Seizure Recovery System For Fuel System Distributor
Follow Team #11's progress on the manufacturing, stress analysis, and assembly of the Seizure Recovery System sponsored by Cummins Engine Company. See details on current activities and future project tasks in this report.
Seizure Recovery System For Fuel System Distributor
E N D
Presentation Transcript
Seizure Recovery System For Fuel System Distributor Progress Report Sponsored by Cummins Engine Company Team #11 Michal Brown, Keron Miller, Sean Edwards, Ben Nuttall
Current Progress: Manufacturing drawings have been completed Materials have been selected Stress analysis of the parts has been performed
Current Activities: • Scheduling shop time with machine shop supervisor • Purchasing materials and necessary tools • Confirming final design with client • Determining optimal assembly techniques • Modifying manufacturing drawings as minor changes are made
Future Project Tasks: • Machining of the parts and final assembly is scheduled to be completed the week before spring break • The assembled prototype will be sent to Cummins for testing • Possible design changes may be necessary as feedback is received from client regarding product testing