The New Fairfield Free Public Library Renovation Project 2012 focuses on upgrading facilities to meet ADA compliance, including elevator installation, wider staircases, electronic doors, and improved lighting. Proposed alterations aim to enhance access, renovate bathrooms, program rooms, and community spaces. The estimated cost for Phase 1 is $565,000 and Phase 2 is $390,000, with funding sources including library funds, town capital fund, grants, and donations.
E N D
NEW FAIRFIELD FREE PUBLIC LIBRARY Renovation Project2012 1
Renovations • Elevator • Doors • Bathrooms • Lighting • Air Conditioner • Program Room • Community Room
Improve AccessTo Meet ADA Compliance Easy Open Electronic Doors Elevator For Access To Both Floors Wider Staircases Updated Bathrooms 5
c Current Narrow Staircase • Width-33” (Fire code- min 36”) • Railing HT-33” (ADA 34-38”) • Railings required on both sides of staircase 7
Air Conditioning • Bring system up to code • Replace system for energy efficiency
Air Conditioner/ Chiller 36 Years Old 10
Renovate Program Room • Provide storage for chairs & tables • Remove or enclose furnace unit • Install cabinets to house program resources & supplies • Install sink for easier access & clean-up • Replace secondary door with window • Add additional outlets for equipment
Other Renovations • Add suspended ceiling to office & workroom on main level • Improve insulation levels in workroom & Community Room
Estimated Costs Phase 1 $565,000 Phase 2 $390,00
Suggested Funding • Library Funds $390,000 • Funds from town capital fund • Possible grants • Donations