1 / 20

IR Quadrupole Magnet Project

IR Quadrupole Magnet Project. GianLuca Sabbi LARP/Hi-Lumi Collaboration Meeting 20 April 8 , 2013. Outline. Project plans: progress since CM19 Magnet project in the LARP “scope selection” proposal Deliverables, contributions, milestones, funding profile

richter
Download Presentation

IR Quadrupole Magnet Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IR Quadrupole Magnet Project GianLuca Sabbi LARP/Hi-Lumi Collaboration Meeting 20 April 8, 2013

  2. Outline • Project plans: progress since CM19 • Magnet project in the LARP “scope selection” proposal • Deliverables, contributions, milestones, funding profile • DOE feedback and revisions for the next iteration • IR Quadrupole requirements and interfaces (HiLumi DS) • Magnet development: current status and key issues • QXF IR Quadrupole design and development • HQ02, LHQ and additional R&D in support of QXF • Summary: main goals and discussion topics for CM20

  3. Construction Project Proposal • Prepared in response to DOE request following the 2012 review • Funding envelope: 200 M$ construction + 4 more years of LARP at constant funding level • Planning group formed with contributors from all Labs • “Scope selection” proposal submitted to DOE in December • Magnet plan includes: • Completion of R&D on 120 mm aperture models • Development of 150 mm “QXF” prototypes (with CERN) • Infrastructure upgrades for magnet production • Fabrication of cold masses for Q1 and Q3 elements: • 4 m long; 2 pre-series, 16 cold masses and 2 spares • 2 production lines for coils and assembly • All magnets tested in the US before shipping to CERN

  4. Project schedule Prototype development Construction start Production units Spare units Main project phases:

  5. Coil production details • Production plan assumed two facilities working in parallel • Studies by BNL and FNAL with generally consistent results Coil fabrication building block Initial rate (coil 1-10 at each facility) Coil production at maximum rate

  6. Funding Profile • Total IR Quad development and construction: 180M$ • Includes 30% contingency (on construction only) • Project management not included (18M$ with 11% contingency) • Additional R&D not included (proposed as a GARD contribution)

  7. DOE feedback on LARP proposal • Strong support for the magnet project – first priority – but: • Formal project approval (Critical Decision process) will not start for the next several years • Contingent on prototype results and a robust construction plan • Still ok to assume CD-3 in 2017 for planning purposes • Meanwhile, “project-like” approach with “CD-like” reviews • For the near term: update plan and budget assuming: • Flat funding until 2015 - only option to augment LARP resources in 13-14 is through GARD contributions • Additional “pre-project” funds may be available from FY15 to support construction infrastructure and long term procurements

  8. Project plan updates • To date: incorporated most recent information • Agreed on project funding profiles within DOE guidance • Preliminary schedule assessment: additional 6-12 months • At CM20: • Refine QXF development plan, taking “project” approach • Continue discussion on GARD contributions • After CM20: • Obtain formal commitments from contributing parties • Look for possible improvements in production plan • Error bars on magnet portion may have significant effect on the other two projects • Project reviews will follow

  9. Magnet Specifications & Interfaces • Significant progress by the Design Study in the last months • Details will be presented in Monday PM plenary session • Critical new information is being provided: • Baseline layout with magnet position, gradient, length • Cooling options and corresponding channel sizes • Shielding options and corresponding radiation doses • Field quality tables and limits on individual effects • Good news: it appears that we have sufficient flexibility in the overall design to find solutions compatible with available magnet technology in critical areas such as conductor, epoxy resins and mechanical structure design • Further improvements are desirable but not a precondition for successful implementation of Nb3Sn IR Quadrupoles

  10. QXF Design Priorities • Three components are presently on the critical path: • Superconducting cable (required for coil design) • Cable insulation (required for coil design) • Coil fabrication tooling (long procurement time) • In parallel, comparatively large effort on other aspects • Magnetic, mechanical, quench protection, integration… • Need to optimize this investment: • (+) Ensure compatibility of key choices with all requirements • (+) Prepare to move forward rapidly • (−) Avoid detailed optimizations using preliminary specs • May have to be repeated, or worse, • May prematurely “lock” sub-optimal design choices

