An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GLAST LAT Tracker Tower-B Pre-Ship Review Luca Latronico INFN-Pisa luca.latronico@pi.infn.it

  2. Tower B Assembly and test highlights • 1/3-1/11 2005 (INFN-Pisa) : • assembly (tray stack, cables, sidewalls, alignment, turn-over) • test (CPT) • 1/17-2/5 2005 (Alenia-Roma) : • VIB test (1/17-18) • New TVAC chamber setup (see NCR/FM/INFN/PI-379) • TVAC test (1/29-2/5) • 2/8 2005 (INFN-Pisa) : • Alignment verification • 2/10 2005: • Through customs in Roma airport • Full EIDP details at: • http://glast.pi.infn.it • Quality Assurance page • EIDP links

  3. Before Vibe Test After Vibe Test Tower Alignment data • All measurements within stay-clear and in spec before and after ENV tests

  4. TOWER CG & MASS Conclusions • Tower well aligned and inside stayclear • Stable after Env. Test • Mass and CG near estimated values (when used real masses)

  5. Assembly and components details Tower PN: LAT-DS-00722 (rev2) Tower SN: B Relevant issues and related NCRs: • INFN/PI-220 (tray Bottom 006) • M4X6 instead of M4x8 • Proposed disposition is use as is and close • INFN/PI-362 (Tower B) • Critical insulation of termination resistor on cable 7 • SLAC will provide all cables with Kapton to protect resistors • Proposed disposition is use as is and close • INFN/PI-371 (Tower B) • Critical insulation between tower cables and fixing clips • Kapton tape was used • Proposed dispositions are • SLAC will provide all cables with kapton on all termination resistors • use as is and close • INFN/PI-349 (tray heavy 037) • GTFE21 back side instabilities • Found to be due to bad termination resistor (100Ohm) on test cable • Proposed disposition is use as is and close • INFN/PI-383 (Tower B) • Complete CPT not performed • Proposed dispositions are • use as is and close • Consider removing test from flow-chart and rely on final test after TVAC

  6. VIB test No new channel loss No change in alignment TVAC test New chamber setup Vacuum level slightly below spec (NCR-379-closed) Charge to Alenia to investigate chamber capabilities Environmental tests highlights

  7. total disconnected channels < 0.25% • ~50% of disconnected channels in 2 layers (Y12, X7): • X7 with large oscillations vs temperature • Y12 responsible for overall channel loss • all other layers were very stable

  8. Semi-disconnected channels (broken ladder wire-bonds) 1 layer only (X5 – tray H037-Front) ~60 bad channels which stabilized during tray thermal cycle and tower assembly no further degradation during tower ENV tests see NCR-368

  9. Open NCRs related to disconnected/bad channels • Bad channels NCRs - proposed disposition is use as is and close : • INFN/PI-368 (tray Heavy 037) • Last disposition (MRB 1/12/2005) is use as is for tower B; build ladders with no encapsulation and test on tower 1 • Disconnected channels NCRs – proposed disposition is use as is and close: • INFN/PI-350 (tray MID 051) • 2 more channels lost in TVAC • INFN/PI-346 (tray MID 043) • 24 more channels lost in tray thermal cycle and tower TVAC • INFN/PI-384 (tray MID 023) • Large fluctuation in number of disconnect vs temperature • INFN/PI-389 (tray Heavy 018) • 13 disconnected and 4 noisy found during TVAC test

  10. Conclusions • Tower B was assembled, tested and shipped to SLAC in 2 weeks (2 more weeks were lost for the setup of the new Alenia TVAC chamber) • No major issue were found in assembly, environmental tests, performance verification – a number of minor issues must be addressed before tower1 activities • The overall number of bad channels is very low • New MCMs with no PA disconnection will reduce even more this number and its stability with time/temperature • New heavy and bottom ladders with no wire-bond encapsulation will show their reliability soon (tower1 trays data available next Monday right before assembly)