1 / 11

Projects Update

Projects Update. Quarterly Meeting of the Technical Oversight Committee June 30, 2009 Jeff Kivett, P.E. South Florida Water Management District. EAA Compartment C STA Buildout.

renata
Download Presentation

Projects Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Projects Update Quarterly Meeting of the Technical Oversight Committee June 30, 2009 Jeff Kivett, P.E. South Florida Water Management District

  2. EAA Compartment C STA Buildout Purpose: The development of additional Stormwater Treatment Area (STA) to further improve the quality of water discharging to the Everglades Protection Area (EPA) by assisting with the redistribution of flows and loads to the STA system. Completed • Phase 1 – Initial Expansion • STA-5 Flow-way 3 (1,985 Acres of Treatment Area) • STA-6 Section 2 (1,387 Acres of Treatment Area) • Phase 2 Build-Out • Design of Civil Works(4,850 Acres of Treatment Area) • Pump Equipment Contract executed • Pump Station Final Design

  3. EAA Compartment C STA Buildout • Accomplishments to Date: • Complete Final Design-Civil Works • Completed Final Design-Pump Station • Purchased Pumps, Gear Reducer and Engines for Pump Station • Civil Works contract awarded at March Governing Board • USACE completed Record of Decision and Compartment C 404 permit prior to March 12, 2009 Governing Board • Land Use Change received • Started Construction – Civil Works • NTP April 6, 2009 • What’s Next: • Bid Solicitation of G-508 Pump Station • Pump Equipment Manufacturing • Start construction of pump station • NTP scheduled for September 2009 • Construction Completion • Flow Capable Civil Works 2010 • Permanent Pump Station 2011

  4. Compartment C G-508 Pump Station Issue for Bid June 24, 2009 Bids due July 28, 2009 Contract Award August 2009 NTP September 2009

  5. Clearing at Intermediate Levee at STA5-5B looking north

  6. Left slope in the picture is Discharge levee at STA5-4B

  7. Compartment B North Build-out Cell 2 Cell 3 Cell 1 STA 2 Cell 4 South Build-out Purpose: The development of additional Stormwater Treatment Area (STA) to further improve the quality of water discharging to the Everglades Protection Area (EPA) by assisting with the redistribution of flows and loads to the STA system. EAA Compartment B STA Buildout Completed • Phase 1 – Initial Expansion • STA-2 Cell 4 (1,902 Acres of Treatment Area) • Phase 2 - Build-out (6,722 Acres of Treatment Area) • Design of Civil Works • Pump Station Final Design Report • Pump Equipment Contract executed

  8. EAA Compartment B STA Buildout • Accomplishments to date: • Complete Final Design-Civil Works • Completed Final Design-Pump Stations • Complete Pump Equipment Contract Process • FDEP Permit received on March 17, 2009 with condition to re-design project discharge to Water Conservation Area 2A • USACE Permit Decision received May 2009 • What’s next: • Started Construction – Civil Works • NTP June 1, 2009 for North and South Buildouts • Complete Final Design Bid Solicitation Decision - Pump Stations • Issue Bid Solicitations for construction of Pump Stations • Re-Design of Project Discharge at L-6 Canal to Water Conservation Area 2A • Construction Completion • Flow Capable Civil Works – December 2010 • Permanent Pump Stations 2011

  9. Compartment B Pump Stations G-435   Issued for Bid May 22, 2009 Bids due June 29, 2009 Contract Award August 2009 NTP September 2009 G-434 & G-436              Issued for Bid June 2, 2009 Bids due July 7, 2009 Contract Award August 2009 NTP September 2009

  10. L-6 Canal Modification Conceptual Design due June 29, 2009 • Intermediate Design due September 18, 2009 • Pre-final design due November 20, 2009 • Final Design due January 19, 2010 • Bid Solicitation March 2010 • Contract Award April 2010 and NTP May 2010

  11. Okeelanta Bridge pre-cast decking prior to post-tensioning

More Related