An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MICE PSAGPM report • MPB summary • Re-organising the UK Project Management • Schedule • Spectrometer solenoid update • Space, people and substation Andy Nichols, STFC, PSAG, 11/11/10

  2. MPB (MICE Project Board) Summary • Inaugural MPB meeting was held on 24th September • Chair is Steve Peggs of BNL • Formal written feedback from MPB is awaited • Main points below, based on our notes only: • Management of the international project is much too light • The UK project is in good shape • The major international deliverables need understanding better as they are the major schedule drivers • MPB requested a revised top-level MICE schedule by mid-December, 2010 • Which incorporates ‘at-a-glance’ dates for the major subsystems • Necessarily adaptive approach to project organisation is welcome and seems to be working

  3. Project Board Summary • Concept of a ‘Magnet Co-ordinator’ unanimously endorsed • UK project management should be reinforced to backfill extra international PM effort • PM needs to be able to trust his inputs to the schedule • MICE does not have a solid Project Management structure in place • RF testing in CERN magnet was recommended • Milestone slippage due to skills/people shortage acknowledged as a real project risk • None of this is really news to us

  4. Re-organising the UK Project • Very tentative discussions started, main difficulty is availability of people and competition from other projects (surprise!) • But it might look like this: • International: PM – AN • Magnet Coordinator – RP • Integration Engineer – JST • UK: PM – TH/IW • System Engineer – TH/IW • Project Associate – AL • DL PM - AG • This fits with the model proposed to us last year by Gary Rae of UKATC

  5. Run date: Where we were last PSAG……… m Sep-Dec 2009 STEP I This is where we hoped to be NOW STEP II Q2/Q3 2010 Schedule under review, directly dependent on S/Sol. Aim to be ready with Step IV in Q2, 2012. Still rather controversial, much discussion to be had – begin at CM28 STEP V 2012 STEP VI 2013

  6. Schedule • Not much to say: • Concept of ‘Straight to Step IV’ was just about accepted at CM28 • That is, Steps II, III and III.1 are deleted on the basis that their scientific goals can be met by an adaption of Step IV • Critically dependent on Spectrometer solenoid delivery • Schedule for above expected by 1st December • Report new top-level schedule to MPB by 15th December

  7. Spectrometer solenoid Update • Rather complex, five stage review of repair plan in progress – quite encouraging though: • 27th October – Preview held – agree review charge, presentations from SS team • 10th November – Reviewers meet and formalise request for any additional information/questions to SS team • 17th November – Response to above from SS team • 26th November – Reviewers conclude • By 1st December – formal closeout • Heat loads are now better understood • Drawings and schedule being made now • SS manpower being reinforced • 5+1 CCRs layout looks likely

  8. Space, people and substation • Space: • Ever more likely that three magnets will arrive at RAL more or less at once in 2011 • MICE has part of R9, but will need much more for parallel pre-integration of AFC/Spectrometer modules – or another building...? • Have registered a request with the various STFC accommodation committees, but little feedback received • Will need help to carry this discussion upwards very soon • People: • Matt Hills and Andy Moss are key to progress with LH2 and RF, but they cannot give enough time for MICE • They need more time in order to delegate more effectively • Simply providing people underneath them to help is only a partial answer

  9. Substation upgrade • Good progress recently: • Tender specification is written • Three potential contractors selected • Does not require OJEU tender action • DL staff fully involved in process - they co-wrote the specification • Timetable: • 26/11/10 – submit tender invitations • 17/12/10 – receive tenders • 14/1/11 – place contract • Q2/3, 2011 – installation period