDING • $85,000. – TITLE II FUNDS • $199,000. COUNTY TRANSPORTATION COMMITTEE (CTC) FUNDS • TOTAL PROJECT EXPENDITURES: $212,066.91
Road Marking • 4 inch double yellow line: $1,689.6 • Bi-directional raised pavement markers: $1,100. • Total amount requested: $2789.6