1 / 39

Using Performance-Based Payments Linking Contract Financing to Performance and Schedule Advanced Program Management Cour

Using Performance-Based Payments Linking Contract Financing to Performance and Schedule Advanced Program Management Course Elective 486A Presented By: Timothy Frank Defense Contract Management Agency. Performance-Based Payments. About the Defense Contract Management Agency. What We Do.

roy
Download Presentation

Using Performance-Based Payments Linking Contract Financing to Performance and Schedule Advanced Program Management Cour

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Using Performance-Based Payments Linking Contract Financing to Performance and Schedule Advanced Program Management Course Elective 486A Presented By: Timothy Frank Defense Contract Management Agency

  2. Performance-Based Payments About the Defense Contract Management Agency

  3. What We Do Achieve Customer Outcomes! • Provide Customer Focused Contract Management Services • Right Item = Quality • Right Time = On-Time Delivery • Right Price = Value for Money • Combat Support Agency • Military Operations • Readiness of Fielded Systems • Modernization of Military Equipment • Industrial Surge – During Conflict Teaming with Military Services and Defense Contractors to ensure that tax dollars achieve mission requirements

  4. PRE-AWARD 81 Functions Pricing / Negotiation Core Contract Admin Program Technical Support Quality Assurance Engineering Surveillance Production Surveillance Property Management Small Business COMPLETION AWARD PERFORMANCE CAS Life Cycle Involvement What We Do!!! • FAR 42.302(a) Standard Functions • DFARS 242.302(a) • FAR 42.302(b) Additional Functions • DFARS 242.302(b)

  5. Full Service Acquisition Impact • Scope of work • All major weapons system programs • $850B in Contract “Face Value” • $95B Unliquidated Obligations • 360,000 Contracts • 25,000 Contractors • Flight Operations (1200 Aircraft/yr) • Span of Control • 12,500 Professionals • 1,000 Locations Worldwide • 65 Major Field Commands • $100M Reimbursable Foreign • Military Sales • DoD Standard Procurement • System • Combat Support Agency

  6. About Performance-Based Payments

  7. What Are Performance-Based Payments? PBPs are… • Part of the acquisition reforms of FASA • Contract financing relying on performance measured by: • Objective, quantifiable methods • Accomplishment of defined events • Other quantifiable measures or results • Focus on performance rather than incurred costs • The preferred method of contract financing

  8. What is OSD Policy? “Increase the Use of Performance-Based Payments” Under Secretary of Defense for AT&L memorandum, November 13, 2000… Established goals for expanding use of PBPs in contracts with contract financing 25% of contracts in 2002 50% of contracts by 2005 Services and Agencies are working hard to meet these goals!

  9. Contract Financing Changes from FY00 to FY01 1st Qtr FY001st Qtr FY01 PBP #s 43% 199 285 PBP $s 94% $1,820M $3,503M Progress Pay #s 28% 4,420 3,190 Progress Pay #s 25% $2,179M $1,632M What are the Trends? Use of Performance-Based Payments is Growing

  10. Why increase use of PBPs? Enhanced technical and schedule focus PBPs require contractor performance before payment is made This is the “performance” aspect – Good for the Government Enhanced cash flow to contractors PBPs can be up to 90% of the contract or line item price This is the “payment” aspect – Good for the contractor

  11. When Can PBPs Be Used? Federal Acquisition Regulation (FAR) requires the contract to be Fixed Price 6 months duration or longer 4 months for small businesses Minimum of $2 million Minimum of Simplified Acquisition Threshold (currently $100,000) for small businesses PBPs are particularly well suited for major programs

  12. What Other Conditions Apply? • Can Be Used • With definitized contracts • When the Contracting Officer finds them practical • When the contractor agrees to their use • And, as of March 2000, with competitive procurements and R&D • Can’t Be Used • In conjunction with most other financing types • Such as progress payments • On undefinitized or cost-reimbursement contract • When contractor and Government cannot agree on terms • For architect-engineer services or construction • For ship building or ship conversion, alteration, or repair

  13. Why would you want to use them? • Government • Payment contingent on performance encourages performance, not costs • Can be structured to motivate improvement • Potentially easier to administer – low level of monitoring/audit • Contractor • Higher payment ceiling (90% of price vs. 80% of costs • (90%-95% for Small Business or SDB) • Better cash flow when initial costs are low, or contract is ahead of schedule (in both an over-run and under-run) • Somewhat less system oversight required

  14. What About Negotiation of PBPs? • Payments must be clearly defined amounts • Dollar value or percentage of known amount such as unit price • Payments may be based on • Accomplishment of defined events • Other quantifiable measures of results • “Financing shall be provided only to the extent actually needed for prompt and efficient performance” • Amounts may be established on any rational basis including • Engineering estimates of stages of completion • Engineering estimates of hours or other measure of effort • Projected costs of performance PBP terms are part of the total negotiation of a fair and reasonable contract price

  15. How Are Events Selected? • Events may be severable or cumulative • If cumulative, no steps can be skipped • Events must be “integral and necessary part of contract performance” • No administrative or perfunctory events • No reliance on costs rather than accomplishment • Schedule and amounts must take into account value of completed work, and Government financial security needs • Need to motivate continued performance • If contract ends at this event, what do we have?

