E N D
1. GS SQSS Review – Onshore Intermittent:Guidance on Economic Analysis
Paul Plumptre
2 and 4 May 2007
2. Agenda Historic Experience of Constraint Costs
Guidance on Economic Studies
Likely Study Conclusions
3. England & Wales Constraints 2001-2006( Cost in £M) England&Wales Constraint Costs:
Have been in the range £10m to £30m since NETA Go-Live
Costs arise over >10 constraint boundaries in each year
No one constraint boundary causes >25% of the annual cost
In early years, import constraint costs predominate
More recently, we have experienced export constraints
Our investments to reduce Constraints have been efficient
4. Scottish Constraints ‘Cheviot’: constraints across the former Scotland-England interconnector circuits
Mainly export; can be import
c. half thermal : half stability
Half summer under transmission outages; half winter
‘Within-Scotland’: constraints across a number of boundaries within-Scotland
Both export and import
Export constraints mainly under summer transmission outages
Import constraints both summer, and winter under intact transmission
5. Scottish Constraints 2005/6 In 2004, we forecast costs at:
Cheviot: £36.9m
Within-Scotland: £17.0m
Costs have outturned at:
Cheviot: £31.6m (export 30 import 1)
Within-Scotland £28.5m (export 6 import 22)
Constraint Volume & Price
Details are confidential – parties are making significant pricing decisions
Cheviot £30m is 250–500GWh × 60–120 £/MWh constraint price
and 60–120 breaks down 60–140 £/MWh English Offer price minus 0–20 Scottish Bid price
6. Scottish Constraints 2006/7 In 2005, we forecast costs at:
Cheviot: £20.4m
Within-Scotland: £31.0m
Costs are projected to:
Cheviot: £28m (export 27 import 1)
Within-Scotland: £56m (export 30 import 26)
Constraint Volume & Price
Cheviot volume is ¼ up on 2005/6
Cheviot price is ¼ down on 2005/6, mainly due to use of commercial inter-trip services
Within-Scotland, both volume and price are up on 2005/6
7. Scottish Constraints 2007/8 onwards In 2006, we have forecast costs for 2007/8 at:
Cheviot: £36m
Within-Scotland: £40m
We have not yet forecast detailed costs for 2008/9 onwards
Cheviot volume will increase with:
Cheviot re-conductoring outages
Gradual windfarm commissioning
Within-Scotland volumes should ease, subject to gradual Transmission reinforcements
8. 1. Historic Constraints – Conclusions Scottish Constraint volumes and costs are already significant
Costs: Cheviot £30–40m within-Scotland £30–50m
Volumes: Cheviot 300 – 600GWh of export restriction
All export constraint prices have been 40 – 120 £/MWh
Our track record of forecasting constraint costs is good
9. Transmission Reinforcements Justified by security:
To achieve the desired level of (implicit) security, the capability to transmit power across a boundary must be greater than the following level – eg Planned Transfer plus half Interconnection Allowance
This is known as a Deterministic rule
Justified by economics:
To provide sufficient capacity to facilitate year-round market operation against reasonably foreseeable conditions of generation
Relative to the base case of ‘Do Nothing’, a proposed reinforcement must be shown to deliver a cost-benefit
Thus the investment cost of the reinforcement is less than the reduction in operating costs (transmission constraints, maybe transmission losses) expected over the lifetime of the reinforcement
This is often termed a Probabilistic rule
It is a given that both approaches will still be included in SQSS
10. Guidance on Economic Study (1) What reinforcements to consider?
In theory, a very large number of conceivable reinforcements
In practice, engineering judgment leads to a limited number of options, which are distinct in terms of investment cost and boundary capability
What years to assess?
In theory, should consider all <25> years of an asset life
In practice, it is hard enough (see below) to assess operating costs for even one planning year. The uncertainties of demand, generation presence, running, and pricing swamp the analysis even 10 years out.
