An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cockcroft-Walton Status Carlo Bemporad Angela Papa Giovanni Signorelli Peter-Raymond Kettle MEG Review February 2007

  2. Overview • Machine Production Status & Schedule • C-W Area + Beam Line Status & Schedule • Integration into Beam Schedule 2007 MEG Review February 2007

  3. Machine Status • original Completion Date: • ~ mid-May 2007 • NEW Completion Date: • ~ end-February & expected • Ready for testing mid-April ~ 2007 MEG C-W. Status End 2006 MEG Review February 2007

  4. Components Section Target Support C-W • LiF Target holder + • vacuum chamber • Bellows System with stroke of ~ 2.2m drives COBRA Insertion System to place target at centre of COBRA Magnet • Quadrupole Doublet • x-, y-Steering Magnets • beam Shutter + Slits Beam Line Components Bellows Section • Bellows system Tested ready for shipment • Beam Elements available • Power Supplies available • Beam Diagnostic Elements • ( shutter, diaphragms, x-, y-slits, quartz crystal+TV-camera) • available or almost ready MEG Review February 2007

  5. Machine Schedule • Completion of manufacture ~ end-February 2007 • Acceptance Tests in Amersfoort NL (or PSI) • with HVEE, INFN, PSI ~ mid-April 2007 ? • Shipment to PSI ~ end-April ? • Machine Installation + • Shipment/Guarantee Test ~ mid-April to mid-May 2007 MEG Review February 2007

  6. Cockcroft-Walton Area • C-W AREA: • Area presented Nov. 2006 at • Coordination Committee Research • Area West • Officially in Shutdown Programme • area & infrastructure planned be • installed by the end of Shutdown • beam-axis extension survey end 2006 • infrastructure groups + Health Physics • notified – need Ministry of Health • clearance for the new area + C-W • M3 shielding to be removed now to • check space • more detailed meetings still needed to • finalize all points (Interlock system) MEG Review February 2007

  7. Constraints • Safety System + • Electrical Infrastructure • unaltered • Permanent Access from • outside E5 Shielding Wall needs modifying Approx. form C-W Area M3 Shielding Must be MODIFIED Cockcroft-Walton Area cont. E5 Zone MEG Review February 2007

  8. C-W Area Layout Virtually all Standard Concrete Blocks Still Problematic MEG Review February 2007

  9. C-W Area Shielding • Planned Work needed for Completion • (By mid-April) • removal of walls + measure & • layout check - freeze design • order special shielding + start • standard shielding construction • infrastructure completion: • water, compressed-air, power • Safety systems completion (Interlock) • Ministry of Health Approval • test of Safety System (Beg. April) MEG Review February 2007

  10. Testing & Integration into Beam Schedule • Full test with LiF-target only possible when: • area + safety aspects completed • C-W beam line components magnets, vacuum chambers etc. at PSI • C-W Bellows System at PSI (will arrive soon storage arranged) • target prepared • CONSTRAINTS: • cannot be tested in parallel with Beam Commissioning • bellows system cannot be placed in zone DC insertion system needed • C-W Bellows System cannot be in place during any DS Insertion • TCs or DCs or End-Cap installation/removal !!! • Proposed Commissioning mid-April – mid-June •  SEE Proposed Beam Schedule 2007 MEG Review February 2007