Jacob K. Javits Expansion & Renovation • Update August 7, 2011
Renovation Scheduled StatusMay 2013 • Roof • North roof complete • South roof temporary (1st layer) completed • Roof Top HVAC Units • All Replaced and Operational • Curtain Wall/Vestibules • All completed • 3rd Floor Expo • Completed all Partitions removed
Renovation Scheduled StatusMay 2013 • Temporary Logistics • Hoist & sidewalk shed located on south side until south roof is completed • Expo Hall and Crystal Palace cleared of temporary scaffold