Opermgt 345 January, 2001 Project ManagementBasic Concepts
What is a Project? A Project is a series of activities and tasks that: Have a specific objective to be completed with certain objectives Have a defined start and end dates Have funding limits (if applicable) Consume Resources
Typical Project Structure Project Definition Project Monitoring Project Planning Project Implementation Project Evaluation Project Adjustment
Project Life Cycle Resources and Effort Phase 1 Phase 2 Phase 3 Phase 4 Phase 5 Conceptual Design Advanced Development Detailed Design Project Implementation Project Termination • Goals • Scope • Baseline • Requirements • Feasibility • Desirability • Plan • Budget • Schedule • Management • Commitment • Define • Responsibility • Team • Organization • Structure • Detailed Plan • Kickoff • Manage • Measure • Control • Update and • Modify Plan • Problem Solve • Closeout • Document • Suggest • Improvements • Reassign • Dissolve Project • Team
Successful Projects A successful project is one which achieves the following objectives: • Completed On Time • Completed Within Cost • Meets Performance Criteria • Minimum Disruption of the Main Work of the Organization • Effective Utilization of Resources
The Triple Play ofProject Management Constraints Time Cost Performance
Triple Constraint Trade-offs $ Budget Better Performance Specifications Worse Schedule Early Late TIME
Major causes of failure • Selection of a unsound project • Selecting the wrong person as a project manager • Lack of support from upper management • Misused management techniques • Project termination not planned
Project Definition Build Canoe Rental Building on Coeur d A’lene Lake
Form Project Team • Select Project Leader • Identify Key People • Gain Management Commitment • Define Project Team Operating Rules
The Top Level Project Tasks Brainstorm the Major Tasks C Establish Work Flow B G A D E F
Define Top Level TasksCanoe Example Site Preparation Build Dock Build Building Finish and Ready for Business
Sequence Top Level Tasks Build Dock Finish Site Preparation Build Building
Sub-Tasks Detailed Tasks C G B A D E F Develop Work Sequence Detailed Tasks
Brainstorm Sub-Tasks Site Preparation Build Dock Build Building Finish Dock Site Install Pilings Foundation Order Canoes Frame Landscape Building Site Build Dock Roof Assemble Canoes Power Siding Open for Business Paint
Work Breakdown Structure Top Level Task 2nd Level Task 2nd Level Task 2nd Level Task 2nd Level Task 3rd Level Task 3rd Level Task 3rd Level Task 3rd Level Task 3rd Level Task 3rd Level Task 3rd Level Task 3rd Level Task 3rd Level Task Lower Level Tasks
Sequence Sub-Tasks Task Description Immediate Predecessor A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canoes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M
Build Network Diagram(PERT Chart)(Activities on Arrows) 1 Task Predecessor A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M
Build Network Diagram(PERT Chart) A 1 3 Prep Dock Site Task Predecessor A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M
Build Network Diagram(PERT Chart) 2 J Order Canoes A 1 3 Prep Dock Site Task Predecessor A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M
Build Network Diagram(PERT Chart) 2 J Order Canoes A 1 3 Prep Dock Site B Task Predecessor Prepare Hut Site A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M 4 D Hut Foundation 6
Build Network Diagram(PERT Chart) 2 J Order Canoes A C E 1 3 5 9 Prep Dock Site Install Pilings Build Dock B Task Predecessor Prepare Hut Site A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M 4 D Hut Foundation 6
Build Network Diagram(PERT Chart) 2 J Order Canoes A C E 1 3 5 9 Prep Dock Site Install Pilings Build Dock B Task Predecessor Prepare Hut Site A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M G Power To Hut 4 D Hut Foundation 6
Build Network Diagram(PERT Chart) 2 L J Order Canoes Assemble Canoes A C E 1 3 5 9 Prep Dock Site Install Pilings Build Dock B Task Predecessor Prepare Hut Site A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M G Power To Hut 4 D Hut Foundation 6
Build Network Diagram(PERT Chart) 2 L J Order Canoes Assemble Canoes A C E 1 3 5 9 Prep Dock Site Install Pilings Build Dock B Task Predecessor Prepare Hut Site A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M G Power To Hut Roof 4 I D Hut Foundation F 6 7 Frame Hut
Task Predecessor A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M Build Network Diagram(PERT Chart) 2 L J Order Canoes Assemble Canoes A C E 1 3 5 9 Prep Dock Site Install Pilings Build Dock B Prepare Hut Site G Power To Hut Paint Hut Roof K 4 I D Hut Foundation F H 6 7 8 Frame Hut Side Hut
