An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SUA ProcessOverviewFAA JO 7400.2 Clark Desing, Manager, Operations Support Group Western Service Center Pacific Aviation Directors Workshop May 2009

  2. Airspace: Pre-ActionConsiderations (Proponent) • Use of existing area • Modification or sub-division of areas • Shared-use • Avoid airways/jet routes, major terminal areas, and high volume VFR routes • Define your requirements

  3. Airspace: Defining Requirements(Proponent) • List Activities (who, what) • Number and type aircraft • Types of activities/mission • Altitudes • Type weapons • Chart of firing points, impact areas, firing fans and safety buffers • Chart of proposed location (where, why) • Days/times of use (when)

  4. Two Processes Work in ConcertFAA 7400.2, Appendix 4 SUA/ATCAA Conceptual Design Aeronautical Impact Environmental Impact * Informal Coordination Process * Formal Aeronautical Proposal * Aeronautical Study * Final Determination * Category Exclusions (CATX) * Environmental Assessment (EA) * Environmental Impact Study (EIS) Must Match at the End

  5. Airspace: Pre-coordination DoD/FAA Informal Coordination Process • Mandatory • Most important step in the process • Who • Proponent with the affected ATC facility • Proponent presents a draft airspace concept with requirements • Is it operationally feasible?

  6. Airspace: Feasibility ReviewInformal Coordination Process • Done by ATC facility, Assistance provided by an OSG ATREP • Determines feasibility • Evaluates potential impact on facility operations • Looks for ways to reduce affect to the NAS • Expect changes • Review can be lengthy • Helps prepare the formal proposal • Not to be considered as FAA endorsement or approval

  7. Submission of Formal Aeronautical Proposal and EnvironmentalFormal Process Stage Begins • Proponent sends airspace proposal to FAA Service Center (Operations Support Group) through the appropriate Military Representative. • Version found to be feasible by ATC facility • Include all requirements listed in FAAO 7400.2 para. 21-3-3 • Include ATCAA’s • Include environmental analysis if complete

  8. Environmental Documentation(Proponent and OSG) • Assess the airspace found to be feasible by ATC facility. • Assessment must meet FAA requirements (Cooperating Agency Agreement) • Contact the OSG Environmental Specialist for FAA process and requirements prior to submitting airspace proposal • Don’t let Environmental Impact Statement or Assessment get too far ahead of airspace proposal • Environmental and aeronautical process must end concurrently

  9. Initial Service Area Action (OSG) Aeronautical Study (*) User Groups Informal Airspace Meetings Rule/Non-Rule Making Process Public Comments (*) Formal Overview of Feasibility 9

  10. Aeronautical Study Content (ATC Facility/OSG) What affect would this new airspace have on: IFR and VFR Terminal Operations Impact on public use and charted private airports (airports with FAA Form 5010 on file) Impact on IFR En Route Operations Impact on VFR Operations, Routes, and Flyways Impact on other pending proposals. Cumulative Aeronautical Impact Associated ATCAA Alternatives ATC Facility Assessment ATC services Recommendation (s) for FAA action on the proposal 10

  11. Aeronautical Study Findings (OSG) • The service area office will: • Coordinate the study findings with the proponent to explore possible options to reduce aeronautical impact

  12. User Groups (OSG) Comprised of varied aviation interests such as: Airlines, general and business aviation, airports, etc Proposal may be submitted to a user group for technical assistance WSC OSG requirement Should be presented jointly by FAA and proponent User groups provide FAA and proponent with other user perspectives Can be effective in helping identify potential problems not already discovered or considered 12

  13. Informal Airspace Meetings (All) • “It is the policy of the FAA to hold, if at all practicable, informal airspace meetings to inform the affected users of planned airspace changes. The purpose is to gather facts and information relevant to the planned rulemaking or non-rulemaking action being studied. These are held in advance of the rulemaking/non-rulemaking action.”

  14. Rulemaking (OSG and HQ) Rulemaking: Changes Federal Law by prohibiting or restricting public access Process for regulatory SUA (Restricted and Prohibited areas) FAA notice to public that FAA is considering Regulatory airspace action Gather pubic comments Process has no provision for waivers or “shortcuts” 14

  15. Non-Rulemaking (OSG and HQ) • Non-rulemaking • Process for non-regulatory SUA (Warning Area/MOA/CFA/Alert): • FAA notice to public that FAA is considering Non-Regulatory airspace action • Gather public comments

  16. Public Comments (All) Who can comment Anybody; not restricted to only users of the NAS 16

  17. Final Service Area Actions (OSG) • Safety Risk Management Document • Business Case • Service Area Concurrence/Recommendation • Environmental Documentation (Final) • Final package to FAA Airspace and Rules

  18. Final Environmental Documentation (OSG and Proponent) • Proponent matches final environmental document with proposed airspace parameters. • Times of use, lateral and vertical dimensions, types and numbers of operations, supersonic flight, etc. • Proponent signs, EA/FONSI or EIS/ROD and submits to Service Center • Service Center reviews for compliance stated above • Service Area Environmental Specialist prepares final draft FAA determinations

  19. Final Package Contents (OSG) • Service Area: • Legal description • Graphic depiction, sectional • Proponents airspace proposal • Aeronautical comments with resolution • Proponents final environmental document • Synopsis of FAA environmental issues (draft) • Aeronautical study • Summary of minutes informal airspace meetings • Summary of user group meetings • SRMD • Business Case • Inter-agency memo’s, FS, Airports, ATC facilities • Director’s recommendations/endorsement

  20. FAA Headquarters Action • Warning/Danger Area Proposal to State Department • Airspace Office reviews, forwards draft final rule or non-rule to Environmental Office with supporting documents • Environmental Office prepares and forwards final FAA FONSI/ROD to Chief Counsel • Chief Counsel completes sufficiency review and sends comments back to Environmental Office • Environmental Office signs decision document and forwards back to Airspace Office

  21. FAA HQ Action • Airspace Office makes final airspace determination • Publishes Final Rule, Non-Rule, charts action • Letter of Rejection • Then begins the process of implementing the change to the National Airspace System (NAS), if appropriate.

  22. Summary • Maximize existing SUA (shared use) • Define requirements and outline environmental issues • * ATC facility feasibility review (Informal Coordination) • * Submit formal airspace proposal and environ. analysis • * Aeronautical impact • * Public and user group comments • * SRMD and Business Case • * Final proposal and matching environmental documents • * FAA HQ final review, approval, charting or disapproval • Implementation, if appropriate • Typically 3-5 years to completion • (*) Potential for change exists