An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NSTX-U Supported by Project Overview Coll of Wm & Mary Columbia U CompX General Atomics FIU INL Johns Hopkins U LANL LLNL Lodestar MIT Lehigh U Nova Photonics Old Dominion ORNL PPPL Princeton U Purdue U SNL Think Tank, Inc. UC Davis UC Irvine UCLA UCSD U Colorado U Illinois U Maryland U Rochester U Tennessee U Tulsa U Washington U Wisconsin X Science LLC Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U Kyushu Tokai U NIFS Niigata U U Tokyo JAEA Inst for Nucl Res, Kiev Ioffe Inst TRINITI Chonbuk Natl U NFRI KAIST POSTECH Seoul Natl U ASIPP CIEMAT FOM Inst DIFFER ENEA, Frascati CEA, Cadarache IPP, Jülich IPP, Garching ASCR, Czech Rep Ron Strykowsky, J.Chrzanowski, L.Dudek, E.Perry, T.Stevenson LSB B318 January 3, 2013

  2. NSTXU Test Cell – May 2012

  3. Neutral Beam Progress

  4. NSTXU Test Cell Beam Box move– 9/13/12 • Began work February 2009 • 30,000 hours (>17 person years) for decontamination, refurbishment, relocation design • 55 people • Safety • >25 people at pre-job brief • Beam box = 40 tons • Lid = 14 tons Photo: Elle Starkman Stevenson

  5. NBI BL Box Relocation… TTC, South High Bay, Over the wall 2425 And on the vent stack… Stevenson

  6. NBI BL Lid Relocation… same as Box move but more involved 2425 Stevenson

  7. NBI Duct Exit Spool Piece and BL TIV installed on Exit of BL… 2480 2485 Stevenson

  8. VV Modification Bay JK weldments repaired in Tech Shop… • Bay JK and port extension weldments procured and received; • HOWEVER… • No weld prep and poor weld quality from vendor • SO… • PPPL Tech Shop repair and rewelding completed • Additional welds added for better integrity • Vacuum prep and annealing heat cycle complete • Leakchecking done… Stevenson

  9. Neutral Beam Summary NBI BL2 Upgrade GRD Requirements achieved General Arrangement maintained by Construction Manager to avoid interferences BL refurbishment almost completed… Tech Shop, Health Physics, and Work Control Center support has been excellent Relocation to NTC – major BL and Lid moves completed Services fabrication and installation has begun – water line S/C planned later this FY Power - cables received & installation S/C planned later this FY Controls progress has been tremendous on BL and NBPS Floor space has been achieved by use of gallery and new elevated platforms Duct procurements, shop work orders, and fabrication going strong VV modifications have begun – parts are here and ready Armor support installation has started and armor fabrication progressing well Preoperational testing planned to begin in FY 14 Cost and schedule indices have tracked well to date – CPI and SPI greater than 1.1 Schedule still adequate for NBI activities – not critical path NSTXU NBI project is progressing on task, under cost, on time…  Stevenson

  10. Construction Progress

  11. NSTXU Test Cell - Current Second beamline in place Umbrella legs being cut out and replaced Vacuum Vessel cutting for Bay J/K neutral beam cap underway 4 Outer TF coils removed

  12. NB Bay J/K Port opening successfully plasma cut Perry

  13. Outer TF Coils -Repair • Removal of TF outer legs that need to be repaired or replaced • Completed with minimal removal of surrounding items • Replacements must be completed before significant re-installations can occur Perry

  14. Outer TF Coils -NEW • The contract for fabricating (2) Outer TF coils was awarded to Everson-Tesla. • Soldering of the cooling tubes has started • February 2013 delivery Chrzanowski

  15. Machine structural improvements well underway Dudek

  16. Hardware Status Dudek

  17. Plan for January 2013 • Ex-vessel set-up for cutting at bay L • Installing containment and ventilation • Vacuum vessel cutting at Bay L for new diagnostics port • Remove temporary in-vessel beams and ventilation • Leak check welds on Bays JK cap • Remove platform at Bays JKL Perry

  18. Plan for December 2012 – March 2013 • Complete modifications to umbrella and coil supports • Complete Neutral Beam systems • Re-install items removed for centerstack work • Re-install items removed for NB work Perry

