110 likes | 220 Views
PS - SPS days 18th January 2006. SPS Activities & Hardware Commissioning. Table of content. Short summary main activities 2005 Planning review : Remaining site activities Hardware tests Start up organisation SPS team Some pictures Final words…. Completed activities 2005. Magnets
E N D
PS - SPS days18th January 2006 SPS Activities & Hardware Commissioning Nicolas GILBERT (AB-ABP)
Table of content • Short summary main activities 2005 • Planning review : • Remaining site activities • Hardware tests • Start up organisation SPS team • Some pictures • Final words… Nicolas GILBERT (AB-ABP)
Completed activities 2005 • Magnets • Replacement quadrupole jacks (ring magnets) • Beam transfer • LSS4 : replacement MSE protection element (TPSG4 beam diluter) • LSS6 : major upgrade extraction channel (fast extraction to LHC), including new septa protection (TPSG6) and 4 MKEs • New bumper configuration in LSS6 • New transfer line configuration for TI2 (+ old T1 removed) • Beam instrumentation (mainly SPS points 4, 5 and 6) • New BIPMH in LSS5 • Instrumentation moves (BSHV, BPSM, BRCV, …) • Removal all BI monitors in TT60 (obsolete slow extraction to West Area) Nicolas GILBERT (AB-ABP)
Completed activities 2005 • RF : Upgrade of SPS damper in LSS2 • Experiment :Removal of the 2 Roman Pots in LSS5(LHC experiment TOTEM) • Civil Engineering : Vault repair in LSS3(lots of contributions !) • Support • AT/VAC : frequent interventions (beam line configurations, access, removal TAL 11431, …) • SC/RP : control during access to tunnel • TS/SU : general check alignments, altimetry, … • TS/CV : various interventions on cooling networks & ventilation ducts • TS/EL : change of irradiated cables in LSS6, as well as in TDC2 including removal of PVC cables • TS/IC – HM : involved in all transport issues Nicolas GILBERT (AB-ABP)
patrols SPS planning Nicolas GILBERT (AB-ABP)
Start up organisation • Weekly SPS coordination meetings from January • Short daily coordination meeting once SPS access restricted (from feb.) with directly concerned people • Regular SPS planning update, available under Web/EDMS • Major update of SPS drawings (more than 250 updated layout drawings up to now by TS/MME) available soon in CDD Nicolas GILBERT (AB-ABP)
Some pictures … • TIDVG : upgraded version to be installed in LSS1 Nicolas GILBERT (AB-ABP)
Some pictures … • The Roman Pot set- up during test beam in the SPS in summer 2004 • Now removed from ECX5 Nicolas GILBERT (AB-ABP)
Some pictures … TPSG4 TPSG6/MST (July 2005) • SPS Extraction line TPSG6/MST (Jan 2006) Nicolas GILBERT (AB-ABP)
Some pictures … • MOPOS consolidation : Passive RC component in original adapter replaced by PCB • About 250 adaptors (=125 MOPOS) to be replaced early 2006 Nicolas GILBERT (AB-ABP)
Final words… • Useful info : • BT & BI contribution to SLI project see EDMS 624554 • MOPOS activities see EDMS 679896 • LSS3 vault repair see EDMS 675246 • SPS detailed planning see EDMS 476624 • Specials Thanks to : • Alan Spinks (SPS technical coordination) • Jose Monteiro (SPS planning) • SPS team (AB & AT divisions) Nicolas GILBERT (AB-ABP)