1. 1 Modernization of I&C systems at theNPP Krko
2. 2 Introduction NPP Krko
Major NPP Krko (I&C) systems modifications implemented since 1983
Process Information System (PIS)
Annunciator System Replacement
Slovenian (I&C) legislation
Conclusion
3. 3 NPP Krko Westinghouse
2 loop PWR
capacity 700 MWe
investment of republic Slovenia and Croatia
architect engineering - Gilbert
decision for construction - 1970
beginning of operation - September, 1981
synchronisation to electric network - October, 1981
commercial operation - January, 1983
4. 4 Major NPP Krko I&C systems modifications implemented since 1983 ATWS Mitigation Safeguard Actuation Circuitry (AMSAC)
Inadequate Core Cooling Monitoring System (ICCMS)
Process Information System (PIS)
Annunciator System
Off-line data acquisition of chemical analysis data (prim & sec. sampling) - Chemnet
RCP and TU Vibration monitoring
Core Monitoring and Operations Support System, BEACON-TSM System
Meteorological Monitoring System
Seismic Instrumentation
5. 5 Major NPP Krko I&C systems modifications implemented since 1983, cont. SG Blowdown Control (digital discrete controllers and digital indicators)
Heater Drain Control, PLC
Condensate Polishing, PLC
Water Treatment, PLC
Switchyard Control & Monitoring (ABB Micro SCADA - although it has remote control capabilities in the MCR it is used for switchyard monitoring only)
Emergency Response Data System (ERDS)
FP- Fire protection (Detection) system
6. 6 Process Information System (PIS) The Process Information System (PIS) was installed in NEK in 1992 as part of the post TMI requirements
The main purpose of the PIS was to monitor critical functions (Critical Function Monitoring System - CFMS)
CFMS was designed to meet SPDS (Safety Parameter Display System) requirements of NUREG-0696 (Functional Criteria For Emergency Response Facilities), NUREG-0737 (Clarification of TMI Action Plan Requirements) Item I.D.2, and NUREG-0737 Supplement 1
Major features of the CFMS include:
A Critical Safety Function Monitor which defines conditions to assess the status of six critical safety functions (criticality, core cooling, heat sink, RCS integrity, containment and RCS inventory),
Engineering Safety Features equipment monitoring
Plant process and area radiation monitoring, and
Meteorological conditions monitoring
7. 7 Process Information System (PIS) Other functions of the PIS are:
Insufficient Core Cooling Monitoring System (ICCMS)
Post-trip review data acquisition
Nuclear process calculations
Primary to secondary leakage calculations
Calorimetric calculations
QPTR evaluations
PIS is a non-safety related system used to provide supplementary information to the operator and to inform him of off-normal conditions
Data is collected by the redundant data acquisition equipment and transmitted to a fully redundant distributed computer system
PIS data is also obtained from other process computers through separate serial or fast Ethernet communication links
8. 8 Process Information System (PIS) Last upgrade of PIS system (May 2006) included:
Wax replaced with Alpha technology
The newest ABB PMS platform
New data connections (MicroScada, Beacon, VibMon, CK-CPS)
Upgraded application software inclusion of ARP procedures
GPS time synchronization
The effects of the upgrade were:
Improvement of overall PIS performance and availability during transients
Expanding the PIS capability to receive and send process parameters to different process computers
Easier and less expensive maintenance
PIS can now also be used for issuing commands to other non-safety digital control systems
Issues during licensing:
Effects on safety systems (control room ventilation)
Expansion of PIS functions to control other systems
9. 9 Annunciator System Replacement former Annunciator System (Betalarm1000)
gathered a switching contact and controlled the operation of a lampbox to turn on and off a dedicated lamp window
was installed 25 years ago and it was becoming increasingly more difficult to provide technical support and replacement parts
new Annunciator System (SER4100 & BL1500)
use of flagship sequential event recorder to record switching contact which are time stamped and processed to a number of outputs (annunciators, visual display units, printers and computer for data archiving and post analysis)
the BL1500 has been designed to have the identical form factors as the lampboxes supplied 25 years ago with the BL1000.
therefore the operators were presented with an identical control room as before the installation
10. 10 Annunciator System Replacement Advantages of the new system:
Event recording
Post event analysis
Redundancy
Expandability
Re-configuration flexibility
Advanced Alarm Filtering capabilities
Availability of spares
11. 11 Annunciator System Replacement Open issue during licensing:
approval of software
SNSA has taken into consideration:
system standards list
NPP reference list
Post-performance problem
inoperability of power supplier
new configuration without power supply redundancy
12. 12 Slovenian (I&C) legislation ZVISJV: Act on protection against ionizing radiation and nuclear safety (Official Gazette of the Republic of Slovenia no. 67/2002, 24/2003, 46/2004)
Reg. E1: Regulation on the conditions for siting, construction, commissioning, commencement of operation and operation of nuclear facilities (Official Gazette of the SFRJ no. 52/88)
Reg. E2: Regulation on the compilation and contents of the safety report and other documentation necessary for the assessment of the safety of nuclear facilities (Official Gazette of the SFRJ no. 68/88)
Some WENRA requirements on I&C systems are already included in current Slovenian nuclear legislation, and also new regulation (consistent with WENRA) is being prepared
Most of the WENRA requirements are already implemented in the Krko NPP
13. 13 Conclusion During the 20 years of commercial operation more than 400 modifications (and a lot of this modifications are related with I&C system) have been implemented in the NPP Krko
The next important modifications will be the DEH (Digital Electro Hydraulic) system for the control and supervision of the TG (Turbine-Generator) set (scheduled for outage 2007)
All of these modifications are performed on the non-safety related I&C system
New regulations will be in compliance with the WENRA requirements
14. 14 Thank you for your attention!