REDEVELOPMENT OF NATIONAL STADIUM INTO A SPORTS HUB AT KALLANG 26 JAN 2005 PowerPoint Presentation
Download Presentation
REDEVELOPMENT OF NATIONAL STADIUM INTO A SPORTS HUB AT KALLANG 26 JAN 2005

Loading in 2 Seconds...

play fullscreen
1 / 20

REDEVELOPMENT OF NATIONAL STADIUM INTO A SPORTS HUB AT KALLANG 26 JAN 2005 - PowerPoint PPT Presentation


  • 366 Views
  • Uploaded on

REDEVELOPMENT OF NATIONAL STADIUM INTO A SPORTS HUB AT KALLANG 26 JAN 2005. WHY DEVELOP A SPORTS HUB ?. It is part of the Sports Industry Development Strategy to turn Singapore into a Sporting Nation To attract & host World Class Sports & Entertainment Events

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'REDEVELOPMENT OF NATIONAL STADIUM INTO A SPORTS HUB AT KALLANG 26 JAN 2005' - ryanadan


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide2

WHY DEVELOP A SPORTS HUB?

  • It is part of theSports Industry
  • Development Strategyto turn
  • Singapore into a Sporting Nation
  • To attract & hostWorld
  • Class Sports&Entertainment
  • Events
  • To promote Singapore as an
  • attractive place forglobal
  • talentto live & play
slide3

WHAT’S A SPORTS HUB?

#1: A cluster of up-to-date and multi-

functional venues to cater to World

Class Sports & Entertainment

Events

slide4

#2:

  • A Lifestyle Hub
  • - To draw Singaporeans &
  • tourists with a buzz
  • of sports, leisure and
  • entertainment activities
  • on both event and non-
  • event days.
  • #3:
  • A National Architectural Icon
slide5

FEASIBILITY STUDY

  • Jun - Dec 2002
  • Consortium led by PricewaterhouseCoopers
  • Consortium (PWC)
  • Feasibility Study-Site, Transport Network, Projected
  • Revenue on event days, Capital & operating cost etc
  • Key result of the study
  • Sports Hub Project is commercially viable on
  • an operational basis. It is not possible to
  • fully recover the Development Cost
comparison of capital cost
COMPARISON OF CAPITAL COST

* Based on 45,000 seats

revenue
REVENUE

Summation of the various potential revenue centres

Projected Revenue is estimated to be abt $34 mil per year

slide9

OPERATING COST

The operating cost is estimated to be abt $20 mil per year

revenues and operating costs in steady state s mil
REVENUES AND OPERATING COSTSIN STEADY STATE (S$mil)

* Revenues and costs shown are the average per year. In the actual model,

these vary from year to year depending on whether there are major events

or cyclical maintenance projected in that year.

facilities
FACILITIES
  • New Stadium (45,000 - 55,000 seating capacity with adjacent 400m warm up track)
  • Multi-purpose Indoor Arena (6,000 seating capacity)
  • Supporting Commercial Facilities (GFA 34,000 m2)
  • Carpark - 3,275 lots
  • Aquatics Centre cum Water Leisure Park*
  • Existing Singapore Indoor Stadium

(Will be included as parts of Sports Hub and be managed by the same Sports Hub operator)

*The Aquatics Centre was not included in the original feasibility study. Capital cost is estimated to be about S$30mil

slide12

SITE

New KPE

Netball Centre

35.6 ha

Tennis/ Squash Centre

Cricket Field

Open Space

New MRT Station

Leisure

Drome

Kallang Theatre

Oasis Rest

Indoor Stadium

slide13

N

NEW TRANSPORT LINKS

Stadium Carpark

National Stadium

Circle Line – Boulevard Station

Kallang - Paya Lebar Expressway

Practice Track

slide14

Nicoll Highway

Stadium Boulevard

Stadium Walk / Crescent

Geylang River

Tanjong Rhu Rd

ECP

KPE Interchanges near Kallang site

slide15

Circle Line Phase 1 (CCL1)

  • Total length : 5 km
  • 6 stations
  • Opening in 2009
method of procurement
Method of Procurement
  • Public Private Partnership (PPP) in the form of

Design, Build, Finance, Transfer, Operate (DBFTO) model

    • Ownership of Sports Hub will be transferred to the government as soon as construction is completed and the PPP provider continue to have the exclusive rights to operate the facilities
ppp model

What is PPP?

PPP Model

Government’s Role

  • Own the Sports Hub land and building
  • Lease the land to PPP provider
  • Annual payment (over 20-30 years) to cover:

- Development Cost of approx $650mil

- Cost of Operations and Maintenance (Availability

Payment)

  • Entitled to x% of event days/year

(To be set aside for govt use)

slide18

PPP Model

PPP Provider’s Role

  • Design, Build, Finance and Operate the entire Sports Hub to meet the public sector’s requirement
  • Market the Sports Hub and attract major events*
  • Ensure operationalviability

* Market event days not taken by the govt and maximise revenues by attracting events

timeline
Timeline

Phase 1 (Jul 05 - Feb 07)

  • Tender Process

- Pre-qualification

- Request for bid and concept design

- Best and Final Offer (BAFO)

Phase 2 (Mar 07 - Dec 10)

  • Construction