An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CM Timeline Update IRIS Coordinating Committee August 21, 2006

  2. Background • Original plan based on SAP upgrade and CM 6.0 • Delay of upgrade meant a go-live with version 4.72 resulting in a significant change in development required • Data conversion • Data integrity from SIS • Not one-to-one mapping • Verification • Relative immaturity of product • Few available “experts” or “peers”

  3. Proposed Timeline - Overview • Event Planning (Course scheduling for Fall 2007) – Go Live 12/04/2006 • Other CM Modules – Go Live 02/26/2007 • Recruitment • Admissions • Progression • Booking • Advising Conferences • Equivalency Determination • Fee Calculation • Centralized Billing

  4. Proposed Timeline - Detail • Event Planning (December 2006) • Completed Configuration 08/15/06 • Completed Business Process Procedures 08/16/06 • Data Conv to DEV & Trng; Integr/Scenario Testing 08/25 – 09/15 • Training System Data Conversion 9/15/06 • Authorization Testing 10/30/06 • End-User Training – Start Date 11/06/06 • Conversion to Production 11/27 – 12/03 • Event Planning for Fall 2007 12/04/06 – 2/2007 • Open Labs 1/2007

  5. Proposed Timeline - Detail • Other CM Modules – Go Live February 26,2007 • Complete Configuration 10/01/06 • Business Process Procedures 10/13/06 • Scenario Integration Testing 10/02/06 – 12/15/06 • Conversion to QAS 10/02/06 • Conversion to Training System 01/01/07 • Conversion Benchmarking 11/01/06 – 12/15/06 • Authorization Testing 12/29/06 • End User Training 1/2007 – 2/2007 • Cutover to Production 2/23-2/25/06 (Benchmarking may indicate additional days are needed) • Go Live 02/26/07 • Mid-Term Grades 03/05/07

  6. Change Control Process • Change requests will be formally written and routed to Project Management through David Hardison. • Requests that may impact the timeline will be presented to the business owner (Don Witt). • Requests that are denied may also be appealed to the business owner (Don Witt).

  7. Contingency Plans • Nov 06 Decision on amount of academic history to load (CMU providing comparative data) • Nov 06 Decision about requesting extension of mainframe • Feb 07 Determine if schedule needs to be entered into SIS1 ***Priority Registration windows will be extended to help distribute the load 1 If entry into SIS is required, it will be accomplished through IRIS team

  8. Communication Plan • Aug 22 Steering Committee Meeting • Aug 22 Provost Dean’s Meeting - Phyllis • Aug 23 Meet with Jacquie Hager and Stephen Barnett of Registrar’s Office • Aug 25 Meet with Enrollment Management Areas • Aug 25 Meet with Campus Management Advisory Group • Aug 28 Send out mass email with details of CM Schedule • Ongoing Work with Lana on CM Communication Plan

  9. Phase II (July 2007 – June 2008) • Workflow • Auto email for various student notifications • Waitlist notifications • Grade change/submissions • Student Self-Service • Transcript request/status checking • Document Archiving (Imaging) Project – Student Accounting History • Customer Relationship Management for student recruitment

  10. Discussion