Ring Building Construction Status. Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities Advisory Committee Review October 5 & 6, 2010. Construction Status Outline. Construction Safety Construction Status Milestones/Phases Cost Performance

saad
Download Presentation

Ring Building Construction Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Ring Building Construction Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities Advisory Committee Review October 5 & 6, 2010

  2. Construction Status Outline • Construction Safety • Construction Status • Milestones/Phases • Cost Performance • Technical and Quality Oversight • Staffing Plans Going Forward • Issues and Challenges • Path Forward • Conclusions

  3. Construction Safety • Maintain “Best in Class” Safety Program Objective • Ongoing Adjustments • Torcon Has Reinforced Safety Effort • CF-CM Working Closely with ESH • Regular Meetings to Continue Improvements • Daily Morning Safety Meetings w/ Torcon • Our success measured by our Safety Performance

  4. Ring Building Construction Status Construction as of September 30, 2010

  5. Ring Building Construction Statistics(As of September 30, 2010) • Contract Amount $172,600,600 • Approved Changes $4,722,859 • Adjusted Contract Amount $177,323,459 • Earned to Date $100,861,441 • Percent Complete 57% • Contract Award February 18, 2009 • Completion Date April 30,2012 • Duration 801 Days • Days Elapsed 500 Days • Percentage 62%

  6. Ring Bldg Construction Phasing Phase Milestone Baseline 1-Feb-11 Pentant 1- BO 1 2 RF Building - BO 23-Mar-11 Injection Building - BO 3 18-May-11 4 Pentant 2 - BO 2-Jun-11 5 Pentant 3 - BO 27-Sep-11 Pentant 4 - BO 28-Nov-11 6 7 Pentant 5 - BO 9-Feb-12 Ring Bldg Const. 30-Apr-12 8 Complete • Beneficial Occupancy Dates • Construction of LOBs Coordinated with Ring Bldg Construction Phasing

  7. Cost Performance Report

  8. Cost Performance Report

  9. Technical and Quality Oversight • Inspection Team • BNL Inspectors • Outside Inspectors (Staff Augmentation) • Testing Agencies • Universal Testing (Steel) • MT Group • Concrete • Soils • Inspection Procedures Developed and Implemented • Concrete and Steel

  10. Technical and Quality Issues • Technical and Quality Issues Identified Immediately • Minor • Contractor Notified – Corrections Made • Inadequate Response • Pending Items Issued in Contract Manager • More Serious Requiring Documentation • Compliance Notice Issued in Contract Manager • PPM Issues or copied • Work Closely with Contractor’s QA Manager • Minimal Serious Issues until recent concrete strength • Maintaining High Quality

  11. Technical and Quality Issues

  12. COMPLIANCE NOTICE-0007Dowels at Ring Tunnel Slab Dowels Identifies

  13. COMPLIANCE NOTICE-0007Dowels at Ring Tunnel Slab

  14. Project Staffing • Current Staffing • Permanent Staffing Hires Complete (6 positions filled) • F&O Field Inspector (CW Piping and Substation Upgrade) • Staff Augmentation Started (3 positions filled to date) • Civil Inspector • Clerk of Works • Mechanical Inspector • Revised Staffing Plan • Added 1.5 FTE to address simultaneous LOB construction • Provides enhanced safety oversight • Additional inspection staff available thru augmentation

  15. CF Staffing Plan

  16. Construction Management Organization

  17. Issues and Challenges • Safety • ‘Best in Class’ Program Going Forward • Meeting Phase 1 Milestone (Pentant 1 Occupancy) • Transition to Operations • Managing contractor change requests • Different LOB Contractor – Ongoing Logistics

  18. Path Forward • Refocus ‘Best in Class’ Project Safety Program • Work with Torcon to Facilitate Project • Continue Inspection and Testing Effort • Continuous Improvement of CF Procedures Manual • Ramp Up Commissioning • Prepare for Upcoming Activities – Checklist • Closeout Utility Construction Packages • Substation Upgrade Contract • Chilled Water Piping Contract • Continue Training When Applicable

  19. Conclusion • Reinforced Safety Effort Working • Lessons learned from early incidents • Enhanced safety program • Project Ahead of Schedule • First milestone still a challenge • Intermediate on track • Completion ahead of schedule • Safety/Technical/Quality Requirements Being Met