Introduction, PDR Recommendations & TS2 PSS Safety Analysis

TS2 PSS Critical Design Review. Introduction, PDR Recommendations & TS2 PSS Safety Analysis. Stuart Birch ICS-Protection Systems Group- Senior Engineer Personnel Safety Systems. ESS/ICS/PS 2019-04-09. Contents. Welcome PDR Recommendations TS2 PSS Safety analysis IE Analysis

rstallworth
Download Presentation

Introduction, PDR Recommendations & TS2 PSS Safety Analysis

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TS2 PSS Critical Design Review Introduction, PDR Recommendations & TS2 PSS Safety Analysis Stuart Birch ICS-Protection Systems Group- Senior Engineer Personnel Safety Systems ESS/ICS/PS 2019-04-09

  2. Contents • Welcome • PDR Recommendations • TS2 PSS Safety analysis • IE Analysis • SIL Determination • SRS • SIL Verification • Example of the Process for a TS2 PSS function (Waveguide Removal)

  3. Welcome Thank you everyone for attending today’s CDR for the TS2 PSS. Critical Design Review (CDR) • The CDR verifies that the specified requirements are met by the detailed design. A CDR demonstrates that the maturity of the design is appropriate to proceed into implementation and installation. • The charge for the CDR – ESS-1083622 • The results of the review shall be summarized in a short report, outlining the answers to the above review questions and whether the review is considered passed, passed with action items, or failed. • The report may also provide findings, comments, and recommended actions. • Actions should be clearly categorized as one of the following: • Must be addressed before CDR is considered closed • Must be addressed prior to the system verification • Must be addressed Post CDR

  4. TS2 TS2 Control racks Removable Waveguides Heavy Shield Door Cryo-Module Modulator TS2 Bunker Bunker Access Klystrons

  5. TS2 PSS Critical Design Review PDR Recommendations ESS/ICS/PS 2019-04-09

  6. PDR Recommendations PDR Recommendation 1. Add changes in operation procedures so that the waveguide removal interlock is rated at SIL 2. Report the solution to this issue at the CDR. ETA for TS2PSS_IE3 – Failure to remove removable part of RF waveguide before the Klystron test

  7. PDR Recommendations • PDR Recommendation 2 • Explicitly show the cross references and traceability between risks and requirements in the documentation. • Section 4 of Initiating Events Analysis Document ESS-0468688 Table 2. Maps the: • Initiating Event id • Hazard from Risk assessment • Hazards from the Initiating Event Register

  8. PDR Recommendations • PDR Recommendation 3 • Use Option 2 for the ODH system. That is, tie it into the PSS system. • We have incorporated the ODH within the PSS • PDR Recommendation 4 • Review explicitly possible common cause failures and present this at the CDR. • I will present this within this presentation. • PDR Recommendation 5 • A verification plan specific to the TS2 PPS shall be created prior to the CDR. • Paulina Skog will present within presentation 2.

  9. PDR Recommendations ETA for TS2PSS_IE1 – TS2 operation inadvertently started

  10. TS2 PSS Critical Design Review TS2 PSS Safety analysis ESS/ICS/PS 2019-04-09

  11. Route map TS2 Risk Assessment Initiating Events Analysis SIL Determination SRS SIL Verification

  12. Route map TS2 Risk Assessment Initiating Events Analysis SIL Determination SRS SIL Verification

  13. TS2 PSS Initiating Events Analysis • The Initiating Event Analysis defines: • The overall safety requirements for the Test Stand 2 Personnel Safety System extracted from the TS2 Risk Assessment • Identification of the Initiating events • Initiating event analysis • Initial ETAs for the initiating events

