An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PRASA SIGNALLING PROGRAM 2011-2025

  2. 1. Network Resignalling • Period: 2011-2017 in all PRASA regions • Includes: • Prasa Regional CTCs • Bidirectional traffic • Replacing the old technology • It is the foundation for Wireless Signalling and correlated with the introduction of the new Rolling Stock • Deliverables: Resignalling of all three regions (electronic interlockings, axle counters, led signals, system monitoring,)

  3. Assets Protection Program(today – 2014) • Lobby for change of legislation for scrap dealers (one regional dealer for Eskom/Prasa/Gautrain, heavy punishment for asset thieves) • Protect rail land (brick & electric fence, alarms, video) • Code and chip the outside assets starting with copper cables (dot tint, invisible paint)

  4. Optical Fibre Network • Installation period 2012-2014 • Will complete the ring for high reliability communication required in Signalling. • Became the main mean of communication in signalling eliminating the copper cable. • Deliverables: FO rings in each region

  5. Radio Digital Signalling Network • Installation period: 2012-2017 • Replaces the obsolete analogue trunk radio being back-up for communication and later becoming main communication mean for Signalling. • Improve communication to the driver and support data transmission from and to new and oldRolling Stock. • Deliverables: Modern signalling networks in all three regions

  6. Wireless Signalling (MTCS) • Installation period: 2012 – 2020 (include in the RS tender document the signalling requirements) • Increase safety (ATP) and capacity. • Eliminates line-side signalling equipment (when complete fleet replaced)

  7. Semi-Automatic Train Operation • Installation period: 2014-2022 • Automates traffic. • Increase frequency of trains

  8. Virtual block • Installation period 2016-2025 • Distance between trains decreases or increases according with traffic requirements. • Traffic capacity increased up to maximum line potential.