Proposed Guidance: in majority of cases, it suffices to consider one year, 3-5 years into the future. If the reduction in mean Constraint costs > 20% of the Investment capital cost, then the reinforcement is economically justified.
11. Guidance on Economic Study (2) Study Tool:
Spreadsheet or Optimising DC Load Flow or AC Load Flow
No Guidance (spreadsheet often suffices)
Representation of Demand:
10 or 100 or 8760 demand levels - No guidance
Should consider at least: Winter Intact; Summer Intact; Summer Outage
Representation of Generation:
Deterministic – inadequate to represent range of unconstrained flows
Combinatoric (all cases by genset) – only possible up to ~6 gensets
Probabilistic – almost always necessary
Operating Costs
Usually Constraints only suffices
Additionally assess Transmission Losses, if methods permit
12. Guidance on Economic Study (3) Number of weeks per summer of circuit outage
In the main, assume 2 weeks per circuit per year, indefinitely
Boundary Capabilities, without / with reinforcement: winter, summer_intact, summer_outage
Either: direct from load-flow model (but stability limit still off-line)
Or: off-line from a generic seasonal load-flow (there may be different boundary limits for different circuit outages)
Assume zero unplanned transmission outages
Assume good operation by TO and SO
Ie optimised substation running arrangements and Quad Booster settings
Degree of usage of inter-trips, and price thereof, on case-by-case basis
13. Guidance on Economic Study (4) Degree of co-ordination of Generator and Transmission outages
Assume none – eg outages taken independently over the summer
Generator Availabilities: winter, summer: as per history
Will need care on degree of independence of distributed windfarms
Generator Running:
Central case: Assume a fairly neutral, national ranking of fuel-types
Sensitivity case of increased running of mid-merit generation in an export group; and decreased running of mid-merit generation in import group
Generator Pricing:
Central case: Assume a fairly neutral, national pricing, as per history
Sensitivity case of more aggressive pricing, on both export and import side
14. 2. Economic Guidance – Conclusions Large number of data assumptions
Easy for two practitioners to disagree by ±50% on (at least):
Generation / Transmission outage co-ordination
Generation Running
Generation Pricing
Hence cost-benefit (‘economic’) approach too variable to form the central case for most transmission reinforcements
We are looking for guidance, for cost-benefit studies to support a main deterministic (‘security’) rule for transmission planning
Consultation Question:
Do you support my indicative points of guidance above?
15. A Generic Constraint Analysis Suppose:
Transmission Reinforcement costs 30 £/MW.km for a 200km boundary = £6,000 per MW = 6 £/kW
Constraint price is 60 £/MWh
Then the cost-benefit break-even point = 6 £/kW ÷ 60 £/MWh = 100 hours = 1% of a year
Thus Constraint assessments are very much looking at the tails of the distribution of Operating conditions
16. Another Generic Constraint Analysis - Theory Assumes Cost of Reinforcement = 6 £/kW
Cost of Constraints = 1MW (per MW below 3000) × 0.5hr (per MW below 3000MW) × 60 £/MWh
Theoretical break-even point ~ 2900MW of boundary capacity
17. Another Generic Constraint Analysis - Practice In practice:
‘Do Nothing’ Option 0 has 2500MW capability – Cost £25-75m
Reinforcement Option 1 delivers 3300MW capability – Cost £15-30m
Is this sufficiently certain to justify reinforcement?
18. Working Group: Economic Studies We are building an elementary model, to assess constraint costs by boundary for the WG scenarios
Expected Conclusions:
Provided the security criterion provided boundary capability at least at (current) Planned Transfer, Constraints will not predominate (eg > 1000 hrs pa)
Constraint assessments are very sensitive, at the tail of the distribution of operating conditions
Scottish Constraint assessments are particularly sensitive to assumptions on the running of mid-merit and low-merit generation
19. Summary Historic Experience of Constraint Costs
Guidance on Economic Studies
Likely Study Conclusions