1 / 7

PMI PMP Real Exam Questions

Test4Direct is furnishing you with the PMI PMP confirmed PDF question and answers. Preparing yourself for the PMI PMP exam enables you to pass your exam in first strive. You can save your effort, time and money because Test4Direct is providing you PDF question and answers which totally simulates with the actual PMP Project Management Professional exam. Test4Direct provide you 90 days free updates related to the PMI PMP exam. We are also Providing you the free demo of PMP exam product and highly recommend you to download free demo before purchasing the PMI PMP product. To view the details of money back guarantee policy and discount offers please visit the http://www.test4direct.com/PMP.html

Download Presentation

PMI PMP Real Exam Questions

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PMI PMP Project Management Professional Demo Product To Buy Full Set of Exam Questions, Visit: http://www.test4direct.com/PMP.html

  2. Version: 40.0 Question: 1 An element of the project scope statement is: A. Acceptance criteria. B. A stakeholder list. C. A summary budget, D. High-level risks. Answer: A Question: 2 Which document describes the necessary information to determine if a project is worth the required investment? A. Cost baseline B. Service level agreement C. Memorandum of understanding D. Business case Answer: D Question: 3 Which input to the Plan Risk Management process provides information on high-level risks? A. Project charter B. Enterprise environmental factors C. Stakeholder register D. Organizational process assets Answer: A Question: 4 Which item is an example of personnel assessment? A. Resource calendar B. Tight matrix C. Team-building activity

  3. D. Focus group Answer: D Question: 5 Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project? A. Feedback analysis B. Stakeholder analysis C. Communication management plan D. Stakeholder management plan Answer: D Question: 6 Which input to the Identify Stakeholders process provides information about internal or external parties related to the project? A. Procurement documents B. Communications plan C. Project charter D. Stakeholder register Answer: C Question: 7 The Identify Stakeholders process is found in which Process Group? A. Initiating B. Monitoring and Controlling C. Planning D. Executing Answer: A Question: 8 An input to Develop Project Charter is a/an: A. Business case. B. Activity list. C. Project management plan. D. Cost forecast.

  4. Answer: A Question: 9 Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project? A. Project Risk Management B. Project Human Resource Management C. Project Scope Management D. Project Stakeholder Management Answer: D Question: 10 Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements? A. Stakeholder register B. Scope management plan C. Stakeholder management plan D. Project charter Answer: A Question: 11 In which Knowledge Area is the project charter developed? A. Project Cost Management B. Project Scope Management C. Project Time Management D. Project Integration Management Answer: D Question: 12 The ability to influence cost is greatest during which stages of the project? A. Early B. Middle C. Late D. Completion Answer: A

  5. Question: 13 Which process involves developing an approximation of the monetary resources needed to complete project activities? A. Estimate Costs B. Control Costs C. Determine Budget D. Plan Cost Management Answer: A Question: 14 Which tool or technique is used in the Develop Project Management Plan process? A. Pareto diagram B. Performance reporting C. SWOT analysis D. Expert judgment Answer: D Question: 15 The organization's perceived balance between risk taking and risk avoidance is reflected in the risk: A. Responses B. Appetite C. Tolerance D. Attitude Answer: A Question: 16 An output of the Manage Stakeholder Engagement process is: A. change requests B. enterprise environmental factors C. the stakeholder management plan D. the change log Answer: A Question: 17 Which process numerically analyzes the effect of identified risks on overall project objectives?

  6. A. Plan Risk Management B. Plan Risk Responses C. Perform Quantitative Risk Analysis D. Perform Qualitative Risk Analysis Answer: C Question: 18 Which Collect Requirements output links the product requirements to the deliverables that satisfy them? A. Requirements documentation B. Requirements traceability matrix C. Project management plan updates D. Project documents updates Answer: B Question: 19 A temporary endeavor that creates a unique product or service is called a: A. Project B. Plan C. Program D. Portfolio Answer: A Question: 20 The process of prioritizing risks for further analysis or action is known as: A. Plan Risk Management. B. Plan Risk Responses. C. Perform Qualitative Risk Analysis. D. Perform Quantitative Risk Analysis. Answer: C

  7. THANKS FOR TRYING THE DEMO OF OUR PRODUCT Visit Our Site to Purchase the Full Set of Actual PMP Exam Questions With Answers. http://www.test4direct.com/PMP.html We Also Provide Practice Exam Software That Simulates Real Exam Environment And Has Many Self-Assessment Features. Download Free Product Demo From: http://www.test4direct.com/PMP.html Money Back Guarantee Check Out Our Customer Testimonials

More Related