Turner Construction Company SLAC LCLS Construction Status
Turner Construction Company • Project Safety • Schedule Review • Tunneling • Purchasing • Critical Issues • Project Information Systems • TCCO Senior Management Support
Turner Construction Company • Safety First • JSA’s and Pre-Task Planning • Establishing the Culture of Safety at SLAC • Safety Training at Orientation • Team Safety: SLAC/TCCO/Subcontractors
Turner Construction Company • Project Schedule • NTP: August 1, 2006 • Start of Construction: September 11, 2006 • Mass Excavation Complete: December 28, 2006 • Tunneling: Nov. 06 to Nov. 07 • Beam Line Complete: Feb. 08 • Closeout Complete: June 08
Turner Construction Company Tunneling • Procurement • Three bidders • Low bidder: Affholder Inc of St Louis – nationally known contractor with excellent safety performance • $1 Million savings achieved during negotiation phase • Methodology • Equipment • Support materials • Status • Submittals • Mobilization • Portal construction
Turner Construction Company Tunneling • Schedule Management • Method • Progress rates • Resources • Sequencing • Cost Management • Geotechnical baseline report • Value engineering • Schedule of values • Issue resolution • Disputes review board
Turner Construction Company • Purchasing • Bid Group 1: Mod Released, Under Contract • Bid Group 2: Recommendations Submitted • Misc. Packages • Scopes Bid with CLOC • Re-bid Packages • Re-Evaluated Packages
Turner Construction Company • Critical Issues • Rainy Season Work • Indoctrination of New Subs to Safety Culture • Tunnel Spoils Traffic Issues & Dewatering • Design Change Impacts to Critical Path
Turner Construction Company • Information Systems • RFI’s • Submittals • Field Change Orders • TurnerTalk Web Based Project Management • Document Scanning
Turner Construction Company • Project Specific Items • SLAC-Turner Team: CFM-UTRs-TCCo-Subs • Turner Oversight Support