  14. TS2 PSS Initiating Events AnalysisOverall safety requirements • The overall safety requirements for the TS2 PSS have been derived Risk Assessment. • The high-level safety requirements can be expressed as follows: • TS2PSS_REQG1: TS2 bunker shall be searched prior to lock-up and search shall be controlled by PSS. • TS2PSS_REQG2: TS2 PSS shall prevent access to TS2 bunker area during operation. • TS2PSS_REQG3: TS2 PSS shall interface the RF waveguide during the Klystron testing outside of the TS2 bunker to ensure that the RF power to CM is disconnected. • TS2PSS_REQG4: TS2 PSS shall have the interface with radiation monitors outside TS2 bunker area to switch off the RF power in case of high radiation. • TS2PSS_REQG5: ODH detection system shall be installed outside the TS2 bunker (if the oxygen levels inside the bunker drop below 18% the ODH evacuation alarms shall be triggered). • TS2PSS_REQG6: TS2 PSS shall provide means within TS2 bunker to switch off the RF power in case of emergency. (PSS team Requirement! not from risk assessments!)

  15. TS2 PSS Initiating Events AnalysisIEs

  16. TS2 PSS Initiating Events AnalysisSIFs SIFs action • Remove permit to energise the TS2 modulator and the LLRF • TS2PSS_SIF04 action • Electrically lock the personnel access door

  17. TS2 PSS Initiating Events Register ESS-0507830

  18. Route map TS2 Risk Assessment Initiating Events Analysis SILDetermination SRS SIL Verification

  19. SIL Determination The SIL Determination of the TS2 PSS shall: • Determine the frequency and consequence of identified hazards; • Determine the risk reduction provided by other measures and the resulting risk gap, if any; • Assign SIL requirements for SIFs to any resulting risk gaps in accordance with IEC 61511.

  20. SIL Determination ESS-0288441 LOW Demand SIFs (demands <1/yr) HIGH Demand SIFs (demands >>1/yr)

  21. Common Cause • Common Cause Failure analysis • Common Cause Failures (CCFs) have been considered during the SIL Determination. IPLs used in LOPA have been examined to ensure that they are independent from each other and each IPL is independent from the initiating events. • Other typical CCF factors are considered below: • Loss of power supply. Loss of power supply to the PSS system would affect all SIFs at the same time. However, since the TS2 PSS SIFs are designed as de-energised to trip, loss of power would put the system in a safe state (i.e. permit to energise TS2 modulator or LLRF removed). • Major accidents. A major accident such as earthquake, fire, flood etc. could lead to power loss affecting all SIFs. Loss of power supply would put the system in a safe state, see the bullet point above.

  22. Route map TS2 Risk Assessment Initiating Events Analysis SIL Determination SRS SIL Verification

  23. SRS – List of Safety Requirements

  24. Route map TS2 Risk Assessment Initiating Events Analysis SIL Determination SRS SIL Verification

  25. SIL Verification – ESS-0478596 SIL Verification of the TS2 PSS, conducted in accordance with IEC 61511. The random hardware reliability, and minimum architecture in terms of hardware fault tolerance of each SIF has been addressed, comprising input devices, logic modules, actuator and final element devices. Based on the test and maintenance strategy, the maximum allowable SIL for the SIF was calculated and compared with the requirements identified by the SIL Determination report.

  26. SIL Verification – ESS-0478596 Summary of Results Summary of Results – LOW Demand SIFs Summary of Results – HIGH Demand SIFs

  27. TS2 PSS Critical Design Review TS2 PSS Safety Analysis Example - Failure to remove waveguide ESS/ICS/PS 2019-04-09

  28. Safety Analysis - IE Analysis The overall safety requirements for the TS2 PSS have been derived from the Risk Assessment. • 3. TS2PSS_REQG3: TS2 PSS shall interface the RF waveguide during the Klystron testing outside of the TS2 bunker to ensure that the RF power to CM is disconnected. TS2 Risk Assessment

  29. Safety Analysis - IE Analysis Identification of the Initiating events TS2 Risk Assessment Initiating Events

  30. Safety Analysis - IE Analysis Define the SIFs Initiating Events Define SIFs

  31. Safety Analysis - IE Analysis Initial ETAs for the initiating events New Define SIFs Initial ETAs for the IEs

  32. Original TS2 PSS Initiating Events Analysis ETA – Failure to remove waveguide

  33. Safety Analysis – SIL Determination IE Analysis • Determine the frequency and consequence of identified hazards; • Determine the risk reduction provided by other measures and the resulting risk gap, if any; • Assign SIL requirements for SIFs to any resulting risk gaps in accordance with IEC 61511. SIL Determination

