COOPER HALL RENOVATION

COOPER HALL RENOVATION. Cooper Hall Project History. Phase I Mechanical System upgrades $2.3M Submitted by EUP to SSHE August 1988 Approved Act 223 of 1990 $2,340,000 Funding Released twelve years later in January of 2002 $1,950,000 Construction

radwan
Download Presentation

COOPER HALL RENOVATION

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. COOPER HALL RENOVATION

  2. Cooper Hall Project History • Phase I Mechanical System upgrades $2.3M • Submitted by EUP to SSHE August 1988 • Approved Act 223 of 1990 $2,340,000 • Funding Released twelve years later in January of 2002 • $1,950,000 Construction • $ 390,000 Design & Construction Contingency

  3. Cooper Hall continued • Phase II Renovation and Addition • Request Submitted to PaSSHE August 1998 • Approved Act 35 of 1999 $10,688,000 • Authorization Expired June 16,2003 • Resubmitted to PaSSHE for Reauthorization August 2002 $15,500,000

  4. Cooper Hall Continued • Resubmitted to PaSSHE May 2003 for 04/05 Budget @ $16,100,000 • August 2003 Project programmed into PaSSHE 5 year spending plan pending reauthorization @ $16,500,000 • Resubmitted to PaSSHE April 2004 for 05/06 Budget @ $21,011,397 • Project Approved by Legislature in Act 40 of 2004 with total authorization of $23,000,000

  5. Cooper Hall Continued • Project funding was released up to $23,000,000 by the Budget Office in February 2006 with funding combined from both Act 40 and Act 223 projects. • $19,450,000 Construction and $3,890,000 design and contingency. • The Department of General Services (DGS) Selection Committee short-listed 3 firms • The DGS Secretary selected Astorino Architects as the design firm in August 2006

  6. Cooper Hall continued • Memorandum of Understanding (MOU) for Project Delegation was received by PaSSHE from DGS in October 2006 • Final MOU received from PaSSHE / DGS legal by EUP February 22, 2007 • Architectural Contract Fee Negotiations are concluded March 2007 • Contracts signed by EUP and Astorino in March 2007 and we anticipate the signed contract to be returned from the Commonwealth Attorney within the next week

  7. Cooper Hall Advisory Group Dr. Eric Randall Dr. Naod Kebede Dr. Craig Van Bell Dr. Brian Zimmerman Mr. Appi Alla Mr. Tom Anderson Mr. William Coleman Mr. Jason Finck Mr. Walter Patterson Ms. Kerri Watson

  8. Tentative Project Schedule • Design begins June 2007 • Schematic Design Completed Jan 08 • Design completed June 2009 • Bid and Award Contracts by Nov 2009 • Construction begins Dec 09 • Construction completed Nov 2011 • Entire building occupied by Jan 2012