Create task dependency links. It’s time to learn how to create links between tasks and after that, to think about when to link them. If you move a task or insert a new task, Project automatically links it in the same way as the tasks around it.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Create task dependency links' - randi


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
create task dependency links
Create task dependency links

It’s time to learn how to create links between tasks and after that, to think about when to link them.

If you move a task or insert a new task, Project automatically links it in the same way as the tasks around it.

By getting all of your tasks in order first, you make sure that the link you like stays just the way you want it.

Linking Project tasks

create an fs dependency
Create an FS dependency

After you’ve identified two tasks that will be dependent on each other, identify one task as the predecessor.

Then select the predecessor task by clicking its ID number.

Next, press the CTRL key and select the task that will be the successor of the task that you have already selected.

Then, click Link Tasks on the Standard toolbar.

Linking Project tasks

create an fs dependency3
Create an FS dependency

After you’ve identified two tasks that will be dependent on each other, identify one task as the predecessor.

Then select the predecessor task by clicking its ID number.

If you need to remove a dependency link:

  • Select the linked tasks. The order of selection does not matter.
  • Click Unlink on the Standard toolbar.

Linking Project tasks

type dependencies in the predecessors column
Type dependencies in the Predecessors column

What if you need to set dependencies between tasks that are quite far apart in the Project plan?

Project provides a simple solution, as shown in Figure 1:

You can create dependency links by typing directly in the Predecessors column.

Linking Project tasks

type dependencies in the predecessors column5
Type dependencies in the Predecessors column

What if you need to set dependencies between tasks that are quite far apart in the Project plan?

First, note the predecessor task’s ID number. Then, scroll to the task that will become its successor.

In the Predecessors field of the successor task, type the predecessor task’s ID number and the appropriate dependency abbreviation: SS, FF, FS, or SF.

Linking Project tasks

type dependencies in the predecessors column6
Type dependencies in the Predecessors column

What if you need to set dependencies between tasks that are quite far apart in the Project plan?

To remove a dependency link from the Predecessors column, select the ID number of the predecessor task, and then press the DELETE key.

Linking Project tasks