  19. Outage Planning for Diagnostic Calibrations • Diagnosticians have listed the calibrations they would like prior to re-starting NSTX • Detailed schedules for these calibrations are being prepared • Schedules will be fit into the existing outage schedule • Each calibration will be scheduled as early as possible to avoid delays once the installation work has been completed • Calibrations may be scheduled to occur after the Upgrade Outage if they are not required for CD-4 or early operations • All work in NSTX Test Cell being done with Engineering Work Packages (90 packages so far, 39 completed) • Written procedures • Permits • Job hazard analysis • Permits: confined space, hot work, radiation work, penetration, etc • Pre-job and post-job briefings Perry

  20. Construction Summary • The plan is being continuously worked • To improve safety and efficiencies • To deal with delays in getting parts • To accelerate tasks to ease pressure on critical path tasks • Coordination and Control • Provided by the Work Control Center • At the Plan-of-the-day meeting • Continuously by the Field Supervisors • Successfully performing the outage Perry

  21. Center Stack Progress

  22. Center Stack Fabrication & Assembly Making Good Progress Cooling tube being soldered into conductor at PPPL Machined conductor at Major Tool being prepared for shipment to PPPL Conductor after cooling tube installation and grinding Conductor being wrapped with fiberglass insulation Insulated conductor being placed into mold Conductor being removed from oven after sandblasting and priming Chrzanowski

  23. Center Stack First Quadrant ready for final assembly • Conductor progress • 4 quadrants of 9 conductors for full inner TF bundle • 38 conductors delivered • 30 cooling tube soldered • 16 primed & wrapped Chrzanowski

  24. Full TF Mold • The full TF mold is being manufactured by Reno Machine (Conn.) – • Scheduled for February delivery Chrzanowski

  25. Testing of Aquapour for OH Conductor Winding • Rolled Aluminum Cylinder wrapped with epoxy/glass insulation represents TF Bundle • Maintains true TF OD and clearance space at top and bottom • Will use actual mold segments and alignment pins • Tested: • 1. Filling of Aquapour √ • 2. Curing of Aquapour with heating blankets √ • 3. Washing Out of Aquapour √ Chrzanowski

  26. OH Winding Station Induction braze station (Complete) OH winding support tooling complete Tension unit being fabricated in house Taping machines complete Turning fixture delivered Chrzanowski

  27. Tooling Fabrication and Procurement • OH Solenoid- tooling • OH copper conductor has been received • OH conductor sandblasting & priming requisition in system • Induction braze station OH braze joints- is being commissioned • OH joint braze qualification program will begin in January • Tension unit & taping machines are in fabrication • OH Mold will be out for bids in January Chrzanowski

  28. Centerstack Casing • The Centerstack Inconel casing is being manufactured by Martinez & Turek located in California. • Delivery is scheduled for first week in January • Upon arrival of the casing 500 Inconel studs will added to the outside surfaces (original casing shown below) • 696 Tiles with diagnostics will then be mounted Chrzanowski

  29. Plans Forward for Centerstack Components • Inner TF Bundle • VPI first Quadrant- January 2013 • VPI Full Bundle- May 2013 • OH Solenoid • Begin winding OH solenoid-July 2013 • VPI OH Solenoid- October 2013 • Centerstack Casing • Delivery is scheduled for December 2012 • Centerstack Assembly- • Final assembly will occur between November 2013 to February 2014 • Developing Assembly procedures Chrzanowski

  30. Plans Forward- continued • Inner Poloidal Field Coils • Requisition has been submitted to procurement- RFQ • Delivery summer 2013 • TF buss and support components • Purchase Order has been placed with Zenox Corp. (TF Flexes) • Super-nuts in procurement February 2013 • OTF Lead extensions (January procurement) • Deliver completed Centerstack Assembly - February 2014 MT Torque-nut™ Flex-Bus (Cu-Cr-Zr) Chrzanowski

  31. Center Stack Summary • The risks associated with the production of the TF conductors have been addressed (Major Tool/Edison Welding) • The soldering trials have been completed and production nearly complete (Retired risk) • The TF bundle manufacturing facility is in full operation • Awaiting delivery of molds and completion of procedures • The R&D and procedures for VPI are complete & first VPI is scheduled for January • The Aquapour trials are complete • Tooling for the OH solenoid is being fabricated • The OH conductor sandblast/priming contract is awaiting bids • The Inconel casing is scheduled for delivery in January • Contract for the OTF has been awarded • Requisition for Inner PF coils is in procurement • The production of the Centerstack Assembly has begun Chrzanowski

