NATIONAL CONFERENCE OF PROJECT DIRECTORS (DRDAs)

Loading in 2 Seconds...

play fullscreen
1 / 26

NATIONAL CONFERENCE OF PROJECT DIRECTORS (DRDAs) - PowerPoint PPT Presentation


  • 86 Views
  • Uploaded on

NATIONAL CONFERENCE OF PROJECT DIRECTORS (DRDAs). PRESENTATION BY DEPARTMENT OF LAND RESOURCES 22.6.2011. Area Development Programmes. DoLR has been implementing three programmes on watershed basis since 1995-96. Drought Prone Areas Programme Desert Development Programme

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'NATIONAL CONFERENCE OF PROJECT DIRECTORS (DRDAs)' - rania


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
national conference of project directors drdas

NATIONAL CONFERENCE OFPROJECT DIRECTORS (DRDAs)

PRESENTATION

BY

DEPARTMENT OF LAND RESOURCES

22.6.2011

area development programmes
Area Development Programmes

DoLR has been implementing three programmes on watershed basis since 1995-96.

  • Drought Prone Areas Programme
  • Desert Development Programme
  • Integrated Wastelands Development Programme
slide4
IWMP
  • Now the 3 progs.- integrated into one prog. IWMP- under Common Guidelines for Watershed Dev. Projects, 2008.
  • Objectives:
  • Restoring ecological balance
  • Conserving & dev. degraded nat. res.- soil/veg. cover & water
  • Prevention of soil run-off
  • Regeneration of natural vegetation
  • Rain water harvesting & recharging of ground water table
  • Introduction of multi-cropping & diverse agro-based activities
  • Promoting sustainable livelihoods

4

abstract of cumulative progress w e f 1 4 95 area in million ha rs in crore as on 1 4 2011
Abstract of Cumulative Progress(w.e.f.1.4.95, Area in million Ha, Rs. in crore) (as on 1.4.2011)
completion of hariyali projects
Completion of Hariyali Projects
  • Dec. 2012 - cut off date of Hariyali projects.
  • Proposals for final installment of hariyali projects (sanctioned upto 2005-06) may be clubbed together along with prescribed documents for last installment.
issues
Issues
  • Delay in flow of funds from DRDAs/ZPs to PIA
  • Non-submission/delayed submission/submission of incomplete release proposals
  • Online reporting of QPRs for all projects at www.watershed.nicnot being done
  • Pending UCs - 1056 no. amounting to Rs. 736.26 Cr. (as on 31.03.2011)
  • Unspent balance - Rs. 2428.02 cr. (as on 31.03.2011) (DPAP-Rs.322.45 cr., DDP- Rs. 259.52 cr., IWDP – Rs. 290.90 cr. & IWMP – Rs. 1555.48 cr.)
important points for drdas zps
Important points for DRDAs/ZPs
  • Advances to PIA - not to be accounted as expenditure.
  • Documents for submission to DoLR to be signed by PD.
  • UCs & ASAs - in original & separately for each FY.
  • OB and CB of UCs to be matched with OB and CB of ASAs of the corresponding year.
  • Exit Protocol to be clearly defined.
  • Foreclosed projects – year-wise UC, ASAs & Progress report & refunding unspent balance, if any
important points for drdas zps contd
Important points for DRDAs/ZPs …(contd.)
  • After release of 45% of project cost, MTER properly graded & duly signed - for timely release of next installment.
  • ATR on MTER - details of follow up action taken/to be taken.
  • After release of all installments, completion report, final UC/ASA & final evaluation report of project - unspent amount with accrued interest to be refunded.
  • The project wise details of actual area converted from wasteland to agricultural land / productive land.
delay in completion of projects
Delay in Completion of Projects
  • 12,567 ongoing pre-IWMP projects are to be completed by December, 2012.
  • Delay mainly due to non-submission/ incomplete submission/ delayed submission of release proposals.
  • Most of the cases are delayed at the time of release of 2nd installment & MTER stage - 3rd(Hariyali) .
  • Monitoring of delayed projects; review performance and in case feasible, extension proposal and action plan with commitment for completion with in extended period.
post project evaluation
Post Project Evaluation
  • So far, 26,536projects under 3 schemes - completed. However:
  • Post project evaluation report and completion report have not been submitted for majority of these projects.
  • PDs should ensure furnishing of completion report, final UC, ASAs, post project evaluation report and refund of unspent balance to GoI.
iwdp status as on 31 5 2011
IWDP – Status as on 31.5.2011

Average

45-71%

Good

>71%

Poor

iwdp status as on 31 5 201117
IWDP – Status as on 31.5.2011

Average

45-71%

Good

>71%

Poor

iwdp status as on 31 5 201118
IWDP – Status as on 31.5.2011

Average- 45-71%

Good

>71%

Poor

dpap status as on 31 5 2011
DPAP – Status as on 31.5.2011

Good

>58%

Average

40-58%

Poor

dpap status as on 31 5 201121
DPAP – Status as on 31.5.2011

Good

>58%

Average

40-58%

Poor

ddp status as on 31 5 2011
DDP – Status as on 31.5.2011

Average

45-62%

Good

>62%

Poor

slide23

Pending UCs (as on 31.05.2011)

(Amount – Rs. in crores)

slide25

Pending UCs (as on 31.5.2011)….Contd.

(Amount – Rs. in crores)

25