1 / 23

Universal Oil and Bag System Design Review

A comprehensive review of the system design for the Universal Oil and Bag System, addressing system goals, project status, engineering requirements, and action items.

Download Presentation

Universal Oil and Bag System Design Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. P16680: AATech Universal Oil and Bag System System Design Review 9/29/15

  2. Team P16680 Philip Couturier - Controls Systems (EE) Samantha Orlando - Systems Design (ME) Jessica Reed - Purchasing (ME) Maria King - Project Lead (ISE) Nicole Anklam - Systems Integration (EE) Bryce Mowers - Manufacturing (ME)

  3. System Design Review Objectives • Confirm that all system goals are addressed in an acceptable manner • Inform stakeholdersof current project status • Update engineering requirements if needed • Review action items for team & customer

  4. Agenda Engineering Analysis Test Plan Risk Assessment Project Plan Lessons Learned Q & A Action Item Recap • Use Scenario • Engineering Requirements • Constraints • Functional Decomposition • Systems Architecture • Benchmarking • Concept Generation & Selection • Cost

  5. Updated Use Scenario

  6. Engineering Requirements

  7. Constraints

  8. Functional Decomposition

  9. System Architecture

  10. Drain apparatus Height of table Door handles Oil lines Benchmarking • Pumps • Sensors • Barcode scanners • Microcontrollers

  11. Morphological Chart

  12. Concept Generation Three Potential Concepts • Manual Concept • Automated Concept • Feasible Automated Concept

  13. Concept Selection Selection Criteria: • Ease of use / Ease of troubleshooting • Ergonomic • Can be completed in two semesters • Durable • Fast cycle time • Size (small preferred) • Organized • Automated • Adaptable

  14. Concept Selection - : Less likely to meet criteria + : More likely to meet criteria s : Equally likely to meet criteria

  15. Final Concept Selection • Combination of best components from each system concept • Different fixture for each model • PLC/HMI display with LED lights • Manual Door Slide with electric door interlock • Locate and secure nozzle using a yoke plate (previous MSD team) • Manual input with a scanner • Electric Centrifugal pump to circulate oil • Internal reservoir to store oil • Gravity flow to return oil to reservoir

  16. Cost Budget: $10,000 • Estimated costs of major components based on benchmarking: • HMI/PLC - $800 • Sensors - $250 • Door Lock - $50 • Pump - $500 • Door handles - $10 • Oil lines - $80 Total: $1,690

  17. Engineering Analysis • How many fixtures are needed/What parts need to change? • Prototype different options • How long will a changeover take? • Prototype a fixture and time a mock changeover • Will the pump provide appropriate pressure and duration? • Benchmark • Which type of door lock ensure safety and eliminate leaking? • Benchmark • Will all of the sensors be compatible with the PLC? • Benchmark

  18. Test Plan • Pump--verify the pressure at different points • Pneumatics--verify cylinder actuation and verify no bleed-off • Pressure sensors--verify they meet specs • Fixturing alignment--verify part fit-up with oil injector • Cycle time--different parts and change-over • Door lock--verify that the door will not open during operation • Noise level--verify less than 50dB • Scanner--verify communication with PLC and pulls up correct parameters • LED and HMI--verify the systems output the correct data at the correct time • User interface--verify intuitive controls • System Control--verify system runs correct parameters and operates as planned

  19. Risk Assessment

  20. Project Plan Gantt Chart thru 9/29 Rest of Project Next 3 weeks

  21. Lessons Learned • Have a method to track risks at a high level • Project schedule may vary from MSD schedule • Have document owners • Practice design review with your guide

  22. Questions?

  23. Action Item Recap • From previous review • Receive oil requirements • Receive copy of software/computer • Receive previous MSD fixture • New action items • Add oil filter? • Add emergency stop?

More Related