Task Predecessor A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M Build Network Diagram(PERT Chart) 2 L J Order Canoes Assemble Canoes A C E M N 1 3 5 9 10 11 Prep Dock Site Install Pilings Build Dock Finish Landscape Open for Business B Prepare Hut Site G Power To Hut Paint Hut Roof K 4 I D Hut Foundation F H 6 7 8 Frame Hut Side Hut
Task Description Time Build Network Diagram(PERT Chart) Canoe ExampleAdd Times A Prepare Dock Site 3 d B Prepare Hut Site 4 d C Install Dock Pilings 6 d D Foundation for Hut 3 d E Build Dock 4 d F Frame Hut 3 d G Power to Hut 2 d H Side the Hut 2 d I Roof the Hut 3 d J Order Canoes 2 d K Paint Hut 4 d L Assemble Canoes 10 d M Finish Landscaping 4 d NOpen for Business 2 d 2 L (10) J (2) Order Canoes Assemble Canoes A (3) C (6) E (4) M (4) N (2) 1 3 5 9 10 11 Prep Dock Site Install Pilings Build Dock Finish Landscape Open for Business B (4) Prepare Hut Site G (2) Power To Hut Paint Hut Roof K (4) 4 I (2) D (3) Hut Foundation F (3) H (2) 6 7 8 Frame Hut Side Hut
Task Predecessor A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M Build Network Diagram(PERT Chart) 2 L J Order Canoes Assemble Canoes A C E M N 1 3 5 9 10 11 Prep Dock Site Install Pilings Build Dock Finish Landscape Open for Business B Prepare Hut Site G Power To Hut Paint Hut Roof K 4 I D Hut Foundation F H 6 7 8 Frame Hut Side Hut
Task Description Time Build Network Diagram(PERT Chart) Canoe ExampleAdd Times A Prepare Dock Site 3 d B Prepare Hut Site 4 d C Install Dock Pilings 6 d D Foundation for Hut 3 d E Build Dock 4 d F Frame Hut 3 d G Power to Hut 2 d H Side the Hut 2 d I Roof the Hut 3 d J Order Canoes 2 d K Paint Hut 4 d L Assemble Canoes 10 d M Finish Landscaping 4 d NOpen for Business 2 d 2 L (10) J (2) Order Canoes Assemble Canoes A (3) C (6) E (4) M (4) N (2) 1 3 5 9 10 11 Prep Dock Site Install Pilings Build Dock Finish Landscape Open for Business B (4) Prepare Hut Site G (2) Power To Hut Paint Hut Roof K (4) 4 I (2) D (3) Hut Foundation F (3) H (2) 6 7 8 Frame Hut Side Hut
Determining Project Length Option 1: Sum all the task durations: A Prepare Dock Site - 3 d B Prepare Hut Site - 4 d C Install Dock Pilings A 6 d D Foundation for Hut B 3 d E Build Dock C 4 d F Frame Hut D 3 d G Power to Hut D 2 d H Side the Hut F 2 d I Roof the Hut F 3 d J Order Canoes and Receive Canoes - 2 d K Paint Hut H 4 d L Assemble Canoes J 10 d M Finish Landscaping L,I,K,E,G 4 d N Open for Business M 2 d Sum = 52 days Anything wrong with this approach?
Determining Project Length Option 2: Determine duration of each network path
Network DiagramProject Paths Paths: A-C-E-M-N = 19 days 2 L (10) J (2) Order Canoes Assemble Canoes A (3) C (6) E (4) M (4) N (2) 1 3 5 9 10 11 Prep Dock Site Install Pilings Build Dock Finish Landscape Open for Business B (4) Prepare Hut Site G (2) Power To Hut Paint Hut Roof K (4) 4 I (2) D (3) Hut Foundation F (3) H (2) 6 7 8 Frame Hut Side Hut
Network DiagramProject Paths Paths: A-C-E-M-N = 19 days B-D-F-H-K-M-N = 22 days 2 L (10) J (2) Order Canoes Assemble Canoes A (3) C (6) E (4) M (4) N (2) 1 3 5 9 10 11 Prep Dock Site Install Pilings Build Dock Finish Landscape Open for Business B (4) Prepare Hut Site G (2) Power To Hut Paint Hut Roof K (4) 4 I (2) D (3) Hut Foundation F (3) H (2) 6 7 8 Frame Hut Side Hut
Network DiagramProject Paths Paths: A-C-E-M-N = 19 days B-D-F-H-K-M-N = 22 days B-D-F-I-M-N = 18 days 2 L (10) J (2) Order Canoes Assemble Canoes A (3) C (6) E (4) M (4) N (2) 1 3 5 9 10 11 Prep Dock Site Install Pilings Build Dock Finish Landscape Open for Business B (4) Prepare Hut Site G (2) Power To Hut Paint Hut Roof K (4) 4 I (2) D (3) Hut Foundation F (3) H (2) 6 7 8 Frame Hut Side Hut
Network DiagramProject Paths Paths: A-C-E-M-N = 19 days B-D-F-H-K-M-N = 22 days B-D-F-J-M-N = 18 days B-D-G-M-N = 15 days 2 L (10) J (2) Order Canoes Assemble Canoes A (3) C (6) E (4) M (4) N (2) 1 3 5 9 10 11 Prep Dock Site Install Pilings Build Dock Finish Landscape Open for Business B (4) Prepare Hut Site G (2) Power To Hut Paint Hut Roof K (4) 4 I (2) D (3) Hut Foundation F (3) H (2) 6 7 8 Frame Hut Side Hut
Network DiagramProject Paths Paths: A-C-E-M-N = 19 days B-D-F-H-K-M-N = 22 days B-D-F-J-M-N = 18 days B-D-G-M-N = 15 days J-L-M-N = 18 days 2 L (10) J (2) Order Canoes Assemble Canoes A (3) C (6) E (4) M (4) N (2) 1 3 5 9 10 11 Prep Dock Site Install Pilings Build Dock Finish Landscape Open for Business B (4) Prepare Hut Site G (2) Power To Hut Paint Hut Roof K (4) 4 J (2) D (3) Hut Foundation F (3) H (2) 6 7 8 Frame Hut Side Hut
Critical Path The Critical Path is the Longest Path Through the Network.
