An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ODOT Roadway Engineers and Certified Traffic Office of Roadway Engineering Services March 20, 2008

  2. What do designers do with certified traffic? • Capacity of Freeways, Interchanges, Highways, and Intersections • Geometric Design (Cross Section) • Pavement Design • Bridge Design (ADT)

  3. What does Roadway Engineering do with certified traffic? • Studies • Planning Level design • Intersections (Turn Lanes, Through Lanes, Etc.) • Interchange Configurations (Diamonds, Par-Clo’s, SPUI’s, etc.) • Geometrics • Cross Sections (Lane Width, Shoulders, etc.)

  4. Planning Level Traffic • Differences between planning level, refined planning level, and certified • What does/can this mean to the designer? • What does this mean at certain points in the Plan Development Process (PDP)? • Conceptual Alternative Solutions (CAS) - Step 5 • Alternative Feasible Assessment (AFA) - Step 6 • Preferred Alternative Verification– between Step 6 and Step 7

  5. Certified Traffic • Validity for design • Duration of Project can outdate traffic? • How long is certified traffic good for? • Rule of Thumb • 3 years from study approval year • 1 year difference between opening year • Need concurrence from approving office/agencies

  6. Design Traffic • Existing Year (Counts) • Opening Year (Identified by Project Manager) • Design Year (20 year from Opening) • Location and Design Manual – All improvements on ODOT’s system will be designed using certified traffic.

  7. Design Hour Volume • AM, PM, or DHV • Which is preferred? • It depends on the location • AM / PM peaks – Allows design to be tailor to peak demands • DHV – Design could be conservative with peak demands occurring simultaneously. • OTS supplies AM/PM as default

  8. Nuances with Certified Traffic • Traffic Impact Studies (TIS) • Interchange Justification Studies (IJS)/ Interchange Modification Studies (IMS) • TIS’s which turn into IMS’s • No Build / Build for TIS / IMS • Build TIS = No Build IMS (development traffic inc.) • Economic Development Scaling to not to degrade facility.

  9. Study Area for TIS Site Minimum intersections to be studied Additional Intersections – determined by PM

  10. Study Area for IMS/IJS Potential Intersection Depending on LA R/W Interchange being studied Potential Intersection Depending on LA R/W Analysis Points

  11. Intersection Design • Rules of Thumb for Signals (4 leg) • Left Turn Lane • Need a left turn lane at 100 vph (vehicles per hour) • Need a double left at 300 vph • Right Turn Lane • Need a turn lane around 400-500 vph • Try to avoid double right turn lanes • Through Lane • A single lane handles around 400-500 vph

  12. Design Software used within ODOT Required • HCS (L&D manual and FHWA policy) Optional • Synchro (closely spaced intersections) • Sidra (multilane roundabouts) • CORSIM (complex freeway analyses) • VISSIM (complex intersection/interchange analyses)

  13. Questions