PMI North Area PMP Exam Study Group

PMI North Area PMP Exam Study Group . Risk Presentation Prepared by Denise Robertson 15 March 2003. Risk Management Processes. Process I/O and Tools/Techniques emphasized on exam, so memorize them Memorize process in order: Risk Management Planning Risk Identification

morrie
Download Presentation

PMI North Area PMP Exam Study Group

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PMI North Area PMP Exam Study Group Risk Presentation Prepared by Denise Robertson 15 March 2003 Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials

  2. Risk Management Processes • Process I/O and Tools/Techniques emphasized on exam, so memorize them • Memorize process in order: • Risk Management Planning • Risk Identification • Qualitative Analysis • Quantitative Analysis • Risk Response Planning • Risk Monitoring and Control Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials

  3. Risk Concepts • Risk tolerance • Risk adverse • Risk factors • Probability • Impact • Range of possible outcomes • Expected timing in project life cycle Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials

  4. Unknowns • Risks are also called “Unknowns” • “Known Unknowns” are identified during Risk Management and are documented in the project plan • Can be planned for with Risk Response • “Unknown Unknowns” are unanticipated risks • Cannot be planned for in advance Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials

  5. Policy Level • Organization’s Risk Management Policy on how to approach risk is now part of PMBOK • Policy describes: • Level of tolerance • Level of acceptable risk Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials

  6. Project Status • 3 possible statuses: • In Jeopardy • Committed to • Approved Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials

  7. Risk Probability/Impact Matrix • 2-D rating system that rates: • Likelihood (probability) of a risk occurring between 0.0 and 1.0 or 100% certainty • Impact of risk should it occur • Impact scale can be • Ordinal (ordered) • Cardinal (assigned numeric values) • Risk Score = Probability * Impact Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials

  8. Evaluating Project Data for Use in Assessing Risk • Assumption Testing Criteria: • Stability of assumption • Impact to project if assumption proves false • Data Precision Ranking Accuracy Dependencies: • Extent risk is understood • Data available about risk • Quality of data • Reliability and integrity of data Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials

  9. Monte Carlo Simulation • Used in Quantitative Risk Analysis and Cost Analysis • Evaluates the project, not the tasks, however: • Provides probability of completing project on any specific day or for any specific task • Provides probability of any task actually being on the critical path • Provides percent probability that each task will be on critical path • Takes into account path convergence • Translates uncertainties into impacts to total project • Can be used to assess cost and schedule impacts • Results in probability distribution Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials

  10. Decision Tree Analysis • Quantitative Analysis Tool • Diagram describes decision and probabilities associated with choices • Determines aggressive or conservative route to highest Expected Monetary Value (EMV) • Total of Probabilities * Consequences for a Choice Event = EMV Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials

  11. Cost Reserve • PMI recommends at least 10% OR • Based on EMV: • Total of Probability * Risk Cost for all risks • Remember risk can be negative or positive Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials

  12. Risk Response Techniques Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials

  13. Residual and Secondary Risks • Outputs from Risk Response Planning • Residual Risks are those that remain after Avoidance, Transference, and Mitigation have been taken. • Secondary Risks arise as a direct result of implementing a risk response • Secondary risks should be identified and responses planned Information derived or quoted from from PMI, Mulcahy, and Look Glass Development's PMP Exam Prep Materials