  11. Cable Optimization Conflicting objectives result in a complex optimization process

  12. Quadrupole cables from TQ to QXF (*) prelim. target values • Larger aperture, energy and forces drive up cable width and aspect ratio • Winding remains challenging: aspect ratio, low keystone, thicker cable • Introduction of core is an additional challenge requiring process changes

  13. QXF cable development status Local RRR– A. Ghosh Cable design & fabrication – Dan Dietderich Cable cross-section micrographs – Dan Dietderich Winding tests – S. IzquierdoBermudez

  14. Comparison with HQ Cable 974R-D3 974R-C2 D. Dietderich, H. Higley, N. Liggins, J. Swanson (2008)

  15. QXF Cable Development Strategy • We are raising the bar in both difficulty and expectations • QXF requirements more challenging than TQ/LQ, HQ/LHQ • …while demanding production-level robustness and margins • Most critical building block for the magnet • Progressively more difficult to make changes as program proceeds • It was agreed to invest additional effort in cable development • Limited delay if tooling design/procurement can proceed • Strategy: perform additional optimization, but in parallel establish clear priorities to enable a decision • Challenges are not only technical • Large and “new” multi-Lab team with different experiences • First benchmark – see what lessons can be learned • High priority for CM20 - Details in Tuesday morning session

  16. Cable insulation and coil tooling • Cable insulation spec also required for coil design • Initial baseline was a braid of 150 mm thickness • Need sample fabrication to confirm dimensions • 125 mm option may be easier to produce • Also attractive in terms of magnetic efficiency • Confirm electrical requirements/trade-offs • Coil tooling is currently on the critical path • Traditionally procured after final coil design • Add features to accommodate expected range • Overall a better approach for first models In both cases, it should be possible to resolve remaining questions during CM20

  17. Recent progress on HQ/LHQ • HQ02 coil series completed: • Reduced compaction, improved insulation, cored cable (presentation by F. Borgnolutti, Monday PM) • HQ02a model assembled: • Achieved pre-load targets and contact with alignment keys • Clear benefits from improvements in coil fabrication • Improved coil uniformity and electrical QA • (presentation by H. Felice, Monday PM) • HQ02 test preparations underway at Fermilab • Positive feedback from mechanical model of HQ alternate structure • (presentation by J. Schmaltzle, Monday PM) • First LHQ coil wound and cured • (presentation by Miao Yu, Monday PM)

  18. HQ and LHQ status HQ02a pre-load HQ02a impulse test Assembled HQ02a magnet Alt. structure model Fabrication of first LHQ practice coil

  19. Future R&D in support of QXF • Available platforms can efficiently support QXF and HiLumi DS • Details were covered in CM19 presentation • Current plan includes HQ02 and LHQ mirror • No firm plans to carry out additional R&D beyond that • Leaves 1-2 year gap: • HQ02 testing complete in 2013, first SQXF test in mid-2015 • LHQ complete by mid-2014, first LQXF test in early 2016 • We need to find the optimal balance: • Provide needed resources for QXF to move forward quickly • Provide experimental feedback on key issues in the interim • Important topic for CM20 discussion and recommendations • Significant opportunities for GARD contributions in this area

  20. Summary and CM20 topics • Discuss project plan updates/refinements and prepare reviews • QXF - technical • Cable assessment, next optimization steps, design selection criteria • Resolve remaining questions on cable insulation & tooling design • QXF - planning and schedule: • Efficiency: use of infrastructure, avoid duplications of effort etc. • Balance/priority between short and long models • Technical: initial focus on short models, then scale-up • DOE review: emphasis on long prototypes to enable project start • How to formalize and manage contributions from different parties • R&D in support of QXF and the HiLumi design study: • Evaluation of HQ/LHQ results and next steps • Future needs and optimal resource balance • Continue discussion on GARD contributions

More Related