  32. Cost and Schedule

  33. Schedule on track for early finish • Critical path based on 5 day/week, one shift no planned OT. • We will implement OT, weekends and 2 shift operations where appropriate on critical path. Late delivery of conductors and rework of vendor supplied quadrant mold Neutral Beam relocated ahead of schedule Forecast Aug 4 2014 Early Finish Sept 30 2014 CD-4 SEPT 30 2015

  34. Lehman Review Dec 11-12 -Conclusions Construction efforts are being executed safely. The project presently has adequate resources and necessary skills mix to execute the project. However, the impact of the possible loss of key personnel if a laboratory staff reduction is required is unknown. The Project team has implemented the required action to update the Risk Registry resulting from the status review in May 2012. Particular emphasis has been placed on using the detailed schedule to manage and accelerate procurements. The current project cost and schedule projections are consistent with the approved baseline cost and schedule. Contingency remaining is adequate for the risks that remain. The management structure is in place to deliver the scope within budget and schedule. Risks are being actively managed.

  35. Lehman Review Dec 11-12 - Recommendations • Develop a comprehensive facility readiness plan and schedule including both project and non-project items. Present plan at the next review. • Assign adequate personnel to assure completion of the Digital Coil Protection System on the original baseline schedule. • Reassess the potential impacts of the loss of critical skills and personnel and update the risk registry by February 1, 2013. • Prepare a plan for startup readiness that is acceptable to by the Site Office prior to the next review.

  36. NSTX Upgrade Summary • The project has maintained a safe working environment. • The project continues to make good technical progress. • The project is on schedule and cost. • The project is sufficiently staffed to meet schedule. • The project is on track for meeting CD-2 baseline within OFES guidance.

  37. Supplemental

  38. Lehman Review -Tour Inner TF conductor cooling tube soldering station showing setup for soldering of bar number 30 Inner TF conductor post-cooling tube soldering. Ready for grinding and cleanup. Barry Sullivan Rick Blaisdall Tony Indelicato Frank Crescenzo Bruce Stauss Steve Meador Tim Maier Will Oren ArnieKellman Ed Synakowski Kin Chao Chris Ackerman Lehman review team

  39. Lehman Review December 11th&12th - Tour Inner TF conductor sandblasting station Inner TF quadrant with 9 conductors in place ready for mold lid. End of inner TF quadrant showing cooling tubes. Aqua pour mockup test.

  40. Second Neutral Beam Safely relocated ahead of schedule • Beam box = 40 tons • Lid = 14 tons • Began work February 2009 • 30,000 hours (>17 person years) for decontamination, refurbishment, relocation design • 55 people • Safety • >25 people at pre-job brief

  41. Performance metrics good • Cost • CPI = 1.00 CV = +199K • Schedule • SPI = 1.06 ( Against early finish baseline) Total float = 2 months to early finish PLUS 12 months to late finish CD-4 • Completion • Forecast = August 4, 2014 • CD-4 Project Baseline (Early Finish) = September 2014 • CD-4 DOE Milestone (Late Finish) = September 2015 • BAC =$82.7 EAC= $83.9 TPC =94.3M • Cost to date = $44.1 M 54% complete • Free balance contingency 31-33% ($11.8M remaining consistent with remaining risk and uncertainty) (27% at CD-2)

  42. Risk & Opportunities Risk • OH Fab $1,290k FY13 • Inner TF bundle fab $544k FY13 • Serious injury stand-down $400k FY14 • Late vendor delivery on critical path $250k/mo FY14 • Other $391k FY14 • I&C add’l capacity $200k FY14 • Diagnostic re-installation $294k FY14 • Hardware fit up issues $427k FY14 • Mgmt direct allocations $216k FY14 • Critical skill lost $137k FY14 • Total open $4,149 • Opportunities • PPPL Overhead rates (baselined at conservative levels) • Schedule acceleration (by applying 2 shifts to critical path) 42