Contract awarded to low bidder EV Williams $25.2 million Contract separated into Three Phases

Route 17 George Washington Highway York County State Project: 6017-099-129,P101, R201, C501, B604 UPC: 60843 Project Status August 20, 2013. Contract awarded to low bidder EV Williams $25.2 million Contract separated into Three Phases Mostly Geographical Limits Each Phase has Three Stages

petula
Download Presentation

Contract awarded to low bidder EV Williams $25.2 million Contract separated into Three Phases

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Route 17 George Washington HighwayYork CountyState Project: 6017-099-129,P101, R201, C501, B604UPC: 60843Project StatusAugust 20, 2013

  2. Contract awarded to low bidder EV Williams • $25.2 million • Contract separated into Three Phases • Mostly Geographical Limits • Each Phase has Three Stages • Notice to Proceed: July 12, 2013 • Completion: December 31, 2016 • Roadway Substantially Complete by 09/30/16

  3. Phase 1: August 2013 to February 2015 Private Utility Relocation Ends Near Bowling Alley Phase 1

  4. Phase 2: February 2015 to December 2015 Ends At Washington Sq. Phase 2

  5. Phase 3: December 2015 to December 2016 Ends At Wolf Trap Rd Phase 3

  6. Each phase has three stages Phase 1 Stage 1 • Add temporary pavement near bridge 2) Shift Traffic to outside and narrow lanes 3) Construct Median and Middle of Bridge August 2013 to February 2014

  7. Each phase has three stages Phase 1 Stage 2 1) Shift SB Traffic to Middle of Bridge 3) NB Traffic 2) Construct SB side of Bridge February 2014 to May 2014

  8. Each phase has three stages Phase 1 Stage 3 1) Shift SB Traffic to Outside on New Bridge 2) Shift NB Traffic to Middle of Bridge 3) Construct NB side of Bridge May 2014 to February 2015

  9. Phases 2 and 3 have three stages Stage 1 2) Place traffic control barrels 1) Add temporary pavement

  10. Phases 2 and 3 have three stages Stage 2 1) Place traffic control barrels 2) Shift traffic toward median Perform construction on the outside lanes

  11. Phases 2 and 3 have three stages Stage 3 1) Place traffic control barrels 3) Perform construction in median 2) Shift traffic toward the outside

  12. Stage 1

  13. Stage 2

  14. Stage 3 Bridge Stage 2 Road

  15. Stage 3 Road