An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2008 LTU and Beam Dump Installation Tim Montagne J Langton

  2. Agenda • 2008 LTU and Beam Dump Installation • Subsystem Responsibilities • Installation Objectives • LTU Installation Schedule • Beam Dump Installation Schedule • LTU and Beam Dump System Test Schedule • LTU Installation Documentation • Beam Dump Installation Documentation • Safety

  3. Subsystem Responsibilities • Mike Saleski - Safety Systems • J. Chan - Linac Project Management • K. Ratcliffe - Installation Manager • T. Montagne - LTU Integration Engineering • J Langton – Beam Dump Integration Engineering • P. Rodriguez - Cable Installation • R. Fuller - Controls Checkout

  4. Installation Objectives • Install and align beamline structural supports • Install and align magnets • Install and align diagnostics • Install and verify vacuum system • Install and verify: • Magnet cooling water supply and return • Vacuum pump power and vacuum gauge signal • AC power • Magnet DC power • Diagnostics controls • Pneumatics • Purge Gas • Install and verify safety systems • Radiation Shielding • BCS system • MPS system • PPS system

  5. LTU Installation Schedule - BTH West • BTH west co-occupancy starting 12/2/07 • Alignment network and monumentation 12/20/07-1/08/08 • Stand hole pattern layout 1/09/08 -1/11/08 • Core drill mount holes 1/14/08 -1/28/08 • Stand installation 1/29/08 -2/19/08 • Install racks & cable plant 9/04/07-11/28/07 • Install components 2/20/08-4/01/08

  6. LTU Installation Schedule - BTH • BTH co-occupancy starting 12/05/07 • Alignment network and monumentation 1/09/08-1/23/08 • Stand hole pattern layout 1/24/08 -1/29/08 • Core drill mount holes 1/30/08 -2/12/08 • Stand installation 2/06/08 -3/19/08 • Install racks & cable plant 12/05/07-3/10/08 • Install components 3/20/08-6/12/08

  7. Beam Dump Installation Schedule • Beam dump co-occupancy starting 12/05/07 • Alignment network and monumentation 12/05/07-2/01/08 • Stand hole pattern layout 12/05/07 - 2/01/08 • Core drill mount holes 12/05/07 - 2/01/08 • Stand installation 2/04/08 - 2/15/08 • Install racks & cable plant 2/19/08 - 3/17/08 • Install components 4/21/08 - 6/18/08

  8. LTU and Beam Dump System Test Schedule • LTU system test complete 10/01/08 • Beam dump system test complete 9/18/08

  9. LTU Installation Documentation

  10. LTU Installation Documentation

  11. Beam Dump Installation Documentation • Beam dump installation documentation is complete pending release.

  12. LTU Section 71 Installation

  13. Beam Dump Installation

  14. Safety • The listed documents are required prior to installation and operation • Safety Overview Approval • Work authorization approval from LCLS and AD • Penetration permit • Earthquake approval • Building inspection approval • Electric safety approval • Radiation Physics approval • Non-ionizing approval