  34. TS2 PSS SIL DeterminationMethodology – LOPA Risks arising from dangerous failures in the process & in the BPCS Target Risk Demands F3 Risk Risk reduction achieved by Conditional Modifiers Risk reduction achieved by Other Risk Reduction Measures Risk reduction achieved by SIS/SIF

  35. TS2 PSS SIL DeterminationMethodology – LOPA 4 3 2 1 Risks arising from dangerous failures in the process & in the BPCS Target Risk SILs Demands F3 Risk Risk reduction achieved by Conditional Modifiers Risk reduction achieved by Other Risk Reduction Measures

  36. Safety Analysis – SIL Determination SIL Determination LOPA

  37. Safety Analysis – SRS Safety Requirements Specification (SRS) for TS2 PSS SIFs • Inputs • Results from SIL Determination • Requirements from IEC 61511 • ConOps • Outputs • SRS (ESS-0288460), used for • Design and engineering • SIL Verification (ESS-0478596) • To confirm the design meet SIL targets from SIL Determination • Subsequent safety lifecycle stages • FAT, SAT, commissioning, operation, maintenance, etc. SIL Determination SRS

  38. Safety Analysis – SRS • TS2PSS_SIF5 – Interlock on Waveguide during Klystron Testing SIL Determination SRS Safety Requirements

  39. Safety Analysis – SRS • TS2PSS_SIF5 – Interlock on Waveguide during Klystron Testing SIL Determination SRS Safety Requirements

  40. Safety Analysis – SRS • TS2PSS_SIF5 – Interlock on Waveguide during Klystron Testing SIL Determination SRS Safety Requirements

  41. Safety Analysis – SIL Verification SRS SIL Verification Based on the test and maintenance strategy, the maximum allowable SIL for the SIF was calculated and compared with the requirements identified by the SIL Determination report.

  42. Safety Analysis – SIL Verification TS2PSS_SIF5 – Waveguide interlock during Klystron test RBD The configuration achieves SIL 3 in terms of architectural constraints in accordance with IEC 61508. SRS SIL Verification RBD

  43. Safety Analysis – SIL Verification The FTA shows the achieved PFD for TS2PSS_SIF5 is 5.9E-04. This falls into SIL 3 band. SIL Verification RBD SIL Verification FTA

  44. Safety Analysis – SIL Verification ETA03 – Human error while conducting Klystron test SIL Verification FTA SIL Verification ETA

  45. Safety Analysis – SIL Verification Summary of Results – LOW Demand SIFs SRS SIL Verification

  46. Questions? Thank you for your attention!

  47. TS2 PSS SRS (ESS-0288460) Safety Requirements Specification (SRS) for TS2 PSS SIFs • Inputs • Results from SIL Determination • Requirements from IEC 61511 • ConOps • Outputs • SRS (ESS-0288460), used for • Design and engineering • SIL Verification (ESS-0478596) • To confirm the design meet SIL targets from SIL Determination • Subsequent safety lifecycle stages • FAT, SAT, commissioning, operation, maintenance, etc.

  48. Dependences • Completed TS2 shield bunker complete with all shielding • Electrical power interfaces with TS2 PSS (new electrical board) • Heavy shield door, operational and ready for PSS interfaces • Fenced area and bunker entrance ready for PSS interfaces • Modulator PSS interface (UV coil installed within the breaker for PSS) • Waveguide Switch • LLRF PSS interfaces installed (co-axial switches 1U box) • Removable waveguide with PSS interface switches installed • EPICS interfaces • UPS backup. • REMs Interface definition.

  49. PDR Recommendations SFF. It is defined as the sum of the potentially dangerous failures revealed by auto-test together with those which result in a safe state, as a fraction of the TOTAL number of failures. SFF = Total revealed hazardous failures + Total safe failures Total failures. IEC 61511 defines minimum hardware fault tolerance (HFT) requirements for the sensors, logic solvers and final elements that make up each safety function