This update presented by Ms. Lil Vayhinger and Ms. Rebecca Davies outlines the goals and progress of the Program Planning and Scheduling Subcommittee (PPSS) as of November 16, 2009. The PPSS aims to enhance program planning and execution within the industry and DoD by developing solutions that ensure consistency and predictability in program schedules. Key initiatives include creating a joint schedule management guide, a comprehensive training curriculum, and a cultural change management plan. The update also details specific product developments, upcoming action plans, and collaborative efforts between government and industry.
E N D
NDIA - ICPM Program Planning and Scheduling Subcommittee Program Planning and Scheduling Subcommittee (PPSS) Update Presented by: Ms Lil Vayhinger and Ms Rebecca Davies 16 November 2009
PPSS Charter Summary Actions and Progress PPSS Next Steps AGENDA
PPSS PPSS Charter Summary
PPSS Charter Summary • The purpose of the PPSS is to define, develop and implement solutions to improve the program planning and execution practices throughout Industry and DoD • The initialfocus will be on gaining consistency, predictability and usefulness of program schedules • Specific deliverable products have been indentified as part of the charter: • Develop a joint Industry and DoD schedule management implementation guide • Develop a joint training curriculum for all levels of Industry and DoD management • Develop approach to favorably influence recruiting, training and retention of planning talent • Sponsor an Industry Day for DoD consultants and software tool vendors • Develop a joint cultural change management plan to be implemented across Industry and DoD
The PPSS is governed by a Management Team, led by Industry and DoD Co-Chairs PPSS Governance and Membership
PPSS Actions and Progress
From 14 September ICPM Meeting: PPSS Next Steps Identify prioritized PPSS PRODUCTS and objectives for each 11/09 Status: In process – PRODUCT status provided on following charts Identify working groups for each of the PRODUCTS 11/09 Status: Complete Establish PRODUCT action plans and milestones 11/09 Status: Initiated (ECD year-end 2009) PPSS “Status to Objectives” The PRODUCTS of the PPSS are targeted for completion and implementation within two years
PPSS PRODUCT Development Progress Enabler: DAU “Knowledge Sharing” E-Room dedicated to PPSS Team Efforts PPSS PRODUCT: • Develop a joint Industry and DoD schedule management implementation guide Status: • NAVAIR/RTN co-developed guide outline • PPSS Members reviewed for content Next Steps: • Develop schedule for populating, reviewing, testing and deploying guide (ECD year-end 2009)
PPSS PRODUCT Development Progress • PPSS PRODUCT: • Develop a joint training curriculum for all levels of Industry and DoD management • Status: • Dave Treacy (NDIA/PMSC and Scheduling Working Group Chair) surveying existing training • Training Sources identified: • Government • Academia/DAU • Industry (Training POC for industry partners identified) • Next Steps: • Collection and categorization information complete for PPSS member review month-end Nov 2009 • Assess training gaps • Develop and deploy detailed plan for training curriculum and deployment Significant training exists… Challenge will be consolidation and deployment
PPSS PRODUCT Development Progress • PPSS PRODUCT: • Develop a set of Generally Accepted Scheduling Principles (GASP) for use in the PPSS governance process • Status: • Final draft GASP has been developed • GASP defines eight principles that describe a valid and effective schedule • 1. Complete 5. Predictive • 2. Traceable 6. Usable • 3. Transparent 7. Resourced • 4. Statused 8. Controlled • Next Steps: • Formally finalize and publish GASP and narratives • Begin applicable governance process using GASP GASP provides a governance framework and forms the basis for other PPSS products
PPSS PPSS Next Steps
PPSS Summary • The PPSS is making good progress thanks to the Government/Industry focus and collaboration • PPSS members are meeting this afternoon to further refine our operating protocol and plan forward • Thanks to the ICPM for their sponsorship