  16. How is a payment processed? • Contractor presents request for payment to ACO, no more than monthly, for all performance events completed in the period • The request contains all required supporting documentation and will be certified by the contractor. • ACO verifies completion of performance events, approves request for payment, and forwards request to payment office. • Payment office processes payment

  17. What happens if…? • There is Government-caused delay? • Contracting officer may renegotiate the PBP terms • There is a modification to the contract? • PBP terms may have to be changed by the contracting officer negotiating the change • Contractor fails to make progress, financial condition deteriorates, or doesn’t pay it’s vendors? • PBPs can be reduced or suspended

  18. How is Surveillance performed? • ACO determines what reviews are required based on assessment of Government risk • Reviews may include: • Verification of performance events • Assessment of financial condition • Evaluation of progress on the contract • Surveillance performed by technical specialists

  19. Performance-Based Payments A Performance-Based Payments Success Story The C-17 Globemaster Note: C-17 information provided courtesy of The Boeing Company

  20. C-17 Program: 2 PBP Applications • C-17 Production Contract - $14.2 Billion • Established On The 80 Aircraft Multi-Year Production Program • Groundbreaking Implementation - Highly Successful • Affordability Improvement Projects - $300 Million • One Time Only Engineering and Manufacturing Development (EMD) Efforts • Struggled To Success

  21. C-17’s Application of Production PBP Part I • Contractor, SPO, DCMA, & DFAS Early Partners In PBP Process • Process Designed To Meet Needs Of All Parties • Deliverable Item (Aircraft) Rather Than Whole Contract • Event Definition -- Each PBP Event Has Two Parts: • The Action: An Easily Observable Physical Move • -- And -- • The Criteria:A Quantifiable Measure Of Completeness • Contractually Defined Description, Criteria, & Required Verification

  22. C-17’s Application of Production PBP Part II • Manufacturing Variability Recognized - Success > 95% Of Event’s Work • Chosen Events Are Central To The Build Of The Aircraft • Both Severable (Stand-Alone) And Cumulative (Dependant) Events • Predetermine Estimated Schedule Dates Payments Replicate Net Present Value Of 100% Progress Payments

  23. Severable Events Cumulative Events Aircraft Delivery PBP Events For Each Aircraft 1 Rough Machining Of MLG Bulkhead Frames 2 Receipt Of Aft Pressure Bulkhead Details Completion Of Wing Spars 3 4 Completion Of Wing Halves Cumulative Assembly Series 5 Completion Of The Four Major Sub-Assemblies 6 Completion Of Final Assembly Aircraft Delivery

  24. Notional Aircraft Cost Profile Performance Events With PBP Billing Percentages Aircraft Delivery 110% 100% Event Billing Percentages 100% Events 90% Major Sub-Assemblies Normative Cost Curve 90% 80% Lot IX ATP Milestone 80% Completion Of Wing Halves 70% 70% 60% Percentage Of Cost Completion Of Wing Spars 60% Percent Of Price 50% 50% Recv Aft Press Bulkhead Details 40% MLG Bulkhead Frames Machined A/C Assembly Complete 40% 30% 30% 20% 20% 10% 10% 0% 0% Feb-96 May-96 Aug-96 Nov-96 Feb-97 May-97 Aug-97 Nov-97 Feb-98 May-98 Aug-98 Nov-98 Quarter Mid-Points

  25. C-17 Production PBP Status • C-17 Program Implemented PBP On September 1996 • First Successful Implementation Of PBP On A Major Program • Process Stable And Functioning Extremely Well • DFAS sees the C-17 Program is an Example To Emulate • Increased Cash Flow For Contractor - Lower Unit Cost For Gov't. • Improved Relationship Between Contractor and Gov’t WIN - WIN For Government And Contractor

  26. Production PBP Lessons Learned • Communication Between Gov’t & Contractor Is Essential • Early Attention To Detail and Risk Mitigation Pay Dividends • Exhaustive Contractual Definition Absolutely Required: • Events • Methodologies • Responsibilities • Resets • Changes • Electronic Billing system Needed for PBPs • (Help is on the way! Ed.) • Subcontractors Reluctant To Use PBP • Need Assistance from Primes Note: These charts represent Boeing’s current approach to the C-17 program, but the company continues to explore methods that would improve on the process.

