Lab5 Production Status: Optics and RBX integration

Lab5 Production Status: Optics and RBX integration. Pawel de Barbaro U. of Rochester. Optics Production completed. All megatiles for L01-L16 have been produced, passed QC, sent to CERN PPP reworks (L01-L03, L15, L09, L16, L00) completed We have completed production of L00, HB- megatiles

morela
Download Presentation

Lab5 Production Status: Optics and RBX integration

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lab5 Production Status: Optics and RBX integration Pawel de Barbaro U. of Rochester

  2. Optics Production completed • All megatiles for L01-L16 have been produced, passed QC, sent to CERN • PPP reworks (L01-L03, L15, L09, L16, L00) completed • We have completed production of L00, HB- megatiles • W16 tests completed, rework under way

  3. W16 and HB- rework, details • Damaged W16 megatiles + 8 additional megatiles (rejected during insertion into HB-) have been inspected • Only two W16 megatiles (L15_s1, L15_s4) need to be repaired, work under way • Will be shipped back to CERN early January 2002

  4. Remaining Optics jobs • HE ODU testing using UIC scanner • HO ODU building+ polishing+ QC • L00 pigtail scanning, assembly (HB+) • UV mirror protection (for HO WLS fibers) • QC HE pins, screws • Optical Cables for HB, PPP and B186

  5. Time estimates for Optics • Best estimate for completion of all optics jobs: 70 man-weeks • With 7 techs in lab5, the goal date is end of February 2002. • Large fraction of optics job is QC of ODU ‘cables’ (15 m-weeks) and building of HB cables (32 m-weeks)

  6. RBX integration:short term goals • two HB RBXes (with QIE electronics and magnets to mimic 0.4Tesla field for test beam • HE RBXes with d0 electronics, for testing of megatiles will only be needed in late Sept 02 • still waiting for a confirmation of the installation schedule for HE from Lucien (Apr - Aug 02 ?) • ODUs for HO (20deg) to be installed inside HB RBX shells

  7. RBX integration: long term plans • Collect all inventory of parts for RBX assembly by later March 02 • Mississippi: RBX shells • Notre Dame: ODUs, RM mechanics 3. FSU: calibration boxes 4. Minnesota: HPDs (+testing, + mounting) • Lab5 (UR, FNAL): HV, LV 6. FNAL: electronics elements available Mar-02

  8. 1. Mississippi: RBX shells • First HB RBX shell machined, sent to FNAL for verification • Full production approved week ago, will begin this week (Dec-17-2001) • Complete full HB production (40 shells) by the end of February 2002 (est. as of Dec 15, 2001) • Need to approve design of HE RBX shell in December in order to allow for the full production of HE RBX shells • Plan to complete HE RBX shells by Apr ‘02

  9. 2. Notre Dame: ODUs • Most of the 40 HB ODUs produced • Quality control: in process, typical RMS at the level of 3%, some ODUs need to be re-made • HE ODU prototype work started

  10. 3. FSU: CalBoxes • Lab5 is making all internal PS cables needed for HB, HE and HO CalBoxes • New design of CalBox (4channels) will be evaluated at FNAL/CERN (HB+ tests in B186) • We do not want to make external calibration cables yet (need to verify lengths, routing scheme, at some point we have thought of 0.83mm cables)

  11. 4. Minnesota: HPDs • DEP to start delivering HPDs to U. Minn. In Oct ’01 • Finish delivery for HB in June ’02 • Need 8 HPDs in early ‘02 (February) for integration/testing in lab5 • Delivery to Lab5 for HB production in early March ‘02

  12. HPD details • 484 HPDs with HV filter and connector, mounted in custom alignment ring • 530 Interface carts (HPD to QIE) • 480 ODU cookies and cookie alignment mount • HPD delivery to FNAL: • First 10 at Feb 15 '02, last Dec 1 '03 • Interface Carts to FNAL: • Unsolved problem: We need HPD to QIE routing for HB before Jan 1 for TB 02 • Cookies and mounts to ND: HB is complete

  13. 5. Lab5 (UR/FNAL): HV • Presently finalizing design for HV systems • First prototypes being built using Lab5 personnel (Jaska, Sasha) • Begin production in sometime in Feb-Mar ’02, depending on the load of Optics work • Parts being ordered for HB and HE right now

  14. 6. Electronics • Production chips coming in May/June 02 • Testing of chips in June/July • Testing of cards in October • Assembly of RMs: October onward

  15. Lab 5 Manpower plans

  16. jobs between completion of the Optics task and the arrival of Electronics parts • HV units for HB and HE (40+40) • HV distributors for HB + HE boxes • Assembly of HB readout boxes, including pressure tests (need input from Dan K.) • VCSEL assembly (need input from Julie W.) • Note HO RBX parts only defined in Aug/Sept 02

  17. Lab5 Personnel • Keep 7 techs until Optics is fully completed, target date end of Feb-02 • Reduce to 5 Rochester people in Mar-02 • Todd working only on ‘hourly’ bases for RBX procurement tasks • Ewa on 30-50% load until Optics ends