An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Smarter Greener Learning The PSBA co-location facility Stephen Frith PSBA Commercial Manager

  2. Topics • A quick overview of the PSBA programme • Some detail of the PSBA co-location facility that is being developed • Green considerations for data-centres in future and the Welsh Public Sector data-centre strategy • Open questions and conversation

  3. What is PSBA? • Public Sector Broadband Aggregation • A fully cross sector collaborative programme • A physical communication network, shared by the public sector in Wales • An enabler: • Same physical infrastructure • One less barrier to controlled information sharing • Different sector representation in the same room • A new way of working: • Cross sector governance • Cross sector funding model • A Platform for shared services

  4. PSBA services • Current: • Connectivity services • Technical wide area network design support • Filtered internet access • In development: • Telephone services • Video services • Data centre based services • Requested • Enhanced internet filtering • Email filtering • Longer term vision • Cloud computing • Unified communications

  5. The PSBA co-location facility Final commercial arrangements still pending. Subject to satisfactory resolution: • 60 racks • Connected to PSBA Network (so to all public sector offices) • 7.3Kw per rack • n+1 resilient power • n+1 resilience for cooling • Security • Internal secure shell (Modusec by Remtec) • CC TV and 24hr staffed facility • Electronic access control – room and rack • Power usage effectiveness (PUE) target under 1.5 • Free cooler unit (starts to reduce burden at 19˚, free under 7˚) • Hot air containment (full segregation and brush strips and blanking panels) • Settings: inlet temperature 24˚

  6. Hot Aisle Plenum return

  7. External experts • Supplier expertise • Capitoline • Workspace Technologies Ltd

  8. Making it green • Include sustainability in the evaluation criteria • Balance higher cost with lower PUE • Shared by the public sector • Increase utilisation (fill it quickly) • Reduce number of smaller facilities • Re-use of existing building • The balance of power demands, power provided (per rack), cooling technologies and size • The cost per Kw versus number of racks • The balance point is constantly moving

  9. An all Wales public sector strategy • The UK data centre strategy • http://writetoreply.org/govictstrategy/ • 10 to 12 secure, resilient services • Welsh input being developed • PSBA approach • A path to aggregation • 6 to 10 network attached facilities • Virtualised data-centres • Opportunity for further consolidation

  10. Questions

  11. Contact details • www.psba.org.uk • Stephen Frith • 078 9422 9422