  27. Affordability Improvement Projects PBP • Affordability Improvement Effort Adapted to PBPs • 270 Affordability Improvement Projects -- $300M in Funding • Manufacturing Processes Improvements • Engineering Redesign For Producibility • Software Systems and Others Types • 23 Events Pulled From Eight Representative “Golden” Projects • Available Plans Conceptual -- Event Definition Problematic • Each Event Unique • High Level Schedules • ROM Expenditure Forecast Observation: Not Easy To Implement PBPs On R&D / EMD Type Projects

  28. Affordability Improvement PBP Lessons Learned Situation: • Plans For First Time Efforts Always Subject To Change • Schedule, Work Flow, Expenditures, Event Definitions • At Odds With PBPs Need For Contractually Precise Definitions • Risk To Event Completions, Cashflow, and Program’s Health Response: • Early Risk Mitigation And Adaptability Planning Essential • Contractual Language Defining Change Process Recommended • Establish and Maintain Partnering Relationship • Use PBPs As A Financing Methodology - Not As A Cudgel PBP Can Be Made To Work On First Time Efforts

  29. The Wrap Up • PBPs Are An Excellent Means Of Program Financing • Many Advantages To Customer and Contractor • Attention To Contractual Definition Pays Long Term Benefits • Customer & Contractor’s Joint Ownership Helps Success The Key: Ongoing and Open Communication - Teamwork

  30. Resources & References • DCMA Onebook chapter 9.3, “Performance-Based Payments”http://home.dcma.mil/onebook/9.0/9.3/PerfBasedPay.htm •   Director, Defense Procurement memorandum, “Performance-Based Payments,” Nov. 9, 1998: http://www.acq.osd.mil/dp/oldmemos/perform.pdf •   DCMA Draft “Contract Financing Application Guide”: http://www.dcma.mil/onebook/9.0/9.2/spot-workingdraftAug30_1.htm • DCAA Audit guidance on PBP’s at: http://www.dcaa.mil/mmr/m98pfc105.pdf

  31. Performance Based Payments Contact: Timothy Frank tfrank@hq.dcma.mil 703-428-1005 Process Owner Performance-Based Payments Defense Contracts Management Agency http://www.dcma.mil/

  32. Performance-Based Payments Some Additional Information

  33. Contract Financing Trends

  34. What are some pitfalls? • Security provisions are unclear in regulations • If defined events do not include “deliverable” work of sufficient value, PBPs become advance payments. In this case the CO must comply with FAR 32.4 requirements for advances • All contract financing requires security. FAR PBP clause gives Government title to materials (similar to PP clause), but this may not be adequate security if “events” are too generously defined. • PBPs paid must be “commensurate with the value of the performance event” & not cause “unreasonably low or negative level of contractor investment” • “To avoid undue risk of loss, contracting officers should negotiate PBPs that establish payment amounts not expected to exceed the projected tangible value of [the titled] property.” (Director, Defense Procurement Memo, Nov, 9, 1998)

  35. Performance Based Payments Some Lessons Learned: Performance Events Examples of bad events: • “Definitization of Contract F12345-99-C-0002: This event is successfully completed upon contractor signature” FAR 32.1004 prohibits using signing of contracts or modifications as performance events; raises fiscal concerns. • “Initiate testing of avionics software” Meaning of “initiate” not clear; no criteria for accomplishment. • “Fabrication complete for forward fuselage; 100,000 hours charged to work order as verified by DCMC.” Charging time not the same as accomplishing work. Is the verification test that fabrication is complete, or hours charged? • “Six months prior to delivery” Not a performance milestone. • “Attendance at Management System Review” Does not show true progress. • “Contractor places orders for all materials for main body assembly.” Since contractor has not acquired title, this raises security concerns.

  36. Performance Based Payments Some Lessons Learned: Payment Amounts Examples of bad PBP amounts: • “90% of actual costs incurred since prior payment.” Must be specific dollar amounts known in advance, not cost reimbursement • “40% of projected costs of next event” [a known amount]. Must be commensurate with value of performed work. This is an advance payment. • “An amount to be determined by contracting officer, taking into account . . . ” Amount must be predetermined and objective. • “Unit price of end items completed at this event.” Must be limited to 90% of price. • “Unit price of end items delivered at this event.” PBPs are not installment payments and not associated with acceptance.

  37. Performance Based Payments A Successful PBP Contract NAVAIR Contract N00019-97-C-0114, for 118 Aircraft Engines • It works because… • Product and processes were well understood by all the parties • Performance events are limited to 7 events per engine • Performance events are clear and understandable, and integral and necessary part of contract performance • e.g. “Receipt of Vane Casting for LPT Nozzle Segment” • Performance verification is clear: • e.g. “Casting received by GE and documented in IMPACT System”

  38. Performance Based Payments Early CAS and Contract Review Checklist • FAR 52.232-32 used if applicable, or other clear clause? (52.232-29 also used if commercial contract?) • Performance events clearly defined? • Are events verifiable by unambiguous standards? • Do events reflect actual work which is integral to performance? • Payment amounts clearly stated? • Do payments appear (a) commensurate with value of undelivered work and (b) adequately secured by title to goods? • If not, what is the security for payment? • Is it clear how payments will be requested? • What surveillance is needed?

  39. Using Performance-Based Payments Linking Contract Financing to Performance and Schedule Advanced Program Management Course Elective 486A Presented By: Timothy Frank Defense Contract Management Agency

More Related