Network Diagram Canoe ExampleCritical Path Paths: A-C-E-M-N = 19 days B-D-F-H-K-M-N = 22 days B-D-F-J-M-N = 18 days B-D-G-M-N = 15 days J-L-M-N = 18 days 2 L (10) J (2) Order Canoes Assemble Canoes A (3) C (6) E (4) M (4) N (2) 1 3 5 9 10 11 Prep Dock Site Install Pilings Build Dock Finish Landscape Open for Business B (4) Prepare Hut Site G (2) Power To Hut Paint Hut Roof K (4) 4 I (2) D (3) Hut Foundation F (3) H (2) 6 7 8 Frame Hut Side Hut
Completed Task Timetable Task Description Immediate Predecessor Time ES LS EF LF A Prepare Dock Site - 3 d 0 3 3 6 B Prepare Hut Site - 4 d 0 0 4 4 C Install Dock Pilings A 6 d 3 6 9 12 D Foundation for Hut B 3 d 4 4 7 7 E Build Dock C 4 d 9 12 13 16 F Frame Hut D 3 d 7 7 10 10 G Power to Hut D 2 d 7 14 9 16 H Side the Hut F 2 d 10 10 12 12 I Roof the Hut F 3 d 10 13 13 16 J Order Canoes and Receive Canoes - 2 d 0 4 2 6 K Paint Hut H 4 d 12 12 16 16 L Assemble Canoes J 10 d 2 6 12 16 M Finish Landscaping L,I,K,E,G 4 d 16 16 20 20 N Open for Business M 2 d 20 20 22 22
Slack Time Total Slack = The length of time an activity can be delayed without affecting the project completion time. Total Slack = Late Start - Early Start Total Slack = Late Finish - Early Finish For Critical Activities Free Slack = The time a task can be delayed without delaying another task.
Slack Time Task Description Immediate Predecessor Time ES LS EF LF Slack A Prepare Dock Site - 3 d 0 3 3 6 3 B Prepare Hut Site - 4 d 0 0 4 40 C Install Dock Pilings A 6 d 3 6 9 12 3 D Foundation for Hut B 3 d 4 4 7 7 0 E Build Dock C 4 d 9 12 13 16 3 F Frame Hut D 3 d 7 7 10 10 0 G Power to Hut D 2 d 7 14 9 16 7 H Side the Hut F 2 d 10 10 12 12 0 I Roof the Hut F 3 d 10 13 13 16 3 J Order Canoes and Receive Canoes - 2 d 0 4 2 6 4 K Paint Hut H 4 d 12 12 16 16 0 L Assemble Canoes J 10 d 2 6 12 16 4 M Finish Landscaping L,I,K,E,G 4 d 16 16 20 20 0 N Open for Business M 2 d 20 20 22 22 0
Critical Path Tasks Critical Path = All tasks with slack = zero
Critical Path Tasks Task Description Immediate Predecessor Time ES LS EF LF Slack A Prepare Dock Site - 3 d 0 3 3 6 3 B Prepare Hut Site - 4 d 0 0 4 40 *** C Install Dock Pilings A 6 d 3 6 9 12 3 D Foundation for Hut B 3 d 4 4 7 7 0 *** E Build Dock C 4 d 9 12 13 16 3 F Frame Hut D 3 d 7 7 10 10 0 *** G Power to Hut D 2 d 7 14 9 16 7 H Side the Hut F 2 d 10 10 12 12 0 *** I Roof the Hut F 3 d 10 13 13 16 3 J Order Canoes and Receive Canoes - 2 d 0 4 2 6 4 K Paint Hut H 4 d 12 12 16 16 0 *** L Assemble Canoes J 10 d 2 6 12 16 4 M Finish Landscaping L,I,K,E,G 4 d 16 16 20 20 0 *** N Open for Business M 2 d 20 20 22 22 0 *** Critical Path = B - D - F - H - K - M - N