240 likes | 931 Views
Chapter 8: Evaluating and Terminating the Project. 2. Background. Project evaluation Primary purpose
E N D
1. Chapter 8: Evaluating and Terminating the Project 1 Chapter 8 EVALUATION
Evaluating, Auditing, and Terminating the Project
2. Chapter 8: Evaluating and Terminating the Project 2 Background Project evaluation
Primary purpose – feedback to senior management
Progress and performance relative to
project’s initial or revised plan.
Against goals and objectives
set during selection process.
Evaluate at crucial points.
To improve project process
Credible to both mgt and team
3. Chapter 8: Evaluating and Terminating the Project 3 Evaluation Criteria Original criteria
for selecting and funding project
Success to date
Efficiency
Customer satisfaction or impact
Business/Direct Success
Future Potential
Contribution to Organization’s Goals
Contribution to Team Member Objectives
4. Chapter 8: Evaluating and Terminating the Project 4 Measurement Measuring performance against planned budgets and schedules
Straight forward, quantitative
Earned value analysis more complicated
Especially if dividing profits are involved
5. Chapter 8: Evaluating and Terminating the Project 5 PROJECT AUDITING
6. Chapter 8: Evaluating and Terminating the Project 6 The Audit Process Thorough examination of
Management of project
Methodology and procedures
Records
Property, budgets, expenditures, progress
Timing depends on purpose
Early – technical, (P)
Later – budget, schedule
Three Levels
general audit – brief investigation
detailed audit – something needs further flogging
technical audit – special technical
7. Chapter 8: Evaluating and Terminating the Project 7 Steps in Project Audit Familiarize audit team
with requirements of project
Audit project on-site
Write up audit report
Distribute report
8. Chapter 8: Evaluating and Terminating the Project 8 Behavior Aspects Audit team must have free access
to anyone with knowledge of the project
Project team members rarely trust auditors
?Audit team must understand politics of project team
Be senssssseeeetiiiiive BE CONSTRUCTIVE
Information must be confirmed
Don’t use otherwise
Project team should be made aware of in-process audit
No judgmental comments, stick to facts
Do not speak out of turn
9. Chapter 8: Evaluating and Terminating the Project 9 The Audit Report Introduction
description of project goals & objectives
Current Status
Budget, % completed, resources
Future Project Status
conclusions regarding project progress
recommendations for changes
projections
10. Chapter 8: Evaluating and Terminating the Project 10 The Audit Report continued Critical Management Issues
issues senior management should monitor
Risk Analysis and Risk Management
potential for project failure and monetary loss
note alternatives if any
Final Comments
caveats, assumptions, limitations
11. Chapter 8: Evaluating and Terminating the Project 11 PROEJCT TERMINATION
12. Chapter 8: Evaluating and Terminating the Project 12 When to Terminate a Project Sunk Cost Approach
Additional return for current investment
Two Other Criteria
has project met its goals
factors associated with success or failure
13. Chapter 8: Evaluating and Terminating the Project 13
14. Chapter 8: Evaluating and Terminating the Project 14 Types of Project Termination Project Extinction
project activity suddenly stops
either successfully completed or high expectation of failure
Termination-By-Addition
becomes a new formal part of organization
Termination-By-Integration
becomes standard part of operating systems
15. Chapter 8: Evaluating and Terminating the Project 15 Types of Project Termination continued Termination-By-Starvation
a project in name only
16. Chapter 8: Evaluating and Terminating the Project 16 The Termination Process Decision made by broad based committee of senior managers
Termination process should be specified in project plan
Termination manager other than PM
17. Chapter 8: Evaluating and Terminating the Project 17 Figure 8-3 A Termination Project
18. Chapter 8: Evaluating and Terminating the Project 18 The Project Final Report Project Performance
what was achieved and reasons for resulting performance
Administrative Performance
review of how well administrative practices worked
Organizational Structure
identify modifications to help future projects
19. Chapter 8: Evaluating and Terminating the Project 19 The Project Final Report continued Project Management Techniques
recommendations for improvements in future projects